Resolved
RESOLVED that the contract for the Phase 1 works at Meadow Vale Primary School be awarded to the preferred supplier, subject to the final lump sum not exceeding the amount set out in section 1.4 of the confidential appendix.
Executive decided this item on Tuesday 18 October 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contract for the Phase 1 works at Meadow Vale Primary School be awarded to the preferred supplier, subject to the final lump sum not exceeding the amount set out in section 1.4 of the confidential appendix.
3.1The value of these contracts constitutes a Key Decision and under the Council’s Contract Regulations, Executive approval is required.
4 ALTERNATIVE OPTIONS CONSIDERED 4.1 A masterplan and options appraisal has been undertaken for the school which have been subject to consultation and agreement with the Headteacher and Governing Body.
4.2Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5 SUPPORTING INFORMATION Background
5.1In July 2008 the Executive approved the Primary Capital Strategy for Change (PCSfC) for Bracknell Forest, which secured £8.378m of government funding through the Primary Capital Programme (PCP) grant for the first 3 years of works. Meadow Vale School is included within that programme.
5.2The PCSfC was intended to be an ambitious programme of school transformation works over a 15 year period, however following cancellation of further PCP grant by the coalition government this programme has been reviewed and significantly scaled down to address only the essential works required to meet the Council’s statutory duty to provide sufficient pupil places. The programme now includes six schools, and due to the phasing of the works, where further classes are built each year to accommodate the additional pupils as they move through the school from Reception to Year 6, is expected to complete by 2017. Meadow Vale Primary School
5.3In February 2010 the Executive agreed the expansion of Meadow Vale Primary School by one form of entry from 2FE (420 places) up to 3FE (630 places), to meet rising school rolls across North Bracknell.
5.4This work is being implemented in phases over three years to keep pace with pupil numbers in the school as they move up from the intake (Reception) year through to Year 6.
5.5Phase 1 will provide three additional classrooms for key stage one. Providing accommodation for 90 new pupils. Planning permission is currently being considered and should be determined prior to formal contract award. The additional pupil places are required for the start of the academic year in September 2012, consequently works are programmed for completion in April 2012 for occupation in September 2012.
5.6These works were procured by competitive tender following advertisement on the South East Business Portal. The tender return sums can be found in table one of the confidential appendix. They will be let under a JCT Design and Build contract up to the maximum contract value set out in section 1.4 in the confidential appendix.
5.7The contractor has been selected on the basis of best value for money through the Council’s established tender evaluation process. The tender returns have been evaluated 40% quality and 60% price. The evaluation score summaries can be found in table two of the confidential appendix with further details available in the EC Harris tender evaluation report.
Costs and Funding
5.8Most of the PCSfC is funded from government grants, in particular the PCP and its replacement, the Basic Need Grant of which the Council received £3.161m of funding in 2011-12. Further contributions have also been secured through the Council’s own Capital Programme and Section 106 agreements. At this stage, there is sufficient uncommitted funding to meet the cost of this contract.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Education Capital Programme: Award of Contract for Meadow Vale Primary SchoolReport | 31 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.