CRSTS City centre – Redcliffe Roundabout and Redcliffe Way
ApprovedCommittee6 papers
Transport & Connectivity Policy Committee approved this item on Thursday 15 May 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity 1. Approved the submission of the Redcliffe Roundabout Full Business Case for approval at WECA committee or WECA Directors. 2. Authorised the Executive Director for Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to take all the steps required to procure and award the necessary contracts for this project (which may be over the key decision threshold), in line with the procurement routes and maximum budget envelopes outlined in this report, should the FBC be approved by the WECA committee/Directors. 3. Authorised the Executive Director for Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To seek approval to submit the City Centre Transport Corridor – Redcliffe Roundabout Full Business Case (FBC) to the West of England Combined Authority (WECA). 2. To accept and draw down City Regional Sustainable Transport Settlement funding to implement the scheme, following a procurement process.
Evidence Base / Options to consider:
1. The Redcliffe Roundabout project comprises a series of active travel measures to enhance and improve active and sustainable modes along Redcliffe Way and Redcliffe Street, part of the City Centre Strategic Corridor which is funded through the City Region Sustainable Transport Settlement. 2. The scheme proposes to implement bus priority on Redcliffe Roundabout and Redcliffe Way. These measures will contribute to a nearly complete anti-clockwise loop of bus priority around the city centre. 3. Two bus gates will be introduced, one on the roundabout itself and another on Redcliffe Street. These measures will facilitate and future proof a rapid transit route through the city centre known as the “red route.” 4. The scheme includes upgrades to walking and cycling infrastructure with the introduction of a two- way segregated cycle track on all arms of the roundabout and along Redcliffe Way. The route will connect the central cycle network to Temple Way, Victoria Street, and Redcliffe Hill. The Brunel Mile will be prioritised for walking and will remove the need for shared space which often creates conflict between different modes. 5. On 28 January 2022 the West of England Combined Authority Committee agreed to submit the
1 Version January 2024 regions Strategic Outline Business Case for the City Region Sustainable Transport Settlement (CRSTS) to the Department for Transport (DfT). 6. The proposed solution looked to build on lessons learnt from metrobus and aimed to enhance existing bus services whilst adding other arms that will complete a more comprehensive network. The sustainable transport corridors in the programme consist of • Continuous bus lanes • Bus gates to filter traffic and improve priority • Traffic signal prioritisation • Segregated walking and cycling infrastructure • Low traffic neighbourhoods adjacent to the corridors • Transport hubs, • Standardised bus stops. 7. Work package 1 – improving our sustainable city transport corridors outlined changes to Bristol City centre to facilitate access alongside further walking and cycling improvements. Officers have developed proposals to achieve this aim in line with government guidance on Bus infrastructure (LTN 1/24) and Cycling (LTN 1/20) and undertook public consultation on the proposed schemes in September 2024. 8. Officers now seek approval to submit the Full Business Case to the Mayoral Combined Authority and draw down funding to deliver the Redcliffe Roundabout scheme. 9. The scheme reallocates road space to enable the sustainable transport upgrades that requires the removal of 10 on-street pay and display parking spaces. The projected reduction in parking income is £27,441.94. 10. A Full Business Case has been prepared by AECOM, which forecasts that the scheme will cost approximately £6.25m and will generate a Benefit Cost Ratio (BCR) of 2.25, which represents high value for money.
2 Version January 2024 Figure 1: summary of Redcliffe improvements, for more detail see Appendix A
Figure 2: Proposed Bus loop enabled by city centre projects
3 Version January 2024 Figure 3: City centre part of a wider strategy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.