2025/26 Finance Provisional Outturn Report

Noted Committee 4 papers

AI summaryBristol Transport and Connectivity Committee noted the 2025/26 P12 outturn, showing a £1.0m revenue improvement and an £8.0m capital underspend against a £68.4m revised budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action requested beyond noting
Money£8.0m capital underspend, £1.0m revenue improvementCapital against £68.4m revised budget; revenue vs revised budget
What happens nextNegotiate EBLN change request with MCATo cover £1.8m EBLN overspend
Who it affectsTransport and highways services in BristolManagement of Place and Economy of Place

What was decided

The committee noted the contents of the report on the P12 outturn forecast for 2025/26. Report P16

Why

Revenue forecast improved by £1.0 million against the revised budget, driven by a £(0.8) million movement in Management of Place (Traffic and Highways) and £(0.2) million in Economy of Place (Strategic City Transport). Report P4

Capital showed a net underspend of £1.0 million against a P10 forecast of £61.4 million and £8.0 million underspend against a revised budget of £68.4 million, mainly from reprofiling of MCA-funded schemes and the A432 Fishponds Road project. Report P6, P7, P9

What happens next

A change request is being negotiated with the Mayoral Combined Authority to cover a £1.8 million realised overspend on the East Bristol Liveable Neighbourhood project. Report P11

The money

  • £1.0 million Revenue forecast improvement against revised budget Report P4
  • £(0.8) million Improvement in Management of Place, Traffic and Highways Report P4
  • £(1.0)m Net CAZ Reserves drawdown for income in Highways Report P4
  • £0.2m Pressure for Streetlighting recognised in the accounts Report P4
  • £(0.2) million Improvement in Economy of Place, Strategic City Transport Report P4
  • £1.0 million Net capital underspend against P10 forecast of £61.4 million Report P6
  • £8.0 million Capital underspend against revised budget of £68.4 million Report P6
  • £4.9 million GR14 Public Transport variance, mainly MCA grant reprofiling Report P7
  • £2.1 million GR17 Local Transport Schemes variance, including A432 Fishponds Road reprofiling Report P9
  • £0.9 million Reprofiling of A432 Fishponds Road spend into future years Report P9
  • £1.2 million PL11A Cattle Market Road site re-development reprofiling for Harbour Walkway into 2026/27 Report P10
  • £1.2 million GR15 Active Transport overspend variance, EBLN project Report P11
  • £1.8 million Realised overspend on East Bristol Liveable Neighbourhood, subject to MCA change request Report P11

Options considered

  • Chosen: Note the P12 outturn forecast report. Officer recommendation to the committee Report P15, P16

Implications

  • Financial: Revenue outturn improved by £1.0m and capital underspent by £8.0m against revised budget, reducing overall pressure on the council's 2025/26 position. Report P4, P6
  • Financial: MCA-funded public transport and active transport schemes had spend reprofiled into future years, with the East Bristol Liveable Neighbourhood requiring an additional change request for £1.8m. Report P7, P11
  • Risk: East Bristol Liveable Neighbourhood is reporting a £1.8m overspend above its funding envelope, and a change request with the Mayoral Combined Authority is being negotiated to cover it. Report P11

Who and where

  • Traffic and Highways services, including Parking and Streetlighting Report P4
  • Strategic City Transport, including metrobus, TROs and bus stop suspension Report P4
  • Public transport and active transport capital schemes funded via the Mayoral Combined Authority Report P7, P11
  • A432 Fishponds Road project Report P9
  • Cattle Market Road site re-development, including the Harbour Walkway due for completion in 2026/27 Report P10
  • East Bristol Liveable Neighbourhood and Bristol Regional Cycling Hub full business case Report P11

Timeline

  • 25 February 2025: Full Council agreed the 2025/26 Revenue and Capital budget Report P1
  • End of March 2026: Period 12 outturn position reported against budget Report P1
  • Summer 2026: East Bristol Liveable Neighbourhood full business case due Report P11
  • 2026/27: Harbour Walkway scheme (PL11A) due for completion Report P10

Plain English for the jargon

  • P12 outturn: Period 12 financial forecast, the end-of-year position as at the end of March 2026
  • CAZ: Clean Air Zone
  • MCA: Mayoral Combined Authority
  • TRO: Traffic Regulation Order
  • EBLN: East Bristol Liveable Neighbourhood
  • R&Os: Reports and other papers referenced in earlier monitoring rounds (not defined in this report)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the Committee for Transport and Connectivity noted the contents of the report on the P12 outturn forecast.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Purpose of report

1. The Council Revenue and Capital budget for 2025/26 was agreed by Full Council on 25 February 2025. This report presents to the Transport and Connectivity Committee the financial forecast at Period 12 (P12) outturn against the budget as at the end of March 2026. Evidence Base / Context

1. The Committee’s remit is divided between Management of Place and Economy of Place.

Revenue

2. Forecast has improved by £1.0 million against the revised Budget: • Management of Place: £(0.8) million improvement in Traffic and Highways driven by £(1.0)m net CAZ Reserves drawdown for income in Highways and improved income in Parking, partly offset by £0.2m pressure for Streetlighting being recognised in the accounts, previously highlighted in the R&Os. • Economy of Place: £(0.2) million in Strategic City Transport driven by lower metrobus costs and small income increases for TROs and bus stop suspension. (Please refer to appendix A1a – table 1a / page 5 and para 2.31 & 2.32 / pages 15-16)

Capital

3. The Transport and Connectivity Committee reported a net underspend of £1.0 million against a P10 forecast of £61.4 million and a £8.0 million underspend against a revised budget of £68.4 million with the main variances relating to the following:

• GR14 - Public Transport variance of £4.9 million primarily due to reprofiling of spend on several Mayoral Combined Authority (MCA) grant funded schemes into future years.

1 Version January 2024

OFFICIAL • GR17 - Local Transport Schemes variance of £2.1 million due to reprofiling of spend on the A432 Fishponds Road project into future years £0.9 million. Smaller underspends / reprofiling in other schemes form the remainder of the balance.

• PL11A - Cattle Market Road site re-development variance of £1.2 million due to reprofiling of spend on the Harbour Walkway into the next financial year. This scheme is due for completion in 2026/27.

• GR15 - Active Transport overspend variance of £1.2 million due to the East Bristol Liveable Neighbourhood (EBLN) project. EBLN was funded to completion of a full business case due in summer 2026. However, an overspend of £1.8 million has been realised and a change request is being negotiated with the MCA to cover these additional costs. The overspend is partially netted off against reprofiling of spend on the full business case for the Bristol Regional Cycling Hub into the next financial year.

• The balance relates to minor variances across several projects and programmes.

(Please refer to appendix A1b – para 1.4)

4. Also to note, in Appendix A1a, section 3 / para 3.5 references the committed Savings for the Committee.

Officer Recommendations:

That the Committee for Transport and Connectivity notes the contents of the report on the P12 outturn forecast.

Corporate Strategy alignment:

1. The Corporate Strategy underpins the council’s budget

City Benefits:

1. Cross priority report that covers whole of council’s business

Consultation Details:

1. N/A

Background Documents: Budget Report 2025/26

APPENDICES Appendix A – Further essential background information and detail YES

2 Version January 2024

OFFICIAL 3 Version January 2024

OFFICIAL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Finance Provisional Outturn ReportReport 112 KB DownloadRead as text
PDF
Budget Monitor PackAppendix A1 783 KB Download
PDF
BCC 2025-26 Provisional Outturn: Revenue FINALAppendix A1a 674 KB Download
PDF
BCC 2025-26 Provisional Outturn: Capital & Investments FINALAppendix A1b 139 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
EP
Councillor Ed PlowdenChair, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
SR
Councillor Serena RalstonCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
TW
Councillor Toby WellsCommittee Member, present
MW
Councillor Mark WestonCommittee Member, present
JS
John SmithOfficer, expected
AH
Alex HearnOfficer, expected
PM
Patsy MellorOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. 2025/26 Finance Provisional Outturn ReportThis decision
  2. 2025/26 Finance Provisional Outturn ReportNoted
  3. 2025/26 Finance Provisional Outturn ReportNoted
  4. 2025/26 Finance Provisional Outturn ReportNoted
  5. 2024/25 Finance Provisional Outturn ReportNoted
  6. 2024/25 Finance Provisional Outturn ReportNoted

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open