Bristol City Council
Homes and Housing Delivery Policy Committee, Friday 10 April 2026 at 10.00am

HIIT Programme - Housing IT Transformation Programme

Approved Committee 4 papers

AI summaryBristol City Council's Homes and Housing Delivery Committee approved up to £1.992m from the Housing Revenue Account in 2026/27 to complete the Housing IT Transformation Programme, with a target closure date of March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFunds completion of the Housing IT Programme to March 2027
MoneyUp to £1.992m from HRA in 2026/27Includes £172k contingency and £100k NEC consultancy days
What happens nextStage 1.2 delivery from April 2026Programme closure targeted for March 2027
Who it affectsCouncil housing tenants, residents and staffContinues use of new NEC housing system

What was decided

Approved up to £1.992m draw down from the Housing Revenue Account during 2026/27 to complete the Housing IT Programme, including £172k (10%) contingency and £100k NEC consultancy draw-down days. Report P63

Approved the re-baseline of the Business Case and allocated funding for full programme delivery with a target closure date of March 2027. Report P63

Authorised the Executive Director Housing, in consultation with the Committee Chair, to procure and award contracts needed to deliver the programme, including any over the key decision threshold. Report P64

Why

The NEC housing system went live in October 2025 with all core systems working, but post go-live issues surfaced in repairs logging, finance reporting, data quality, and citizen registration. Report P5, P14, P15, P16, P18

The original £7.5m approved by Cabinet in February 2023 was fully spent by end of November 2025, and a December 2025 Urgent Decision added up to £1.257m for the remainder of 2025/26. Report P4, P11

Not progressing with full delivery would leave citizens, residents and services with a partially implemented solution, as remaining modules are needed to enable the full capability of the system. Report P13, P54, P55, P56

What happens next

Stage 1.2 of the programme will enter delivery from April 2026, including an NEC v25.2 upgrade by end of April 2026 and migration of the Housing Support Register into NEC by end of May 2026. Report P25, P36

Additional modules including Risk Management, Compliance, Assure, Accessible Homes, Contractor Portal and decommissioning of Compliance365 are planned for rollout before December 2026, with full programme closure targeted for March 2027. Report 9.1, P36, P38

The Executive Director Housing, with the Committee Chair, will take steps to procure and award the contracts needed, while regular progress updates will be provided to the Committee. Report P64, P23

The money

  • £1.992m Total draw down from HRA requested in 2026/27 Report P63, P53
  • £172,031 Total contingency at 10% Report P53
  • £100,000 NEC consultancy draw-down days Report P53, P63
  • £1,330,314 Resources Report P53
  • £390,000 Supplier costs Report P53
  • £1,500,000 Capital funding secured Report P49, P53
  • £492,364 Revenue funding secured from 25/26 underspend Report P51, P53
  • £7.5m Original Cabinet approval in February 2023 Report P4, P11
  • £1.257m Additional spend approved by Urgent Decision in December 2025 Report P11
  • £0.492m Revenue cost Report P71
  • £1.5m Capital cost Report P71

Options considered

  • Rejected: Halt the programme at the end of the financial year. Would leave citizens, residents and services with a partially implemented solution Report P54
  • Rejected: Deliver only upgrades v25.2 and 26.1 as business as usual. Would not enable the full capability of the system Report P55
  • Rejected: Deliver upgrades v25.2 and 26.1 as business as usual and resolve Stage 1 issues. Would still not enable the full capability of the system Report P56
  • Chosen: Approve up to £1.992m and re-baseline the Business Case for full delivery by March 2027. Allows completion of remaining modules and full system capability Report P63

Implications

  • Financial: All programme costs split 80% Housing Revenue Account and 20% General Fund, with no unfunded pressure on budgets. Report 11.2, P77
  • Financial: Revenue funds will be met by the 25/26 underspend of funding approved in December 2025. Report P51, P76
  • Financial: Finance notes specialist data, integration and NEC consultancy input may place pressure on the overall financial envelope, requiring close monthly monitoring. Report P78
  • Legal: Additional funding on existing contracts must comply with their terms; any procurement must follow the Public Contract Regulations 2015 and/or the Procurement Act 2023. Report P79
  • Risk: Asset data is currently maintained in two systems (Compliance365 and NEC), rated as a red risk until a strategic direction is agreed. Report P58
  • Risk: Staff ability to adapt to change and new technology is rated amber, with organisational development and training to be provided. Report P60
  • Staffing: External contractor resources replaced by Bristol City Council staff where possible to reduce costs and aid transition to business as usual, with some specialist roles retained. Report P45, P23
  • Equalities: An Equality Impact Assessment (Appendix B) and Environmental Impact Assessment (Appendix C) accompany the report. Report P88, P89

Who and where

  • Council housing tenants and residents on the Housing Register, which was reduced from over 22,000 to 18,140 after data cleansing Report P7
  • Bristol City Council housing staff, who will adopt new ways of working and a revised business structure Report P45, P68, P83
  • Citizens seeking to register and bid for properties, where barriers are being resolved in the next system upgrade Report P18
  • Contractors and surveyors using Direct Resource Scheduler and the planned Contractor Portal Report P9, 9.1
  • The Housing Consumer Standards Programme, with dependencies between the two programmes being actively managed Report P23, P26

Timeline

  • February 2023: Cabinet approved £7.5m for the Housing IT Transformation Programme Report P4
  • October 2025: NEC system went live with a significant number of modules and new functionality Report P5, P6
  • End of November 2025: Programme had spent the original £7.5m Report P11
  • December 2025: Urgent Decision approved up to £1.257m additional spend for remainder of 25/26 Report P11
  • 16 December 2025: Homes and Housing Committee approved additional 25/26 funding now used as revenue source Report P51, P76
  • 24 February 2026: HITT Programme Board endorsed this report Report P43
  • 3 March 2026: Data, Digital and Technology Board endorsed this report Report P43
  • 4 March 2026: EDM Board endorsed this report Report P43
  • 17 March 2026: CLB endorsed this report Report P43
  • End April 2026: NEC upgrade to v25.2 to be implemented and change controls refreshed Report P36
  • 10 April 2026: Committee decision taken
  • End May 2026: Housing Support Register to be migrated into NEC Report P12, P36
  • End September 2026: New business-as-usual structure for NEC system support to be in place Report P36
  • End October 2026: Decommissioning of legacy systems to be complete Report P36
  • End December 2026: All data to be extracted into NEC modules Report P38
  • No later than February 2027: Compliance365 to be decommissioned Report P38
  • March 2027: Target programme closure date Report P2, P47

Plain English for the jargon

  • NEC: The housing management IT system being implemented by the council to replace legacy systems
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
  • General Fund: The council's main, non-ring-fenced revenue account
  • HITT / HIIT Programme: Housing IT Transformation Programme, replacing legacy housing IT systems with the NEC managed service
  • HomeChoice Bristol: The council's housing allocations scheme and team that manages the Housing Register
  • HCSP: Housing Consumer Standards Programme, a related council programme with dependencies on the NEC system
  • Compliance365 (C365): A separate compliance system used by the council, planned for decommissioning once data moves into NEC
  • DRS: Direct Resource Scheduler, used to allocate repairs and servicing jobs to operatives and contractors
  • BCC: Bristol City Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

It was RESOLVED that the Committee for Homes and Housing Delivery (Unanimously FOR): Approved up to £1.992m draw down from the Housing Revenue Account during 2026/27 to complete the delivery of the Housing IT Programme. This includes £172k (10%) contingency and £100k NEC consultancy draw-down days. Approved the re-baseline of the Business Case and allocates funding to support the full delivery of the programme with a target closure date of March 2027 as outlined in the report. Contractual: Authorised the Executive Director Housing in consultation with the Chair of the Homes and Housing Delivery Committee to take all steps required to procure and award contract(s) to give effect to the programme, including any which may be over the key decision threshold. Note: Noted the progress made on resolving issues with the system experienced since “Go Live” in October 2025. Noted the lessons learned being taken forward as we seek approval for the next stage of activity to deliver the programme in full.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

This report seeks to provide an update on the progress made to date on the delivery of the NEC system and evidence base and justification for the funding needed to deliver the programme in full. It also provides an overview of the revised delivery approach that incorporates lessons learned and builds on our strength following October go-live of the system.

The Programme is seeking endorsement of the re-baselined business case and approval to draw down up to £1.992m from the Housing Revenue Account during 2026/27 to complete the delivery of the Housing IT Programme by March 2027.

Evidence Base

1. In February 2023 Cabinet approved £7.5m to deliver the Housing IT Transformation Programme with programme with the objective of replacing our legacy systems with a managed service which provides a full supported IT Housing system, with the applications and data our tenants, residents and staff need to successfully manage their social housing journey.

2. We went live in October 2025 with a significant number of modules and new functionality. Considering the size and complexity of this transformational change, a lot has been successfully achieved and presently all core systems are working. However, some areas requiring attention did surface post go-live, and work has been underway since then to ensure these are working as well as possible for both citizens and staff.

Template approved October 25

OFFICIAL 3. A data cleansing exercise was carried out ahead of the NEC implementation to improve the accuracy and integrity of the Housing Register, as is good practice to undertake such exercises periodically. The HomeChoice Bristol team reviewed Band 3 and 4 applications to identify where no bids had been placed in the last two years, in line with Section 7.1 of the Allocations Policy. Where no bids were made, applications were cancelled and households notified, with the option to request reinstatement. Applications for households with specific vulnerabilities were reviewed but not closed. This work ensured only active applications were migrated. As a result, the register reduced from over 22,000 to 18,140.

4. The following outlines all the modules and elements of the system that have been successfully implemented so far:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment Housing ITAppendix B 424 KB Download
PDF
Environmental Impact Assessment: HITTP Stage 1.1 Key decision April2026 (002)Appendix C 407 KB Download
PDF
Housing IT Business Case update 100426 (1)Appendix H 589 KB Download
PDF
HIIT Programme: Housing IT Transformation ProgrammeReport 291 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
PG
Councillor Paul GogginCommittee Member, apologies
CG
Councillor Caroline GoochCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
AA
Councillor Al Al-MaghrabiCommittee Member, present as substitute
ST
Councillor Sibusiso TshabalalaCommittee Member, apologies
KB
Councillor Kerry BailesCommittee Member, present as substitute
DM
David McNultyOfficer, in attendance

All 17 on the meeting page

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Annual Cladding Remediation UpdateThe Committee Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies