Bristol City Council
Harbour Committee, Tuesday 23 June 2026 at 3.00pm

Refurbishment Works to Existing New Cut Bridges and New Cut River Retaining Walls and Future Feasibility Studies to Manage Other New Cut Assets.

Noted Committee 2 papers

AI summaryBristol Harbour Committee notes progress on New Cut bridges and river wall programme, with cost estimates now exceeding approved capital by about £2.4m and a further funding paper going to the Transport and Connectivity Committee on 9 July.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted progress and backed continued delivery
Money£22,465,347 estimated walls costGrand total estimated cost for New Cut critical wall sites
What happens nextFunding paper to 9 July committeePaper being drafted for Transport and Connectivity
Who it affectsHighway users, residents, businesses194 river wall assets and 9 bridges on strategic routes

What was decided

The committee noted the update on project progress, covering completed works, works currently underway and the remaining programme. Report P70

The committee continued to support delivery of the New Cut River Wall stabilisation and New Cut Bridges refurbishment programme. Report P71

Why

The council has statutory duties as Highway Authority to maintain 194 identified river wall assets and the New Cut bridges, with 67 sites rated as a major corporate risk and 11 highest priority sites identified. Report P6, P7, P8, P9, P73

Multiple partial river wall failures have occurred due to accelerating deterioration from tidal ranges, the age of structures (over 200 years old), and a historic lack of routine maintenance. Report P10, P11

Significant hidden structural defects were found on bridges once decking was removed, particularly on Vauxhall Bridge, requiring far more extensive repairs than originally envisaged. Report P63, P67

What happens next

A further funding paper is being drafted for the Transport and Connectivity Committee to consider at its 9 July meeting, given scope increases and cost pressures. Report P67

Officers recommend sustained engagement with regional and central Government, including West of England Combined Authority and Bristol Infrastructure Programme routes, to secure additional capital funding. Report P13, P47, P52

Stabilisation and refurbishment works continue on remaining sites, with York Road permanent works and The Gateway due for completion in July and August 2026, and Vauxhall Bridge due in December 2026. Report P15, P58

The money

  • £20.071m Capital funding approved in principle for the New Cut Walls programme Report P22
  • £17,071,000 Total funding allocation spent to date on the New Cut Walls programme Report P33
  • £16,635,292 Overall final project capital budget for the New Cut Bridges CRSTS programme Report P56
  • £22,465,347 Grand total of estimated costs required on New Cut Walls to date Report P42
  • £2.4 million Immediate funding gap on walls after approved £20.1m against c.£22.5m estimated Report P86
  • £10 million per annum Proposed alternative capital investment over a five-year period FY28/29 to FY33/34 Report P48
  • £14.51M Total estimated project costs for New Cut Bridges refurbishment works Report P66
  • £20m to £30m Indicative replacement cost range for Vauxhall Bridge if demolished Report P63

Options considered

  • Recommended: Pursue central government grants via WECA and Bristol Infrastructure Programme to secure capital funding for the New Cut Walls. Would offer value for money and minimise corporate financial exposure Report P47
  • Alternative: Approved provision of £10 million per annum in capital investment over five years (FY28/29 to FY33/34) under a flexible risk-based approach. Supports proactive, ongoing management, improves resilience and optimises lifecycle costs Report P48
  • Rejected: Do not adopt the flexible risk-based funding strategy. Increased risk of catastrophic asset collapse, loss of life, highway closure, legal action and reputational damage Report P50

Implications

  • Financial: Cost estimates on the walls programme now stand at c.£22.5m against £20.1m approved, creating an immediate funding gap of c.£2.4m with further escalation risk. Report P86
  • Financial: Long-term unfunded liability could require c.£10m per annum over five years unless external funding is secured. Report P87
  • Risk: Without sustained investment there is a significantly increased risk of catastrophic asset collapse with potential loss of life and closure of strategic highway routes. Report P50, P51
  • Legal: No specific legal implications arising as the report is for noting only. Report P89
  • Equalities: An Equality Impact Assessment is attached as Appendix B. Report P95
  • Staffing: No HR implications identified. Report P92
  • Other: No implications on IT identified. Report P91

Who and where

  • Highway users and the public, with 194 identified river wall assets supporting key strategic routes in and out of the city Report P6, P73
  • Vessel owners operating within the Floating Harbour who require continuous, notified maritime access Report P77
  • Public transport passengers using routes such as Metrobus that depend on the affected highway network Report P77
  • Local neighbouring interest groups, including FRANC, to be kept informed of planned works Report P80
  • The council in its role as Highway Authority, facing potential corporate sanctions, criminal liability and reputational harm if assets fail Report P8

Timeline

  • June 2024: Bedminster Bridge wall completed Report P15
  • November 2024: York Road temporary works completed, permanent works begin in December 2024 Report P15
  • 15 April 2026: Ground investigations commenced on three newly discovered sites (Bristol Metal Spraying, Co-Op Wall, Gaol Ferry Rock Faces) Report P17, P18, P19
  • 9 July: Further funding paper to be considered by the Transport and Connectivity Committee Report P67
  • July 2026: York Road permanent works scheduled for completion Report P15
  • August 2026: The Gateway construction works and Bathurst Bridge full completion due Report P15, P66
  • December 2026: Vauxhall Bridge full completion due Report P58, P66
  • 31 March 2027: Original programme completion date for the New Cut Bridges CRSTS project Report P54

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a DfT capital funding programme
  • WECA: West of England Combined Authority, a potential source of capital funding
  • BIP: Bristol Infrastructure Programme, a council strategic partner delivery vehicle
  • MMO: Marine Management Organisation, responsible for licensing and regulating marine activities
  • OBC: Outline Business Case, a stage of project business case development
  • VRS: Vehicle Restraint System, added during bridge refurbishment works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Harbour Committee RESOLVED to: Note the update on project progress to date, including completed works, works currently underway and the remaining programme. Continue to support the delivery of the New Cut River Wall stabilisation and New Cut Bridges refurbishment programme.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Purpose of report

1. To provide an update on project progress to both the New Cut Walls and bridges, including remaining programme activities, works currently underway, emerging project risks, and newly identified asset condition issues.

2. To highlight to the Committee of the further ongoing capital funding required to stabilise the critical New Cut river walls and newly identified high-risk sections.

3. To highlight the ongoing structural and corporate risks associated with the New Cut river wall and bridge assets, and to confirm the need for escalation to regional and central Government to secure additional funding.

Evidence Base

New Cut river walls update

Following the collapse in early 2020 and subsequent repair of the river retaining wall at Cumberland Road, the council carried out a comprehensive condition inventory of all river wall assets. The Condition Report, completed in 2023, identified approximately 194 assets, including 67 sites assessed as posing a major corporate risk due to their role in supporting key strategic highway routes in and out of the city. Failure at any of these river wall locations would result in significant disruption and present a substantial health and safety risk to the public and the council.

As the designated Highway Authority, the council must discharge its statutory duties at all times. Any incident resulting in loss of life, injury, flooding, property damage, or closure of the public

1 highway would constitute a breach of these statutory duties, exposing the council to potential corporate sanctions, criminal liability, reputational harm, and long-term economic and environmental impacts.

The BCC Structures Team identified 11 No. separate wall sites as being of the highest critical priority, prompting development of a dedicated programme of work to stabilise these river walls.

Despite ongoing stabilisation interventions, multiple new instances of partial river wall failure have occurred, attributable to:

• Accelerating rates of deterioration due to high tidal ranges along the New Cut River. • The advanced age of the structures (over 200 years old). • A historic lack of routine ongoing maintenance.

This report sets out the scale of the issues, the short-term mitigation measures available, and the level of capital investment required to support both current and future works.

The funding required to mitigate the identified risks significantly exceeds current allocations. Officers therefore recommend sustained new engagement with regional and central Government to secure additional capital funding opportunities.

Stabilisation Work Progress on 11 No. identified critical sites:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EQIA: New Cut River Walls stabilisation and Repair ProjectAppendix B 162 KB Download
PDF
Refurbishment Works to Existing New Cut Bridges and New Cut River Retaining Walls and Future Feasibility Studies to Manage Other New Cut Assets.Report 182 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AB
Councillor Andrew BrownChair, present
PM
Councillor Patrick McAllisterVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
RE
Councillor Richard EddyCommittee Member, apologies
KD
Kathryn DavisCo-Optee, apologies
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
CB
Cliff BrandCo-Optee, present
JS
John SmithOfficer, in attendance

All 17 on the meeting page

On this subject at Bristol

Search all
  1. Refurbishment Works to Existing New Cut Bridges and New Cut River Retaining Walls and Future Feasibility Studies to Manage Other New Cut Assets.This decision
  2. Refurbishment Works to Existing “New Cut River” Bridges, and Future Feasibility Studies to Manage Other AssetsDecided

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies