CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bristol City Council
Harbour Committee, Tuesday 23 June 2026 at 3.00pm

Bristol Harbour Authority Annual Report 2025-2026

Approved Committee 3 papers

AI summaryBristol Harbour Committee approves the Bristol Harbour Authority Annual Report 2025-2026, which recorded a £0.445m operating surplus and £1.620m in capital receipts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedHarbour Committee approved the report for publication and submission
Money£0.445m operating surplusPlus £0.494m dredging reserve, £0.171m general reserve, £1.620m capital receipts at 31 March 2026
What happens nextPublish and submit reportAs required under statutory and governance duties
Who it affectsHarbour users and cityResidents, businesses and visitors using the waterfront

What was decided

The Harbour Committee approved the Bristol Harbour Authority Annual Report 2025-2026, enabling its publication and submission as required. Report P7, P1

Why

Producing and approving the Annual Report is a statutory and governance requirement for the harbour authority. Report P4, P25

Finance supports approval as a statutory, governance and assurance document covering the 2025/26 financial position, with an operating surplus of £0.445m. Report P21

Approval provides transparency and accountability, supporting public confidence and effective scrutiny of harbour operations. Report P11

What happens next

Publish and submit the Annual Report as required by statutory duties. Report P1, P7

Any feedback from the Committee will be considered in future reporting and harbour management processes. Report P14

The Authority will continue working towards a financially self-sustaining operating model by 2031, with further capital funding sources under review. Report P22

The money

  • £0.445m Operating surplus for 2025/26 Report P21
  • £0.494m Reserve balance for dredging at 31 March 2026 Report P21
  • £0.171m General reserve balance at 31 March 2026 Report P21
  • £1.620m Capital receipts balance at 31 March 2026 Report P21

Options considered

  • Chosen: Approve the Bristol Harbour Authority Annual Report 2025-2026. Statutory and governance requirement; must be presented to and approved by the Committee Report P4, P7

Implications

  • Legal: The Annual Report is prepared in accordance with the Department for Transport's Ports Good Governance Guidance and the Port Marine Safety Code. Report P25
  • Financial: Approval does not constitute approval for any new expenditure, additional budget, borrowing, reserve drawdown, procurement, tariff change, capital scheme or delegation; any such proposals need separate approval. Report P23
  • Risk: The Harbour faces significant infrastructure, asset management and long-term sustainability risks; significant capital investment is needed for aging infrastructure and cannot be met by Bristol City Council alone. Report P22
  • Equalities: Harbour activities support inclusive access to the waterfront for residents, businesses and visitors through balanced management of recreational, commercial and community uses. Report P12
  • Climate: Report evidences progress in environmental management, navigational safety, and actions supporting biodiversity and climate resilience. Report P12
  • Other: Officers confirmed there are no IT or HR implications arising from the report. Report P27, P29

Who and where

  • Residents, businesses and visitors using Bristol Harbour and the waterfront Report P12
  • Bristol City Council as harbour authority and owner of the surrounding infrastructure Report P9, P22

Timeline

  • 31 March 2026: Reserve balances and capital receipts reported as at this date Report P21
  • By 2031: Target date for the Harbour to move to a financially self-sustaining operating model Report P22

Plain English for the jargon

  • Port Marine Safety Code: A Department for Transport code setting out the national standard for safe port and marine facility operations.
  • Ports Good Governance Guidance: Department for Transport guidance on how harbour authorities should be run, including the requirement to publish an annual report.
  • EqIA: Equality Impact Assessment, an appraisal of how a proposal affects people with protected characteristics.
  • EIA: Environmental Impact Assessment, an appraisal of likely environmental effects of a proposal.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

The Harbour Committee RESOLVED to: Approve the Bristol Harbour Authority Annual Report 2025-2026.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Purpose of report

1. To present the Bristol Harbour Authority Annual Report 2025–2026 to the Committee, summarising the Authority’s performance, governance, statutory functions, financial position, and key achievements over the reporting period, and to seek formal approval of the report for publication and submission as required.

Evidence Base

1. Bristol Harbour Authority Annual Report 2025–2026, including operational, financial, and governance performance information. 2. Statutory and regulatory reporting requirements applicable to harbour authorities. 3. Performance data, compliance records, and audited financial information contained within the report.

Alternative options considered

1. The Annual Report is a statutory and governance requirement and must be presented to, and approved by, the Committee.

Template approved October 25

OFFICIAL Officer Recommendations: -

1. That the Harbour Committee approves the Bristol Harbour Authority Annual Report 2025-2026.

Corporate Strategy alignment:

1. The Annual Report demonstrates how Bristol Harbour Authority activities support the Council’s Corporate Strategy by enabling safe and effective harbour operations, supporting sustainable economic activity, protecting the city’s maritime heritage, and contributing to wider regeneration, environmental resilience, and inclusive growth objectives.

City Benefits:

Approval of the Annual Report provides transparency and accountability for harbour operations, ensuring continued public confidence and effective scrutiny.

1. Equalities: Harbour activities support inclusive access to the waterfront for residents, businesses, and visitors through balanced management of recreational, commercial, and community uses. 2. Health: Safe management of the harbour environment promotes wellbeing through access to water-based recreation, active travel routes, and public spaces. 3. Sustainability: The report evidence’s progress in environmental management, navigational safety, and actions supporting biodiversity and climate resilience. 4. Social Value: Harbour operations contribute to local employment, tourism, cultural activities, and partnership working that strengthens the wider city economy and community outcomes.

Consultation Details:

1. This report is presented for noting and discussion by the Committee. As such, no formal consultation was required or undertaken in advance of publication. 2. The Annual Harbour Report reflects operational activity, performance and governance matters that have been subject to ongoing internal oversight and engagement with relevant stakeholders throughout the reporting period. Any feedback or issues arising from the Committee’s consideration of this report will be considered in future reporting and harbour management processes.

Background Documents:

1. Ports and marine facilities safety code - GOV.UK 2. A guide to good practice on port and marine facilities - GOV.UK

Revenue Cost £ Source of Revenue Funding Capital Cost £ Source of Capital Funding One off cost ☐ Ongoing cost ☒ Saving Proposal ☐ If yes - existing or new saving? N/A OR Income generation proposal ☐

Template approved October 25

OFFICIAL Professional comments section:

1. Finance Advice:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BHA Annual Report 2025-20261Appendix A 4.1 MB Download
PDF
Equality Impact Assessment: Template (May 25)1Appendix B 117 KB Download
PDF
Bristol Harbour Authority Annual Report 2025-2026Report 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AB
Councillor Andrew BrownChair, present
PM
Councillor Patrick McAllisterVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
RE
Councillor Richard EddyCommittee Member, apologies
KD
Kathryn DavisCo-Optee, apologies
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
CB
Cliff BrandCo-Optee, present
JS
John SmithOfficer, in attendance

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Bristol Harbour Authority Annual Report 2025-2026This decision
  2. Bristol Harbour Activated – Harbour Commercial ProspectusDecided
  3. Bristol Harbour Annual Report 2023/24Noted
  4. Bristol City Docks - Harbour Revision OrderApproved
  5. Bristol Harbour Festival 2023-2027Decided
  6. Bristol Heat Networks (heat network expansion and utilisation of the floating harbour to provide low carbon heat)Approved

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies