That Cabinet: 1. Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Climate, Ecology, Energy and Waste and the s151 Officer, to (if successful), enter into a grant agreement to accept and spend £11,393,650 Home Upgrade Grant (HUG2) awarded by central government to Bristol City Council and its partners to deliver energy efficiency and renewable measures to low-income private households with poor energy efficiency ratings. 2. Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Climate, Ecology, Energy and Waste and the s151 Officer, to bid for, enter into a grant agreement to accept, and spend any additional funding or extensions offered on the Home Upgrade Grant up to end 2025, provided that the grant conditions remain materially the same and it is 100% grant funded. 3. Authorised the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Climate, Ecology, Energy and Waste to procure and award the contract(s) (which may be over £500k) necessary for the implementation of Home Upgrade Grant, in line with the procurement routes and maximum budget envelopes outlined in this report, noting the associated Legal commentaries. 4. Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report in line with the provisions of the grant agreement.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Citywide Author: Helen Reed Job title: City Leap Client Function Lead Cabinet lead: Cllr Kye Dudd, Cabinet Member for Executive Director lead: Stephen Peacock, Executive Director Climate, Ecology, Energy and Waste Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: This report sets out actions to deliver key commitments within the One City Climate Strategy to: 1. Decarbonise heat within the city 2. Use grant funding to make capital investments in buildings to reduce their energy demand and cost
Cabinet is asked to 1. Accept UK Government grant funding applied for and permission to apply for further funding under the Home Upgrade Grant scheme up to 2025. 2. Note that it is intended for the scheme to be delivered by Ameresco as the council’s City Leap partner
1. Evidence Base: 1.1. Bristol City Council declared a Climate Emergency in November 2018 and the Mayor published his initial Action Plan in July 2019, including an ambition for the city to be carbon neutral by 2030. 1.2. Bristol City Council developed and endorsed the One City Climate Strategy February 2020 committing to decarbonisation actions within its own estate and the city. 1.3. Bristol City Council approved its Climate & Ecological Emergency Programme on 3 November 2020 to help implement the strategy, including a key objective of the council leading the city by example. 1.4. 14.4% of homes in Bristol are in fuel poverty, that represents 27,615 households in the city (LILEE Sub- regional data 2019).
2. Private Homes 2.1. As part of the Heat and Buildings Strategy, Central Government (BEIS) has allocated £950 million to the Home Upgrade Grant (HUG) from April 2022 to March 2025. BEIS have already had two rounds of funding
1 Version Feb 2022 and intend to open further opportunities to bid for this funding, until all funds have been allocated by 2025. 2.2. In February 2021 Bristol City Council was successful in being awarded £3.2million for improving low income, low energy efficiency owner occupied households. 2.3. Subsequently, in March 2022 Bristol City Council was successful in being awarded a further £3.6million to support homes without gas central heating that were both low energy efficiency and low-income households. This funding was called the Home Upgrade Grant Phase 1 (HUG1). 2.4. Bristol City Council submitted a consortium bid in November 2022 for HUG Phase 2 funding. This was done under delegated authority from Cabinet paper “Delivery of Energy Efficiency and renewable energy measures to reduce fuel poverty, household expenditure and carbon emissions” (Link below). The consortium is with North Somerset, and Bath and North East Somerset (B&NES) councils, and the total bid is for £11.4 million. The bid is an 100% grant funded programme to support households with energy efficiency measures and low carbon heating. 2.5. The HUG2 bid proposal will see £10million being delivered in measures across the region. £3million of which will be delivered directly into Bristol. 2.6. Should we be successful in our grant application, announcements should be in January, initial funding is transferred from February 2023 and installation starting from March 2023. 2.7. The funding will be subject to a Memorandum of Understanding (MOU) with BEIS which will set out the terms of the spending and the return of any unspent grant at the end of the programme. 2.8. Installation will be carried out by Ameresco Limited (the strategic partner procured by the council to deliver low carbon energy infrastructure through the City Leap partnership and/or another contractor procured via a regulated procurement.
Cabinet Member / Officer Recommendations:
That Cabinet:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.