That Cabinet: 1. Authorised the Executive Director Growth and Regeneration in consultation with the Mayor, to take all steps required to accept and spend the grant of up to £16m from the City Region Sustainable Transport Settlement (CRSTS) challenge fund grant on a capital programme of works to refurbish and repair all 6 key bridges over the cut during the next 4 years including procuring and awarding contracts which may be above the key decision threshold, in-line with the procurement routes and maximum budget envelopes and as outlined in this report. 2. Authorised the Executive Director Growth and Regeneration to take all steps required to spend the CRSTS Capital funding, using the following Asset Management and Risk Management prioritised maintenance approach: • Gaol Ferry Footbridge (already commenced). £1.50m • Sparke Evan Footbridge (due to commence in 2023). £2.0m • New Brislington Bridge (Ongoing Condition and feasibility Studies). £0.50m • Saint Phillips Causeway (Ongoing Condition and feasibility Studies). £0.50m • Remaining New Cut Bridges: Langton Street (Banana) footbridge, Vauxhall footbridge, Bedminster New over Bridge, Bath New over Bridge. (Full Refurbishment Works over 4 years). £11.50m 3. Authorised the Executive Director Growth and Regeneration to make any amendments to the Asset Management and Risk Management prioritised maintenance approach allocations within the overall budget envelope.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Refurbishment Works to Existing “New Cut River” Bridges, and Future Feasibility Studies to Manage Other Assets Ward(s) Various affected: Central, Hotwells &Harbourside, Bedminster, Southville, Lawrence Hill, Brislington East and Saint Georges West Author: Chris Dooley Job title: Bridges and Highway Structures Manager Cabinet lead: Mayor Rees Executive Director lead: John Smith, Interim Executive Director Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To seek approval to accept and spend CRSTS funding on the existing New Cut Bridges during the next 5 years. 2. To seek approval to proceed to programme, plan and procure these proposed Capital Programme of Works over the next four years, using the CRSTS Challenge Funding grant mechanism. Evidence Base: 1. Bristol City Council’s ongoing statutory bridge inspection regime and the recent overall Harbour Asset Study of overbridges along the New Cut have identified serious areas of concern which need repair. The condition inspections were done by BCC inspectors, external procured specialist inspection and testing consultancies as well as using other technological tools such a drone and GIS techniques. These bridges have been identified from west to east along the flow route of the old excavated navigable tidal river channel route known as the “New Cut” as described follows:
• Vauxhall Footbridge (57137) • Gaol Ferry Footbridge (57153) • Bedminster New Bridge (57067)* *Twin Bridges used in a roundabout configuration • Langton Street (Banana), Footbridge (57151) • Bath New Bridge (57069)* *Twin Bridges used in a roundabout configuration • Sparke Evans Footbridge (67106)
2. Repair work has already commenced on Gaol Ferry Footbridge. Capital costs are forecasted to be approximately £1.50m. The funding was previously approved in a cabinet report in May 2022.
3. Feasibility and inspection work has commenced on Sparke Evans Footbridge in May 2023, and these works are forecasted to be in the region of £1.50m - £2.00m. To undergo the repair works, this Footbridge will be closed to the public and a full condition assessment and then a full structural refurbishment will be undertaken by Council Framework Contractors.
4. The proposal is to spend the CRSTS Capital funding, using the following Asset Management and Risk Management prioritised maintenance approach:
• Gaol Ferry Footbridge (already commenced on site). £1.50m • Sparke Evans Footbridge (due to commence in 2023). £2.0m • New Brislington Bridge (feasibility Studies). £0.50m
1 Version Feb 2022 • Saint Phillips Causeway (feasibility Studies). £0.50m • Remaining New Cut Bridges – Langton Street (Banana) footbridge, Vauxhall footbridge, Bedminster New Bridge, Bath New Bridge. (Full Refurbishment Works over four years). £11.50m
5. There is also a requirement to do further condition assessment, work prioritisation and costing proposals for two major assets other than the eight New Cut bridges listed in above.
6. These additional strategically important structural assets are as follows:
• Saint Phillips Causeway (67033 - Spine Road): This is a 1km long elevated Viaduct structure which a recent Principal Inspection has identified now needs a major structural refurbishment and it is proposed to spend half a million pounds (£0.50m) in doing further feasibility studies, costings and a detailed design package to allow the Authority to fully prioritise the works required and procure these works out to external market and ultimate execution of these strategic maintenance works on site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.