Homes and Housing Delivery Policy Committee, Friday 10 April 2026 at 10.00am

Finance report update

Noted Committee 3 papers

AI summaryBristol City Council's Homes and Housing Delivery Committee noted the Period 10 finance forecast for Housing and Landlord Services, showing a £0.5m General Fund overspend, a £0.5m HRA overspend, and capital slippage of £7.8m and £16.6m respectively.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedP10 forecast for Housing and Landlord Services
Money£0.5m GF and £0.5m HRA overspendsPlus £7.8m and £16.6m capital slippage
What happens nextYear-end overspends from reservesHRA overspend met from general reserve
Who it affectsHousing and Landlord ServicesCouncil tenants and homeless households

What was decided

The Committee noted the Period 10 forecast and appendices for Housing and Landlord Services. Report P71

Why

The report sets out the year-to-date financial position against the approved 2025/26 budget for both the General Fund and the ringfenced Housing Revenue Account. Report P1, P2

It also covers the impact of the additional Rough Sleepers Grant announced in February 2026 and the rent convergence arrangements for the HRA announced in January 2026. Report P6

What happens next

The HRA year-end overspend will be contained within HRA general reserves. Report P23, P43

An additional £0.3m HRA risk linked to the IT replacement programme will continue to be monitored through the implementation board. Report P24, P26, P47

Several capital projects have budget reprofiled into 2026/27, including Filwood Cultural Hub, Leinster Avenue, Cameron Centre and Major Block Refurb at Ropewalk House. Report P18, P53, P58

The money

  • £22.8m Revised General Fund Housing budget 2025/26 Report P8
  • £23.3m General Fund Housing forecast outturn Report P8
  • £0.5m General Fund Housing overspend variance Report P8, P10
  • £62.1m Revised General Fund Housing capital budget Report P13, P16
  • £54.3m General Fund Housing capital forecast at P10 Report P13, P16
  • £7.8m General Fund Housing capital slippage Report P13, P16, P17
  • £145.8m Revised HRA capital budget 2025/26 Report P49
  • £129.2m HRA capital forecast at P10 Report P49
  • £16.6m HRA capital slippage Report P49
  • £0.5m HRA forecast overspend at P10 Report P23
  • £0.3m HRA risk on IT replacement programme Report P24, P47
  • £2.2m HRA Repairs and Maintenance overspend (5.3% of budget) Report P31
  • £2.8m HRA Supervision and management overspend Report P35
  • £2.5m HRA Waking Watch saving Report P36
  • £1.5m HRA Depreciation and Impairment overspend Report P39
  • £2.3m HRA Income favourable variance Report P29
  • £9.8m New Build and Land Enabling Programme slippage Report P57
  • £15.6m Capital receipts received to P10 Report P63
  • £14.7m Right to Buy receipts received to P10 Report P63

Options considered

  • Chosen: Note the P10 finance forecast and appendices. Officer recommendation; report is for noting Report P1, P69, P71

Implications

  • Financial: General Fund Housing forecast overspend of £0.5m against a £22.8m revised budget, driven by salary costs, temporary accommodation and subsidy loss. Report P8, P10, P67
  • Financial: HRA forecast overspend of £0.5m, to be met from HRA general reserves at year-end. Report P23, P43
  • Financial: Capital programme slippage of £7.8m on General Fund and £16.6m on HRA, with several projects reprofiled into 2026/27. Report P13, P17, P49
  • Financial: 103 temporary accommodation units acquired so far under the Tackling Homelessness Transformation Programme, with further units in the pipeline. Report P18
  • Risk: Additional £0.3m HRA risk from the IT replacement programme, with costs and timelines still subject to change. Report P24, P26, P47
  • Equalities: Report is cross-priority and covers the whole of the council's Housing and Landlord Services, affecting tenants, leaseholders and homeless households. Report P75

Who and where

  • Council housing tenants Report P2, P3
  • Leaseholders Report P3, P46
  • Homeless households using Housing Options and Temporary Accommodation Report P2, P18
  • Private sector landlords and tenants in the Private Landlord Licensing scheme area Report P2, P4
  • Refugee resettlement households supported through the Local Authority Housing Fund Report P15

Timeline

  • End of January 2026 (Period 10): Forecast position reported against the 2025/26 approved budget Report P1
  • January 2026: Rent convergence arrangements for the HRA announced (covered in Appendix B) Report P6
  • February 2026: Additional Rough Sleepers Grant allocation announced (covered in Appendix A) Report P6
  • 31 March 2026: End of 2025/26 financial year; any HRA overspend to be contained within HRA general reserves Report P43
  • Early next financial year (2026/27): Further temporary accommodation units expected to complete; Filwood Cultural Hub, Leinster Avenue, Cameron Centre and Ropewalk House budgets reprofiled into 2026/27 Report P18, P53, P58
  • Nov 26: Practical Completion date now expected for the Cameron Centre new build Report P58

Plain English for the jargon

  • HRA: Housing Revenue Account, a ringfenced account funded by rents and service charges from council housing
  • General Fund: The council's main revenue account, covering services such as Housing Options, Private Sector Housing and Housing Delivery
  • P10: Period 10 of the financial year, in this case the end of January 2026
  • Right to Buy (RTB): Scheme allowing secure council tenants to buy their home at a discount, generating capital receipts for the HRA
  • Rent convergence: Arrangements announced in January 2026 affecting HRA rents, analysed in Appendix B
  • Waking Watch: Patrolled fire safety cover in residential blocks, usually a temporary measure while building safety works are carried out
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

It was RESOLVED that the Committee for Homes and Housing Delivery noted the report on the P10 forecast and associated appendices for Housing and Landlord Services.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

1. This report presents to the Homes and Housing Delivery Committee, the Housing and Landlord Services financial forecast at period 10 against the approved budget as at the end of January2026. The report is for noting. Evidence Base / Context

1. The Housing and Landlord function is a complex service area, split between the Housing Revenue Account (HRA) – a ringfenced account - and General Fund activities such as Housing Options (including Homelessness), Private Sector Housing (including Private Landlord Licencing schemes) and Housing Delivery. There are a variety of funding sources within the function which include: -

HRA • Tenants Rental Income • Leasehold Service Charges • Commercial Income • Revenue and Capital Grants

General Fund • Housing Benefit • Licensing Scheme Income • Grants

1 Version October 2025

OFFICIAL In addition to the standard period reporting, this report will also provide some analysis on the potential impact of both the additional Rough Sleepers Grant allocation announced in February 2026, and the rent Convergence arrangements for the HRA announced in January 2026 within Appendices A and B respectively.

General Fund

For 2025/26 the General Fund element of Housing and Landlord Services has a revised budget of £22.8 million. The forecast outturn is £23.3 million, resulting to an outturn variance of £0.5m Budget. This is shown in Table 1.

Table 1 Summary General Fund Housing Forecast Position 2025/26 Period 10

General Fund Housing is forecasting an overspend of £0.5m against the revise Budget. The key movements are driven by a combination of salary cost, Temporary accommodation expenses and subsidy loss.

Since P9, Housing Options has seen a small deterioration of £0.1m in forecasts to reflect a slight increase in demand, and Private and Accessible Homes is seeing a £0.4m increase as assumptions around salary recharges have been revised.

General Fund - Capital

The revised capital budget for General Fund Housing for 2025/26 is £62.1m. At P10, a forecast of £54.3m is reported, leading to an underspend variance of £7.8m.

Table 3: General Fund Housing Capital Programme Summary

Revised P10 P9 M’ment Budget F’cast Var F’cast P10-P9 £m £m £m £m PL30 - Housing Delivery 16.5 1.7 Programme 18.2 14.8 3.4 NH07 – Private Housing 5.5 4.9 0.6 4.9 0.0 PE06C – Local Authority Housing Fund (LAHF) – Refugee 1.5 0.0 Resettlement 1.5 1.5 0.0 2 Version October 2025

OFFICIAL GR19 – Tackling Homelessness Transformation Programme 36.9 33.1 3.8 36.6 3.5 Total 62.1 54.3 7.8 59.5 5.2

There is an overall current year slippage of £7.8m against the Capital Works Budget of £62.1m, an increased movement of £5.2m in forecast slippage compared to the forecast spend reported at P9 as detailed below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Rough Sleeper Grant FundingAppendix A 85 KB Download
PDF
Imapct of Rent convergene AnnouncementAppendix B 160 KB Download
PDF
Finance report updateReport 699 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
PG
Councillor Paul GogginCommittee Member, apologies
CG
Councillor Caroline GoochCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
AA
Councillor Al Al-MaghrabiCommittee Member, present as substitute
ST
Councillor Sibusiso TshabalalaCommittee Member, apologies
KB
Councillor Kerry BailesCommittee Member, present as substitute
DM
David McNultyOfficer, in attendance

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Finance report updateThis decision
  2. Q1/P3 Finance update reportNoted
  3. 2026/27 Quarterly Finance Report: P3/Q1Noted
  4. Q1 (P03) Finance UpdateDecided
  5. 2026/27 Quarterly Finance Report: P3/Q1Noted
  6. Finance report updateNoted

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Annual Cladding Remediation UpdateThe Committee Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies