Bristol City Council
Harbour Committee, Tuesday 23 June 2026 at 3.00pm

Long Term Opportunity for Redcliffe Wharf

Agreed Committee 4 papers

AI summaryBristol Harbour Committee approves nine-month exclusivity deal with BTQ LLP and Muse to draw up plans for the long-term redevelopment of Redcliffe Wharf and Phoenix Wharf.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNine month exclusivity with BTQ LLP/Muse
Money£516,000 returnedBrownfield Land Release Funding repaid March 2025
What happens nextDetailed proposal to CommitteeAfter exclusivity period ends
Who it affectsRedcliffe and Phoenix WharfHarbour Estate regeneration sites

What was decided

The Executive Director for Growth and Regeneration, with the Chair of the Harbour Committee, is authorised to enter a nine month exclusivity agreement with BTQ LLP and Muse covering Redcliffe Wharf and Phoenix Wharf, subject to the Harbour Authority's financial requirements and Section 123 best consideration. Report P33

A financial proposal and draft heads of terms will be brought back to the Committee for a decision on whether to proceed with a contractual arrangement. Report P34

The Committee noted that if an acceptable agreement is not reached within the exclusivity period, the site is to be offered on the open market by the most appropriate marketing method. Report P36

Why

The Harbour Authority must become self-funding by 2031 under the Bristol Harbour Strategy 2026 to 2031, and current income from rents, marine activities, car parking and events does not cover the cost of maintaining the City Docks. Report P9

Redcliffe Wharf and Phoenix Wharf are prominent waterfront sites that have been underused for many years, with several failed redevelopment attempts over the past 30 years. Report P5, P28

BTQ LLP is one of Europe's largest regeneration projects, aiming for at least 10,000 new homes, and its private sector partner Muse has a national track record in long-term regeneration with the public sector. Report P12, P16, P22

What happens next

BTQ LLP and Muse will work up a detailed financial proposal and draft heads of terms during the nine month exclusivity, with agreed milestone dates and review points. Report P25, P26, P35

Savills will carry out an independent assessment of the final proposal to check it meets the Council's Section 123 best consideration duty. Report P26, P54, P55

If the exclusivity lapses without agreement, the site is to be marketed on the open market, which officers estimate would add around 18 to 24 months before a new partner is appointed. Report P27, P31

The money

  • £516,000 Brownfield Land Release Funding awarded in December 2020 and returned in March 2025 after the Council terminated the previous Agreement for Lease Report P8

Options considered

  • Chosen: Enter a nine month exclusivity agreement with BTQ LLP and Muse to develop a detailed financial proposal and draft heads of terms. Muse is a credible delivery partner, the proposal aligns with the existing implemented planning consent, and exclusivity allows the Harbour Authority to secure long-term rental income while keeping competitive tension through an open market fallback Report P22, P25, P26, P28, P33
  • Rejected: Continue operating the site as it is now, taking short-term meanwhile enquiries only. Does not exploit the commercial potential of the site and leaves it underused Report P30
  • Rejected: Offer the site on the open market now. Would delay redevelopment further and put at risk the benefits of progressing with BTQ LLP and Muse, though it is the recommended fallback if exclusivity fails Report P31
  • Rejected: Progress the unsolicited high-level proposal from a specialist leisure operator. Savills concluded the proposal did not provide enough detail to justify progressing as an alternative to BTQ LLP and Muse Report P18, P20, P22

Implications

  • Financial: A long leasehold disposal is intended to generate long-term revenue to help the Harbour Authority reach a self-funding operating model by 2031, but no specific rent or premium is yet on the table. Report P2, P9, P10, P55
  • Legal: Any disposal must comply with Section 123 of the Local Government Act 1972 and demonstrate best consideration, with Savills providing independent verification of the final proposal. Report P26, P54, P55, P57, P58
  • Risk: Officers warn that a previous developer was terminated after the Council returned Brownfield Land Release Funding, and exclusivity is time-limited with clear milestones to manage the risk of another failed attempt. Report P8, P26, P28
  • Staffing: Finance, Legal, IT and HR confirmed no direct IT or HR implications, with engagement from finance and legal teams on the detailed proposal. Report P55, P56, P60, P61, P63
  • Equalities: An Equality Impact Assessment is appended to the report and the development is framed around inclusive access and public realm improvements. Report P40, P66
  • Climate: An Environmental Impact Assessment is appended, and the scheme is expected to align with BTQ LLP's wider sustainable infrastructure and public space goals. Report P12, P67

Who and where

  • Bristol Harbour Authority, which needs a self-funding operating model by 2031 Report P9, P52
  • BTQ LLP and Muse, selected as the proposed long-term development partner Report P16, P33
  • Existing tenants of Phoenix Wharf, including the Benjamin Perry Boathouse on a 60-year lease and the Former Fireboat Station tenant holding over on a 3-year lease Report P6
  • The CRSTS site compound currently occupying Redcliffe Wharf until early 2028 Report P6
  • Bristol residents and visitors, who would gain new housing, public realm and harbour access Report P38, P40, P41, P42

Timeline

  • December 2020: Council awarded £516,000 of Brownfield Land Release Funding for Redcliffe Wharf Report P8
  • March 2025: Council terminated the previous Agreement for Lease with Complex Developments Limited and returned the Brownfield Land Release Funding Report P8
  • March 2025: Economy and Skills Committee approved Redcliffe Wharf being progressed by BTQ LLP, subject to a land option and Section 123 best consideration Report P13
  • 24 April 2025: Land options completed between BTQ LLP and Council sites at Redcliffe Way, City Point and Bath Road; Redcliffe Wharf was not included in this package Report P14
  • January 2026: BTQ LLP selected Muse as its private sector development partner Report P16
  • February 2026: Initial high-level proposal received from BTQ LLP, Muse and Umberslade identifying Redcliffe Wharf and Redcliffe Way as early delivery sites with an estimated start on site in 2028 Report P17
  • March 2026: Savills appointed to assess the BTQ LLP/Muse proposal and an unsolicited leisure operator proposal Report P19
  • 6 May 2026: Growth and Regeneration EDM endorsed entering time-limited exclusivity with BTQ LLP/Muse rather than the unsolicited offer Report P20
  • 23 June 2026: Harbour Committee approved a nine month exclusivity agreement with BTQ LLP/Muse for Redcliffe Wharf and Phoenix Wharf Report P33
  • Early 2028: CRSTS site compound occupation of Redcliffe Wharf is required until this point Report P6
  • 2031: Target date for the Harbour Authority to establish a self-funding operating model under the Bristol Harbour Strategy 2026-2031 Report P9

Plain English for the jargon

  • BTQ LLP: Bristol Temple Quarter Limited Liability Partnership, the public-private regeneration partnership for the area west of Bristol Temple Meads
  • Section 123 Local Government Act 1972: Statutory duty requiring local authorities to obtain the best consideration reasonably obtainable when disposing of land
  • Harbour Authority: Bristol's Statutory Harbour Authority, responsible for operating and maintaining the City Docks and harbour estate
  • CRSTS: City Region Sustainable Transport Settlement, a government transport funding programme whose site compound currently occupies Redcliffe Wharf
  • AFL: Conditional Agreement for Lease, the type of agreement previously held with Complex Developments Limited and terminated in March 2025
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

The Harbour Committee RESOLVED to: 1. Authorise the Executive Director for Growth & Regeneration in consultation with the Chair of the Harbour Committee to enter into an exclusivity agreement with BTQ LLP/Muse for an initial period of nine months to allow time to develop a detailed financial proposal and draft heads of terms in respect of the long-term use of Redcliffe Wharf and Phoenix Wharf. This will be subject to meeting the Harbour Authority’s financial requirements and best consideration under Section 123 Local Government Act 1972. 2. Once the financial proposal and draft heads of terms have been prepared, the proposal will be brought back to Committee for a decision on whether to proceed with BTQ LLP/Muse and to progress with a contractual arrangement. 3. Note the exclusivity agreement will include agreed milestone dates and events to ensure a clear timeline for obligations and performance under the agreement. 4. Note in the event an acceptable agreement is not achieved within the exclusivity period, it is recommended that the site is offered through an open market process by way of the most appropriate marketing method.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Purpose of report

1. To seek approval to enter into an exclusivity agreement with Bristol Temple Quarter Limited Liability Partnership (BTQ LLP)/Muse in respect of the long-term use of Redcliffe Wharf and Phoenix Wharf.

2. The objective of the proposed exclusivity agreement is to agree terms that delivers early redevelopment and secures long-term revenue generation through a long leasehold disposal, that supports the Harbour Authority’s financial objectives.

3. To note that once terms have been prepared this will be brought back to Committee for a decision on whether to proceed with BTQ LLP/Muse and incorporate the site within BTQ.

Evidence Base:

1. Redcliffe Wharf and Phoenix Wharf are prominent waterfront regeneration sites located within the Harbour Estate and as such managed and operated by the Harbour Authority. The site includes heritage sensitive elements and has remained underutilised for many years. Over the past 30 years there have been several failed attempts to develop the site.

2. Redcliffe Wharf is currently being used for the CRSTS site compound, occupation is required until early 2028. There are two active tenancies on Phoenix Wharf. The Benjamin Perry Boathouse is let on a 60-year lease with 15 years remaining. The Former Fireboat Station is let on a 3-year lease, the tenant is currently holding over. Template approved October 25

OFFICIAL 3. In 2012 the Council entered into a Conditional Agreement for Lease (AFL) for Redcliffe Wharf with Complex Developments Limited who subsequently secured and implemented planning consent for a mixed use redevelopment scheme comprising 43 homes (including 3 affordable), 5,976 sqm office and ground floor commercial, retail use, 12 moorings, water bus stop and extensive high quality public realm (ref 18/06659/F).

4. In December 2020 the Council were awarded £516,000 of Brownfield Land Release Funding to facilitate the development. In March 2025 the Council terminated the Agreement for Lease and the Council returned all the Brownfield Land Release Funding.

5. The Harbour Authority is required to establish a self-funding operating model by 2031 as detailed in the Bristol Harbour Strategy 2026–2031. The Harbour Authority currently generates revenue from rents, marine activities, car parking and events which does not cover the true costs of maintaining the City Docks in an operational state and in a condition befitting its heritage status. The Harbour Authority therefore needs to identify and use any remaining underutilised land for commercial opportunity.

6. The Harbour Place Shaping Strategy identified opportunities, which included Redcliffe Wharf, for activation of underutilised sites through meanwhile uses pending longer term development. The disposal of the Redcliffe Wharf and Phoenix Wharfe sites, on a long leasehold basis, will secure future revenue returns for the Harbour Authority contributing toward the priority objective of establishing a sustainable operating model.

7. Redcliffe Wharf was originally included within the Temple West Masterplan which identified the importance of the site as a key connection point between Temple Meads West, Queen’s Square, the floating harbour and the city centre. The Masterplan identifies Brunel Mile as a primary travel route in and out of the area and Redcliffe Wharf plays a key role in enhancing this setting and improving the character of the area, alongside new residential development on Portwall Lane.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
01. Committee Report Template Final Oct 25Report 171 KB DownloadRead as text
PDF
Equality Impact Assessment: Template (May 25)Appendix B 230 KB Download
PDF
Environmental Impact Assessment: Template (Oct 25)Appendix C 109 KB Download
PDF
Long Term Opportunity for Redcliffe WharfReport 171 KB Download

At this meeting

Whole meeting

Who was there

10 of 17 attended
AB
Councillor Andrew BrownChair, present
PM
Councillor Patrick McAllisterVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
RE
Councillor Richard EddyCommittee Member, apologies
KD
Kathryn DavisCo-Optee, apologies
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
CB
Cliff BrandCo-Optee, present
JS
John SmithOfficer, in attendance

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Long Term Opportunity for Redcliffe WharfThis decision
  2. Compulsory Purchase of Long Term Empty PropertyApproved
  3. Proposed Pricing Strategy for Residential and Nursing Care for Adults under 65 years old with long term ImpairmentsApproved

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open