That Cabinet: 1. Approved an increase to Bristol’s Economic Development Fund allocation to MetroWest Phase 2 of £1.894m subject to a report being brought back Cabinet to provide an update on the latest EDF profile that highlights funding that has been released to enable this work to be fully funded. 2. Noted the additional funding of £1.894m is to be released from the £17.5m that Cabinet previously agreed to be held in abeyance towards the Temple Island (TI) enabling project. 3. Authorised the Executive Director of Growth & Regeneration, in consultation with the Cabinet Member for Transport to take all steps required to approve the final scheme design and deliver the approved scheme and associated landscaping based on the draft scheme designs set out in Appendices A1 and A2. 4. Authorised the Executive Director of Growth & Regeneration, in consultation with the Cabinet Member for Transport and the Director of Legal and Democratic Services to take all steps required to agree and enter into a grant agreement and spend the funding (including procuring and awarding contracts over the key decision threshold) to deliver the approved scheme and associated landscaping as outlined in this report. 5. Noted the progress on the MetroWest Phase 2 programme including the revised costs and programme, updated design information and changes to governance as outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE MetroWest Phase 2 and Ashley Down Rail Station
Ward(s) The MetroWest Phase 2 project has a Citywide impact. Highway works and improvements impact Bishopston & Ashley Down and Lockleaze wards Author: Melanie Bufton Job title: Principal Transport Planner Cabinet lead: Cllr Donald Alexander, Cabinet Executive Director lead: John Smith, Interim Executive Member for Transport Director, Growth & Regeneration Proposal origin: City Partner Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To provide an update on the MetroWest Phase 2 programme and specifically Ashley Down Rail Station. To include updates on progress, governance, delivery model and costs. 2. To seek approval to increase the funding allocation to the programme from Bristol’s Economic Development Fund. 3. To request approval for delegation of authority to the Executive Director of Growth & Regeneration, in consultation with the Cabinet Member for Transport to approve the final scheme design, and the delivery of the approved scheme and associated landscaping based on the draft scheme designs set out in Appendices A1 and A2. 4. To request approval for delegation of authority to the Executive Director of Growth & Regeneration, in consultation with the Cabinet Member for Transport and The Director of Legal and Democratic Services to enter into a grant agreement to deliver the approved scheme and associated landscaping, if required.
Evidence Base: 1. MetroWest is a programme of rail enhancements across the West of England including the reopening of former passenger rail lines, the delivery of new stations and enhancements to cross-Bristol services. The programme seeks to increase both the capacity and accessibility of the local rail network. MetroWest Phase 2 consists of a new rail station at Ashley Down and two new rail stations on a re-opened Henbury Line (North Filton for Brabazon and Henbury). The Henbury Line is currently freight-only; this project will enable passenger services to use the line. The project also includes enhanced rail frequencies between Bristol and Gloucester from hourly to half-hourly.
2. Key benefits of the MetroWest Phase 2 programme include; £2 return on every £1 spent, 1.3m passengers expected to use the new services each year, journey time savings, reduction of private car use leading to over 500 tons of CO2 saved each year, support new housing delivery.
3. Bristol City Council’s Cabinet was last updated on progress of the project in June 2019, following completion of the Outline Business Case. Since then, the project has progressed with Ashley Down station moving into construction in March 2023. In 2019, it was anticipated that the City Council would enter into a joint promotion agreement with South Gloucestershire Council and the West of England Combined Authority (the Combined Authority). Since then, a change in governance 1 Version Feb 2022 arrangements has meant that the Combined Authority is now the sole promoter of the scheme, with the City Council and South Gloucestershire Council being key project partners. This has significantly reduced the financial risk to the City Council.
4. The anticipated final cost of the programme was estimated at Outline Business Case stage to be £54.163m (as reported to Cabinet in June 2019). The current anticipated final cost of the programme is now £72.613m, an increase of £18.45m. Key reasons for this increase in costs include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.