That Cabinet: 1. Approved the Schedule of Fees and Charges as laid out in Appendix 1 to support the harbour authority to becoming financially self-sufficient. 2. Approved the increase of fees and charges from Financial Year 2024/25 by RPI plus 5% to be reviewed in 2025/26. 3. Authorised the Executive Director Growth and Regeneration to take all steps required to implement the fees and charges as outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Hotwells and Harbourside and Central Author: Tony Nichols Job title: Harbour Master Cabinet lead: Mayor Executive Director lead: Stephen Peacock, Executive Director Growth and Regeneration Proposal origin: BCC Staff Decision maker: Mayor Decision forum: Cabinet Purpose of Report: 1. To approve the Schedule of Fees and Charges as laid out in Appendix 1. 2. To approve the increase of fees and charges from Financial Year 2024/25 by RPI plus 5% to be reviewed in 2025/26 Evidence Base: 1. Over the past two years the harbour authority has carried out a review of the harbour’s operations, governance, regulatory responsibilities, and finances (Operational Harbour Review). The review has identified that the current schedule of fees and charges applied are in some case extremely low when benchmarked against other harbour authorities in the Southwest. This has been borne out in the BCC Internal Audit Report (Dec 2020), and the Savills Bristol Docks Mooring Review (February 2020), which stated that “there is considerable scope for increasing fees when comparing with other harbour authorities”.
2. Bristol Harbour Authority has reviewed and benchmarked the current fees and charges which it applies against several harbour authorities to inform the proposals being made in Appendix 1. The introduction of the new fees and charge’s structure will enable the Bristol Harbour Authority to:
• Implement a schedule of fees and charges which will support the service to become financially self- sufficient. • Reflect fees and charges which other harbour authorities charge. Enable the Harbour Authority to apply for a new Harbour Revision Order- When applying the applicant must show that all assets and income within the harbour estate is sufficient to be able to carry out the harbour undertaking (the day-to-day operation of the harbour.
3. Bristol Harbour has always been an important historic economic asset for the city. Key features, such as the 250-year-old Floating Harbour, have now become an integral part of the City’s increasing popularity and a significant attraction at the heart of the city.
4. Functioning as a commercial dock until the mid-1970s, Bristol Harbour is not only a major tourist attraction with museums, restaurants, bars, and nightclubs, but also preserves a working shipyard in the Floating Harbour. The annual Harbour Festival is one of the highlights in the City’s internationally renowned cultural programme and is one of the country’s largest free festivals. Over a 4-day period, the Harbour Festival attracts over 300,000 visitors and celebrates the maritime heritage of our city and the
1 Version April-2018 continuing importance of the docks and Harbour to Bristol’s economy.
5. The use of the City Docks has changed since the last review of fees and charges was introduced and the commercial income it previously benefited from has reduced to a negligible amount and the harbour is now used for more leisure purposes than commercial. The review of fees and charges will be carried alongside the review of commercial rents and use of land within the Harbour Estate.
6. In 2021 the harbour authority commenced an Operational harbour review which looked at the harbour’s operation, governance, regulatory responsibilities, and finances. The review has identified that the fees and charges applied are in some case extremely low when benchmarked against other harbour authorities, and this has been borne out in the BCC Internal Audit Report (Dec 2020), and the Savills Bristol Docks Mooring Review (February 2020), which stated that “there is considerable scope for increasing fees when comparing with other sites”.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.