City Centre Transport Corridor – Bond St Full Business Case Submission
ApprovedCommittee4 papers
Transport & Connectivity Policy Committee approved this item on Thursday 15 May 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity: 1. Approved submission of the Bond St Full Business Case for approval at West of England Mayoral Combined Authority (MCA) 2. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee and Section 151 officer, subject to approval of the Full Business Case by the MCA to a. Take all steps required to accept and invest the CRSTS funding amount as set out in this report and appendices b. Procure and award all necessary contracts for this project (including any over £500k), in line with the maximum budget envelope outlined in this report
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Committee Report
PURPOSE: Final Decision Report
KEY OR NON-KEY DECISION: Key decision over £500k spend/save & impacts more than 2 wards
COMMITTEE: Transport and Connectivity Committee
DATE: 15 May 2025
TITLE: City Centre Transport Corridor – Bond St FBC Submission Ward(s): Ashley, Lawrence Hill
Officer presenting the report: Adam Crowther Job title: Head of City Transport
Committee Chair: Cllr Ed Plowden Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report: To seek approval for submission of a Full Business Case (FBC) to the West of England Combined Authority (MCA) for the City Regional Sustainable Transport Settlement (CRSTS) funding and subject to approval, to accept and invest the funding to deliver the City Centre Transport Corridor – Bond Street improvements.
General Arrangement drawings of scheme:
1 Version January 2024
OFFICIAL Please see Appendix A for all scheme drawings.
2 Version January 2024
OFFICIAL Evidence Base / Options to consider:
1. This project comprises a series of bus and cycle improvements along Bond St in Bristol City Centre.
2. The scheme proposes inbound and outbound bus priority along Bond St. The bus interventions will contribute to an updated network of bus priority around the city centre.
3. The scheme includes a segregated cycle route proposed parallel to Bond St on quieter streets. This will maintain a clear route for the bus services. The cycle infrastructure will offer a segregated cycle route which will complement and connect to the existing cycle network.
4. The Bond St scheme forms part of the City Centre Transport Changes Programme, which is funded through the City Region Strategic Transport Settlement.
5. A Full Business Case has been prepared jointly by BCC and Aecom. The scheme is forecast to cost approximately £2.785 million (minus contingency and inflation). The scheme has a Benefit Cost Ratio (BCR) of 2.15 for the bus service.
6. The BCR for the full scheme (i.e. when including the monetised impacts on general traffic) is negative due to the impact of delays to general traffic through reallocating road space to buses. The calculation of this BCR follow’s guidance from the DfT and it is widely accepted, including by the DfT, that the guidance is out of date. The guidance prioritises motorised traffic making journeys as quickly as possible. These journey time savings are then monetised, where a journey becomes even 30 seconds longer, this impact is monetised as a disbenefit, included in the BCR calculation and contributes to the negative BCR. The strict application of the guidance means the scheme must be considered in isolation, so the bus service changes associated within the Broadmead area changes are not included. In summation it is considered that the BCR including traffic (dis)benefits is not a suitable metric to solely judge the scheme by.
7. Accepting that the BCR calculation and the DfT guidance are not appropriate to measure the value of the scheme. BCC has conducted extensive modelling and scheme appraisal to satisfy ourselves as an organisation that the scheme should be implemented. The negative BCR for general traffic is attributed to the junction being over-capacity following the scheme updates. Modelling done by both BCC and AECOM show the junction being over-capacity and queue lengths increasing (as seen in the diagrams below). The proposed updates are modelled to cause the gyratory to be approximately 26% over capacity in the AM peak, and 15% over capacity in the PM peak. The simple explanation about a junction being over capacity is that it means not all the traffic gets through the junction during a cycle of the signal sequence. So if an approach is 20% over capacity, then 20% of the traffic will still be there after the green light, so that traffic will take 2 green lights to get through.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.