RESOLVED that 1 The outturn capital expenditure and in particular the key variances identified in paragraph 5.5 of the report be noted. 2 The carry forward of £27.951m from the 2014/15 capital programme to 2015/16 including £1.300m relating to projects approved in 2013/14 be approved (see paragraph 5.6). 3 The financing of capital expenditure as shown in Table 2 to the report be noted. 4 Amendments to the 2015/16 Schools Programme as agreed by the Education Capital Programme Board, outlined in Annex F to the report be approved.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
a) Notes the outturn capital expenditure and in particular the key variances identified in paragraph 5.5. b) Approves the carry forward of £27.951m from the 2014/15 capital programme to 2015/16 including £1.300m relating to projects approved in 2013/14 (see paragraph 5.6). c) Notes the financing of capital expenditure as shown in Table 2. d) To approve amendments to the 2015/16 Schools Programme as agreed by the Education Capital Programme Board, outlined in Annex F
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme for 2014/15 consisted of £53.806m on projects and programmes. The projected outturn is £25.436m (47% of approved budget) which is broadly consistent with performance in previous years. These figures remain subject to change, pending external audit. However, no significant movement is anticipated. The capital programme is monitored on a monthly basis by officers and reported formally to the Corporate Management Team on a quarterly basis and through to Members in the Quarterly Service Reports.
5.2The published capital budget is based on scheme approvals and does not reflect the anticipated cash flow. Cash budgets are also monitored against to reflect the spend profile of the capital works. The actual spend is 98% of the cash budget (£25.855m) and highlights the importance of setting cash budgets as well as scheme approvals. Many of the capital schemes are both technically and logistically complex to implement. Issues such as planning approvals, land transfers and inclement weather can all lead to unavoidable delays. In addition, their financial scale requires a lengthy Unrestricted
tender process to ensure that best value is obtained prior to letting the works contract. It is therefore extremely difficult to complete such schemes within the financial year in which they are approved. Cash budgets are therefore a more accurate way of monitoring spend and performance.
5.3Table 1 summarises the outturn position for schemes managed by Service Departments based on latest information available. The detailed monitoring sheets are provided at Annexes A-D. Table 1: Capital outturn for each Service
Annex Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 A Adult Social Care, Health 4,548.1 2,409.3 1,856.1 -282.7 & Housing B Children, Young People & 22,224.9 10,714.7 11,510.2 0.0 Learning C Council Wide 10,310.3 4,097.3 6,203.8 -9.2 C Corporate Services 888.2 330.9 566.4 9.1 D Environment, Culture & 15,834.5 7,884.3 7,814.8 -135.4 Communities Total Capital Programme 53,806.0 25,436.5 27,951.3 -418.2 % spent 47%
5.4The total carry forwards requested by service departments amount to £27.951m and have been reflected in the cash budgets mentioned above. Many of the projects are either close to being completed or are contractually committed and underway.
5.5According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget and there have been some significant variances which are required to be drawn to the attention of Members (>£25,000). The key budget variances are detailed below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.