Approved the incorporation of additional capital to the Bristol Beacon Transformation Project of £25m from Bristol City Council’s own capital programme and resources funded by Prudential Borrowing (proposed to be released from capital programme contingency) with a total project cost of £131.9m. BCC total contribution will be £83.9m. 2. Authorised the Executive Director for Growth & Regeneration in consultation with Cabinet Member Finance, Governance and Performance, Section 151 officer and the Monitoring officer to take all steps required to enter into any contracts required and negotiate and agree any changes to existing contract terms (including those above a value of £500k) to give effect to the above including; a. Enter contracts for professional services required to complete the construction and renovation project b. Amend the construction contract and issue appropriate instructions and notifications 3. To acknowledge that the project has changed fundamentally from its initial business case and that the future operation must set out to provide a revenue stream to Bristol city council to reflect the substantial investment in the asset. As a step towards that, authorise the Executive Director Growth and Regeneration to take all steps required to negotiate changes to the Entrustment Agreement and Collaboration Agreement with BMT to ensure that; a. There is no financial contribution from BCC to BMT b. future leasing arrangements with BMT will include revenue to the council 4. In parallel with a renegotiation of a lease with BMT, Bristol City Council will undergo market testing to identify alternative operational models to ensure that as well as protecting the cultural impact of Bristol Beacon, the council receives value for money for its investment.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Bristol Beacon – Update on inflation, opening date and new funding decision
Ward(s) Central Ward directly (the whole city, region and nationally operationally) Author: James Anderson Job title: Head of Capital Projects John Smith Director: Economy of Place Cabinet lead: Mayor Executive Director lead: Stephen Peacock – Chief Executive Proposal origin: BCC Staff Decision maker: Mayor Decision forum: Cabinet Purpose of Report: 1. To update Cabinet on impact of inflation and compensation events that have caused project delay 2. To present options available to cabinet to respond to these issues 3. To set out changes in the contractual relationship with the Bristol Music Trust and the need to secure ongoing commercial and cultural benefits for Bristol citizens 4. To authorise all necessary actions/negotiations to give effect to the proposals. Evidence Base: 1. The Bristol Beacon (formerly Colston Hall) transformation project is a city decision that has been supported by multiple administrations since 2003. The Grade 2 listed building is a Bristol City Council owned freehold asset, operated since 2011 by Bristol Music Trust (BMT) under a peppercorn lease. It has a capacity of more than 2,000 and hosts a programme of pop, jazz, world and classical music as well as stand-up comedy. The building sits on a constrained site and has suffered from a lack of maintenance and modernisation with no major refurbishment for 60 years.
2. BMT is an arm’s length trust established to manage events at Bristol Beacon and granted a lease and responsibility for day-to-day maintenance. The project funding envelope consists of a number of different grants from partners including the Arts Council (ACE), Heritage Lottery Fund, and WECA. As the freehold owner of the building Bristol City Council agreed to be the accountable body for the overall project with ultimate responsibility to underwrite costs of development and ultimate funder of last resort including funding risk and construction risk.
3. In March 2021, a Cabinet paper (link in background documents section) articulated significant challenges faced by the project in the fabric of the building that impacted time and cost. The decision was made by Cabinet to secure the benefits associated with the scheme and increase the budget for the transformation to £106.9m.
4. The project was subject to an external audit published in June 2021. The report noted that the Council had ensured there was a strong client-side management capacity in place as soon as the emerging issues had been identified and escalated and that it was no longer a significant weakness. The nature of the project in a listed, poor-quality structure and the volatile economic and geopolitical context has meant that despite being well resourced and managed, the project has continued to encounter significant challenges.
1 Version Feb 2022 5. External Influences & Structural Challenges – Inflation and External Influences Impact (appendix A1) & Building Structure (appendix A2) Since the February 2021 Cabinet paper, the project has gained significant momentum and made great strides towards completion but has faced further pressures and continued challenges. The impact of inflation and external influences (appendix A1) on the budget has been significant and the complex and flawed fabric of the building has continued to cause problems (appendix A2) negatively effecting time and cost. Appendices A1 and A2 provide detail around the nature and quantum of the challenges faced since the last Cabinet paper. The consequence of these issues are:
a. The loss of 17 weeks resulting in a practical completion date at the end of August 2023 with an opening period though the Autumn of 2023 with a full commercial opening on 30 November 2023. b. An increase in cost of £25m resulting in a total budget required of £131.9m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.