Transport & Connectivity Policy Committee, Thursday 20 March 2025 at 5.00pm

City Centre Transport Corridor – Temple Way FBC

Approved Committee 5 papers

Transport & Connectivity Policy Committee approved this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

That the Committee for Transport and Connectivity: 1. Approved submission of the Temple Way FBC for approval at WECA Committee or WECA Directors. 2. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to take all steps required to procure and award the necessary contracts for this project (which may be over the key decision threshold), in line with the procurement routes and maximum budget envelopes outlined in this report, should the FBC be approved by the WECA Committee.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Committee Report

PURPOSE: Final Decision Report

KEY OR NON-KEY DECISION: Key decision over £500k spend/save & impacts more than 2 wards

COMMITTEE: Transport and Connectivity Committee

DATE: 20 March 2025

TITLE: City Centre Transport Corridor – Temple Way FBC Submission Ward(s): Central; Lawrence Hill

Officer presenting the report: Adam Crowther Job title: Head of City Transport

Committee Chair: Cllr Ed Plowden Executive Director lead: John Smith: Executive Director for Growth & Regeneration

Proposal origin: BCC Staff

Purpose of Report: To seek approval from the Transport and Connectivity Committee to: - Submit the City Centre Transport Corridor – Temple Way Full Business Case (FBC) to the West of England Combined Authority (WECA). - Authorise the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to take all steps required to procure and award the necessary contracts for this project (which may be over the key decision threshold), in line with the procurement routes and maximum budget envelopes outlined in this report, should the FBC be approved by the West of England Combined Authority.

Evidence Base / Options to consider: 1. This project comprises a series of complementing bus and cycle improvements along Temple Way in Bristol City Centre (see Figure 1). 2. The scheme proposes inbound and outbound bus priority along Temple Way. The bus interventions will contribute to a near complete anti-clockwise loop of bus priority around the city centre. 3. The scheme includes a two-way cycle route proposed along Temple Way parallel to the southbound carriageway. The cycle infrastructure will offer a segregated cycle route which will complement and connect to existing segregated cycled lanes along Temple Way, Victoria Street, the Bristol to Bath Cycle Path and Concorde Way. 4. The Temple Way scheme forms part of the City Centre Transport Corridor, which is funded through the City Region Strategic Transport Settlement. 5. A Full Business Case has been prepared by Aecom, which forecasts that the scheme will cost approximately £4.6 million and generate a Benefit Cost Ratio (BCR) of 6.22, which represents very high value for money. 6. Updated cost estimates have been produced by BCC Engineering Design, which total £4.4

1 Version January 2024

OFFICIAL million. This has been reflected in the Financial case but, as the total cost is within 5% of the original estimate, the calculations in the Economic case have not been updated. 7. The implications on the transport network have been assessed and this scheme is not expected to have a significant negative impact, either during construction or after delivery.

Figure 1: Map of existing and new bus lanes and cycle routes in Temple Way

Table 1: Total Project Costs Pre-FBC Post-FBC £289,708 £4,117,783

Table 2: Annual Cost Breakdown 2024/25 2025/26 2026/27 £289,708 £1,701,672 £2,416,111

Table 3: Funding Sources CRSTS Section 106 £2,441,794 £1,965,697

Table 4: Monetised Impacts of the Scheme

2 Version January 2024

OFFICIAL Costs & Benefits (2010 prices, £’000s) AMAT* SSAT~ Total

Present Value Benefits (PVB) £2,063.81 £4,919.56 £5,932.57 Present Value Cost (PVC) £953.38 Benefit Cost Ratio (BCR) 6.22 Value for Money Category (VfM) Very High * Small Scheme Appraisal Toolkit (SSAT) assesses the impacts of bus and highway interventions. ~ Active Mode Appraisal Toolkit (AMAT) assesses the impacts of active travel interventions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App H1 Temple Way General Arrangement DrawingsAppendix A 5.5 MB Download
PDF
Equality Impact Assessment: Temple WayAppendix B 601 KB Download
PDF
Environmental Impact Assessment: Temple WayAppendix C 349 KB Download
PDF
City Centre Transport Corridor: Temple Way FBCReport 273 KB DownloadRead as text
PDF
Committee Report: Temple Way: updated linkReport 273 KB Download

At this meeting

Whole meeting

Who was there

9 of 18 attended
EP
Councillor Ed PlowdenChair, present
GM
Councillor Graham MorrisVice-Chair, apologies
DA
Councillor Donald AlexanderCommittee Member, present
RB
Councillor Rob BryherCommittee Member, present
NC
Councillor Nicholas CoombesCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present
JS
John SmithOfficer, in attendance
AH
Alex HearnOfficer, in attendance
PM
Patsy MellorOfficer, in attendance

All 18 on the meeting page

On this subject at Bristol

Search all
  1. City Centre Transport Corridor – Temple Way FBCThis decision
  2. City Centre Transport Corridor – Bond St Full Business Case SubmissionApproved
  3. CRSTS City centre – Redcliffe Roundabout and Redcliffe WayApproved
  4. City Centre – Broadmead Area/ Union Street Area Outline Business Case and deliveryApproved
  5. City Centre – Bedminster Bridges Outline Business Case and Construction DeliveryApproved
  6. Strategic Corridors update and delivery of City Centre projectNoted

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies