CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bristol City Council
Strategy and Resources Policy Committee, Monday 13 July 2026 at 2.00pm

Translation and Interpreting Services - Corporate Framework Procurement

Approved Committee 3 papers

AI summaryBristol City Council's Strategy and Resources Committee approved a four-year corporate Translation and Interpreting Services framework worth up to £2.4m, replacing the current arrangement that expires on 23 October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTranslation and Interpreting Services, up to four years
Money£2.4m maximum£600k per year over four years
What happens nextProcurement to beginDirector authorised to award and run tender
Who it affectsCouncil services and residentsServices needing language support and residents needing access

What was decided

The committee approved procuring a corporate Translation and Interpreting Services framework for up to four years, with a maximum total contract value of £2.4m. Report P19

The Director: Policy, Strategy & Digital, in consultation with the Chair of the committee, was authorised to run the procurement and award the framework within the approved budget envelope. Report P20

The same Director was authorised to set up short-term interim contractual arrangements if needed, and to approve extensions or variations within the maximum budget. Report P21, P22

Why

The existing framework expires on 23 October 2026 and cannot be extended under procurement regulations, leaving the council without a compliant route to market for language services. Report P1, P3, P16

Translation and interpreting are needed to meet the council's public sector equality duty under the Equality Act 2010, supporting residents with limited English, British Sign Language users, and others with communication needs. Report P4, P25

Before the current corporate framework, services used about 90 different suppliers with no consistent quality assurance, DBS checks or performance management, creating legal, reputational and safeguarding risks. Report P10

What happens next

An accelerated procurement will be carried out to put a new framework in place before 23 October 2026, with a short-term interim arrangement used if a gap appears. Report P12, P21

The council will explore selective use of machine translation and other technology-enabled solutions, where suitable and proportionate, alongside quality assurance and safeguarding. Report P13

Future award and any contract variations will be made by the Director: Policy, Strategy & Digital within the £2.4m envelope. Report P20, P22

The money

  • £2.4m Maximum total contract value over four years for the new framework Report P1, P19, P32
  • £600k per year Equivalent annual maximum for the new framework Report P1, P9
  • £0.509 million Average annual spend through the existing framework over the last three financial years Report P34
  • approximately £322k Recorded spend in the second half of 2022/23 Report P7
  • £582k Recorded spend in 2023/24 Report P7
  • £430k Recorded spend in 2024/25 Report P7
  • £514k Recorded spend in 2025/26 Report P7

Options considered

  • Chosen: Procure a new corporate Translation and Interpreting Services framework. Provides a compliant, consistent, value for money approach with quality assurance, governance and continuity of service Report P17
  • Rejected: Do nothing and allow the framework to expire. Risk of service disruption, no compliant procurement route, and increased legal and equalities risk Report P14
  • Rejected: Spot purchasing or devolved commissioning by individual services. Inefficient, inconsistent, lower value for money, and increased governance and compliance risk Report P15
  • Rejected: Extend the existing framework. Not lawful under procurement regulations Report P16

Implications

  • Financial: The service operates on a cost-recovery model with 85% of income from recharges to internal service users, so contract cost increases are passed on to commissioning services rather than creating a direct budget pressure. Report P35
  • Financial: No savings are proposed through renewing the contract framework; the £2.4m envelope allows for inflation, demand growth and fluctuations in volume or complexity. Report P9, P34, P36
  • Legal: The substantial and any interim contract must be procured in line with the council's Procurement Rules to maintain a compliant route to market. Report P3, P11, P38
  • Equalities: The framework supports the council's public sector equality duty by reducing language barriers and improving access to services for residents with limited English proficiency and additional communication needs, including BSL users. Report P4, P25
  • Risk: Without a new framework by 23 October 2026, services would revert to ad hoc procurement from individual suppliers, reintroducing fragmented and unmanaged spending and associated legal, reputational and safeguarding risks. Report P3, P10, P11
  • Other: IT advice notes no current IT implications, with possible future options to use IT to deliver part of the service; HR advice notes no HR implications. Report P40, P42

Who and where

  • Residents with limited English proficiency across Bristol, described as one of the most linguistically diverse cities in England Report P4
  • British Sign Language users and residents with other communication needs Report P4
  • Internal council service areas that commission translation and interpreting work Report P32, P35
  • In-house casual interpreters and translators covering over 50 languages Report P5

Timeline

  • 23 October 2026: Current Translation and Interpreting Services framework expires and cannot be extended Report P1, P3
  • up to four years from award: Proposed maximum term of the new corporate framework Report P1, P9
  • since 2022: Hybrid in-house and external provider model has been in operation Report P6

Plain English for the jargon

  • TIS: Translation and Interpreting Service, the council's in-house first point of provision
  • BSL: British Sign Language
  • DBS: Disclosure and Barring Service checks required of suppliers
  • EqIA: Equality Impact Assessment, provided as Appendix B
  • EIA: Environmental Impact Assessment, provided as Appendix C
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the Strategy and Resources Committee: 1. Approved the procurement and establishment of a corporate Translation and Interpreting Services framework for a term of up to four years, with a maximum total contract value of £2.4m. 2. Authorised the Director: Policy, Strategy & Digital in consultation with Chair of the Strategy and Resources Committee to procure and award the Translation and Interpreting Services framework in line with the procurement approach and maximum budget envelope set out in this report. 3. Authorised the Director: Policy, Strategy & Digital to put in place any necessary short term interim contractual arrangements, if required, to ensure continuity of service until the new framework is in place. 4. Authorised the Director: Policy, Strategy & Digital to approve any extensions or variations in line with the terms of the contract, within the approved maximum budget envelope.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Purpose of report

To seek approval from the Strategy and Resources Committee to procure and establish a new corporate Translation and Interpreting Services (TIS) framework for a term of up to four years, with a maximum total contract value of £2.4m (£600k per year). The existing framework expires on 23 October 2026 and cannot be extended. A new framework is required to ensure legal compliance, continuity of services, and to meet the Council’s equalities and statutory obligations.

Evidence Base

1. The Council’s current Translation and Interpreting Services framework expires on 23 October 2026 and cannot continue beyond this date. Procurement regulations do not permit the Council to continue spending with external suppliers without a compliant contractual vehicle in place. Failure to have a replacement framework in place by this date would leave the Council without a lawful route to market for language services.

2. Translation and interpreting services are a core part of how the Council delivers accessible, equitable services to all residents. Bristol is one of the most linguistically diverse cities in England, with significant communities whose first language is not English. The Council has a public sector equality duty under the Equality Act 2010 to ensure services are accessible, and language access is a key enabler of that duty. Services are also used to support British Sign Language (BSL) users and other communication needs.

3. The Council’s Translation and Interpreting Service (TIS) operates as the first point of provision, drawing on a pool of in-house casual interpreters and translators covering over 50 languages. Where internal capacity cannot meet demand, for example for rare languages, high volume periods or specialist requests, TIS calls upon external providers through the corporate framework. This

OFFICIAL hybrid model has been in place since 2022 and provides a consistent, quality assured and cost- effective approach to meeting language needs across the organisation.

4. Recent financial data shows that total spend on translation and interpreting services has increased significantly since the implementation of the corporate framework. Recorded spend was approximately £322k in the second half of 2022/23, £582k in 2023/24, £430k in 2024/25 and £514k in 2025/26. This indicates current annual spend in the region of £500k to £600k.

5. Demand for translation and interpreting services has increased in recent years, reflecting both improved awareness across services and the Council’s commitment to providing accessible and inclusive services for all residents. This growth demonstrates that services are increasingly embedding equitable access into service delivery and responding more effectively to the needs of Bristol’s diverse communities. The proposed framework supports this continued improvement and aligns with the Council’s Corporate Strategy 2025–2030, particularly the priorities to make it easier for residents to access services and to tackle inequality by ensuring that language is not a barrier to engagement.

6. The proposed maximum contract value of £2.4m over four years (£600k per year) reflects current demand levels and provides appropriate headroom for inflation, increased service demand, and fluctuations in volume or complexity of requests. The framework is zero commitment, meaning the Council will only pay for services used.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact Assessment: TIS Corporate FrameworkAppendix B 168 KB Download
PDF
Environmental Impact Assessment: TIS Corporate FrameworkAppendix C 108 KB Download
PDF
Translation and Interpreting Services: Corporate Framework ProcurementReport 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 24 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, apologies
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present as substitute
NH
Nick HibberdOfficer, in attendance
PA
Pete AndersonOfficer, in attendance

All 24 on the meeting page

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies