That Cabinet: 1. Noted the progress towards and delivery of the Southmead Masterplan and the amendments to individual sites within the Masterplan area. 2. Noted previous Cabinet approval on 25 February 2021 to allocate capital investment of up to £7m from Strategic Community Infrastructure Levy for non-residential elements of the revised Glencoyne Square Scheme. 3. Approved an additional sum of up to £620k from Strategic Community Infrastructure Levy for non-residential elements of the revised Glencoyne Square Scheme to support the additional cost increase. 4. Authorised the Executive Director Growth & Regeneration, (in consultation with the S151 Officer, Cabinet Member for Finance, Governance & Performance, and Cabinet Member for Housing Delivery and Homes to: (i) Use Strategic CIL funds up to £7.62m to deliver the non-residential elements of the Glencoyne Square scheme, supporting the non-residential development including], public realm, commuted sums, library relocations, and delivery of advice learning, Library and training hub and new Health, and Well-Being Hub at Glencoyne Square by SDT; (ii) To negotiate and agree all remaining further property and financial transactions, and to procure all necessary contracts (goods, services, grants and works) contract which may be above key decision threshold, required to deliver the CIL funded works subject to keeping within the budget outlined in the report. (iii) take all steps required to negotiate terms for the total CIL funding drawdown and spend.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Southmead Authors: Mohammed Al-Bayatti and Job titles: Housing Development Manager and Tim Midwood Senior Housing Development Manager Cabinet lead: Cllr Renhard, Cabinet Member Executive Director lead: John Smith, Interim Executive Housing Delivery and Homes Director Growth and Regeneration Proposal origin: Other Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. This report seeks Cabinet approval and authorisation of an additional sum of up to £620k (in addition to £7m previous cabinet decision in February 2021) from Strategic Community Infrastructure Levy for non-residential elements of the revised Glencoyne Square Scheme and authorisation to implement key aspects of the scheme. 2. It also notes progress with, and amendments to, the ‘Southmead Masterplan’.
Evidence Base: In 2018 an ambitious community-led ‘Southmead Masterplan’ was developed to guide regeneration in Southmead. The Masterplan shows the spatial redevelopment of a range of central Southmead sites to support improved public service provision, local amenity, regeneration, and the delivery of new homes. A copy of the Masterplan showing spatial plans can be found at: https://www.southmead.org/wp- content/uploads/2018/10/FV_18061_U01_002_Masterplan-Report_181010.pdf.
The overall aims of the masterplan are to: • Provide high quality floor space and open space for community, health and commercial use. • Deliver 240-330 new homes in central Southmead, with a mix of new affordable and market housing options, including smaller homes to enable downsizing and reduce under-occupation. • Enable a sustainable income for Southmead Development Trust to deliver its charitable objectives. • Provide appropriate anchor supermarket provision. • Improve the sense of place and public realm within the Arnside area.
Implementation of the Southmead Masterplan is being undertaken over several phases. It will enhance development densities, protect retail provision, provide a sustainable future for the local centre, and improve the accessibility and efficiency of local services.
In 2019 Bristol City Council (BCC) received a £3.6m Housing Infrastructure Fund (HIF) funding award from Homes England to support the delivery of the Masterplan, including site acquisition, public realm works, and sustainable drainage improvements.
1 Version Feb-2018 Significant progress against the Masterplan has been made by the Council working in partnership with the Arnside and Glencoyne Regeneration Project Group (AGRP) and Southmead Development Trust (SDT): • Public realm and sustainable urban drainage (SuDs) improvements to Arnside have been completed and opened to the public in May 2022. These sustainable drainage improvements will mitigate the impact of building homes identified in the Southmead Masterplan. • The White Hall site has been purchased by Bristol City Council for re-development with the former building now demolished. • Planning permission has been granted for the first major new housing scheme on Glencoyne Square, for 120 new homes and the scheme has subsequently been enlarged and re-designed to improve viability with an additional level of HIF funding made available toward pre-development costs and enabling work. • The Youth Centre has been returned to Bristol City Council, and local youth services have been consolidated and improved on the Ranch Adventure Playground (not HIF funded). • The Library has been relocated temporarily to Southmead House (not HIF funded).
To date, circa £2.2m of HIF funding has been spent, with a further £290k contributed by the Wessex Water, and BCC Flood and City Design Teams for SuDs and public realm Arnside improvements.
Southmead Masterplan Changes to note
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.