RESOLVED that i. the outturn capital expenditure is noted. ii. the carry forward of £24.225m from the 2018/19 capital programme to 2019/20 is approved. iii. the financing of capital expenditure as shown in Table 3 of the Director: Finances report is noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1At its meeting on 28th February 2018, the Council approved a capital programme for 2018/19-2020/21. This report updates the Executive on the capital outturn expenditure position for 2018/19 and requests approval for the carry forward of the remaining capital programme, the majority of which is committed but not yet spent. The report also sets out how the 2018/19 expenditure is to be financed.
Recommendations
2.1That the Executive:
a) Notes the outturn capital expenditure b) Approves the carry forward of £24.225m from the 2018/19 capital programme to 2019/20 c) Notes the financing of capital expenditure as shown in Table 3.
Reasons for recommendations
3.1The reasons for the recommendations are set out in section 5 below.
Alternative options considered
4.1Not Applicable
5 SUPPORTING INFORMATION
Outturn Capital Expenditure 5.1 The capital programme for 2018/19 consisted of £95.688m on projects and programmes. The projected outturn is £63.475m (66% of approved budget). These figures remain subject to change, pending external audit. However, no significant movement is anticipated.
5.2Table 1 summarises the outturn position for schemes managed by Service Departments – detailed scheme information is provided in Annex A-C. Table 1: Capital outturn for each Service
Service Approved Estimated Carry (Under) budget Outturn forward /Over spend £’000 £’000 £’000 £’000 Central Departments 12,571 6,393 6,102 (76) Delivery 51,311 40,507 6,326 (4,463) People 31,806 16,575 17,797 (3,444) Total Capital Programme 95,688 63,475 24,225 (7,983) % spent 66% 5.3 According to Financial Regulations, departments are required to manage their budgets to ensure that the overall department capital programme is not exceeded. As can be seen above the overall capital programme is underspent against budget. However, there are a number of individual variances which are required to be drawn to the attention of Members (>£25,000). The most significant areas of underspends are;
Binfield Learning Village (£2.3m) – The project was robustly managed throughout the process and the scheme was brought in under budget as a result of re-engineering and holding the contractor to timescales and cost projections.
Downshire Homes (£1.2m) – The Downshire Homes Board has concluded that their property portfolio is now at an optimum number and have decided to curtail future property purchases at this time – as such the balance of the available outstanding loan is no longer required.
Commercial Property Investment Strategy (£3.1m) – The Strategy has met its goal of delivering £3m of additional annual revenue income and no further investments are being considered.
Civic Accommodation (£1.1m) – This project is nearing completion and a large part of the remaining budget is no longer required.
5.4The total carry forwards requested by service departments amount to £24.225m. Many of the projects are either close to being completed or are contractually committed and underway.
5.5The most significant carry-forwards that have been funded from Council resources (as compared with grant funding which is normally automatically carried forward) are as follows:
Replacement LED Street Lights (£1.7m) – This is a continuing project and was agreed as an Invest-to-Save project whereby the costs of the programme will be repaid over the life of the assets being replaced and upgraded. Work is now progressing onto subway lighting throughout the borough
Bracknell Sports and Leisure Centre – ITS (£0.8m) – This is a continuing project whereby an improvement programme is funded by the Council, the costs of which will be recovered in a higher management fee.
Civic Accommodation (£0.6m) – There are outstanding works to the toilet facilities to Time Square to accommodate the significant addition in staff within the building and a budget to fund a few remaining team moves into Time Square
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.