Strategy and Resources Policy Committee, Monday 13 July 2026 at 2.00pm

Hengrove Park and Response to Golden Motion 10 March 2026

Noted Committee 6 papers

AI summaryBristol's Strategy and Resources committee noted past Hengrove Park decisions, supporting 350+ new homes in Phase 1 and a new sports strategy, while regretting a private Phase 1 land disposal hours before a Full Council debate.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted past decisions and new strategy; criticised disposal timing
Money£19.8m WECA securedWECA Development Infrastructure Fund to the council
What happens nextNew sports strategy later this yearBuilt Sport and Active Recreation Facility Strategy to be commissioned
Who it affectsHengrove Park and South BristolFuture residents, athletics community, wider South Bristol residents

What was decided

The committee noted past decisions that have secured delivery of 350+ new homes on combined Phase 1 land at Hengrove Park (the consented Phase 1b plus the former Phase 8 athletics track site). Report P16, P56

The committee noted the commissioning of an updated Built Sport and Active Recreation Facility Strategy later this year to drive new delivery and funding routes for sports provision. Report P40, P56

The committee expressed regret that the Phase 1 land disposal was taken only hours before Full Council was set to debate the issue, and called for higher transparency and accountability in democratic decision-making, regardless of members' views on the merits of the decision.

Why

The report responds to a Full Council Golden Motion Resolution of 10 March 2026 about delivery of new market and affordable homes on the decommissioned Whitchurch Athletics Track site and alternative athletics provision in South Bristol. Report P1, P2

It also sets out background on the wider Hengrove Regeneration Masterplan, the financial viability of Phase 1b, and existing and planned sport and physical activity provision across South Bristol. Report P2, P46

What happens next

A new Built Sport and Active Recreation Facility Strategy will be commissioned later this year to provide a comprehensive, up to date assessment of need across the city, including any requirement for additional specialist athletics provision in South Bristol. Report P40

Officers will continue engaging with national bodies such as Sport England and England Athletics on potential funding for alternative athletics provision, aligned with the new evidence base. Report P42, P44

The committee will continue to support the combined Phase 1 development of 350+ new homes through the existing Goram Homes and Vistry Group delivery structures, with the wider 1,435 home masterplan to follow. Report P16

The money

  • £19.8m West Of England Combined Authority Development Infrastructure Fund grant to the council Report P6
  • £9.2 Homes England Brownfield, Infrastructure and Land Fund loan secured by Goram Homes Report P6
  • £16m Approximate viability deficit (negative land value) for Phase 1b as a standalone phase Report P22
  • £12m Approximate enabling infrastructure obligation within Phase 1b Report P22
  • £1.5m - £3m Estimated cost to deliver a new replacement running track on retained Phase 8 land Report P52
  • £12- 29m Potential capital repayment risk to WECA and Homes England if delivery milestones are missed Report P50
  • £572,000 Public Health and Communities Committee approved funding for Whitehall track lifecycle works Report P32
  • 1,435 Total homes to be delivered at Hengrove Park under the Framework Agreement with Vistry Report P16

Options considered

  • Rejected: Retain Phase 8 for a replacement athletics track and reduce Hengrove Park by 140+ homes. Would breach the Framework Agreement with Vistry, leave Phase 1b unviable, risk £12-29m repayment to WECA and Homes England, and require costly redesign and possible new planning application Report P49, P50
  • Rejected: Replace the 140+ lost homes elsewhere on Hengrove Park. Phase 1b would remain unviable, the planned 22 acres of parkland and community sport provision would be lost, the LLP with Vistry would be breached, and redesign costs would be significant Report P51
  • Rejected: Build a new running track on retained Phase 8 land. Cost estimated at £1.5m-£3m, no capital identified, would dilute use from Whitehall, and does not meet national or local sport and recreation funding priorities Report P52, P54
  • Chosen: Continue with the combined Phase 1 (1b plus former 8) development of 350+ new homes as the consented scheme. Secures the wider 1,435 home masterplan, meets WECA and Homes England funding requirements, and enables viability through shared infrastructure across phases Report P16, P24, P27

Implications

  • Financial: Independent valuation confirms Phase 1b is unviable as a standalone phase, reducing expected capital receipts to the council and exposing it to market risk through its indirect interest in the LLP with Vistry. Report P72
  • Financial: Up to £12-29m of WECA and Homes England capital is at risk of repayment if delivery milestones for the 1,400+ homes are not met. Report P50, P6
  • Financial: The 15 year land Option Agreement with Goram Homes reduces the council's direct control over the timing and phasing of land disposals, which may affect cashflow and ability to optimise receipt values. Report P72
  • Risk: Market risk from house price fluctuations and cost inflation is shared through the council's indirect interest in the LLP, with phase by phase financial monitoring described as paramount. Report P72
  • Equalities: Distance, transport costs and limited connectivity to Whitehall Athletics Track can restrict access for South Bristol residents, particularly children, disabled people and lower income households. Report P34, P36
  • Climate: Hengrove Park is designed to deliver Net Zero homes with EPC A ratings, RIBA Climate Challenge targets, biodiversity net gain, and Building with Nature accreditation. Report P8, P10
  • Legal: Legal advice confirms the report is for noting only; any further key decisions will be taken under the council's constitutional requirements or existing delegated authority. Report P73
  • Other: Officer comments confirm no HR or IT implications arising from this report. Report P76, P77

Who and where

  • Future residents of around 1,435 new homes at Hengrove Park, including over 700 social rent and shared ownership homes Report P8, P16, P64
  • Athletes and the athletics community in South Bristol, particularly users of the former Whitchurch Athletics Track Report P29, P34
  • Goram Homes and Vistry Group as joint developers through the Phase 1 LLP Report P16
  • South Bristol residents, including children, disabled people and lower income households with limited access to the Whitehall Athletics Track Report P34, P36
  • Schools, clubs and community organisations using local parks, running routes and education-based sports facilities in South Bristol Report P40, P46
  • Campaigners petitioning for retention of the athletics track, who are to be given input into the new sports strategy Report P66

Timeline

  • 2010: Whitchurch Athletics Track formally decommissioned and closed Report P29
  • 18 December 2025: Goram Homes entered 15 year Option Agreement with the council for the Hengrove Park site Report P16
  • 23 February 2026: Council as sole Shareholder approved the Framework Agreement with Vistry Group and the formation of the Phase 1 LLP Report P16
  • 10 March 2026: Council approved disposal of Phase 1 land (Phase 1b and former Phase 8) to Goram Homes for 350+ new homes Report P16
  • 10 March 2026: Full Council Golden Motion Resolution on homes and athletics provision in South Bristol Report P1
  • 02 April 2026: LLP between Goram Homes and Vistry Group formally incorporated Report P16
  • 16 April 2026: Goram Homes signed the Framework Agreement with Vistry and the transfer of Phase 1 land was completed Report P16
  • Later this year: New Built Sport and Active Recreation Facility Strategy to be commissioned Report P40

Plain English for the jargon

  • WECA: West Of England Combined Authority
  • DIF: Development Infrastructure Fund, the WECA funding stream supporting the scheme
  • BILF: Brownfield, Infrastructure and Land Fund, the Homes England facility used by Goram Homes
  • Goram Homes: Bristol City Council's housing development company
  • LLP: Limited Liability Partnership, the joint vehicle between Goram Homes and Vistry Group for Phase 1
  • Phase 1b: Land with detailed consent for 209 new homes, now combined with former Phase 8 as Phase 1
  • Phase 8: Former Whitchurch Athletics Track site, now combined with Phase 1b as Phase 1
  • Golden Motion: Full Council motion requesting a committee response, here on homes and athletics provision
  • s73: Section 73 planning application, used to vary conditions on an existing consent
  • EPC A: Top energy performance certificate rating, the standard targeted for new Hengrove Park homes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That Strategy and Resources committee: 1. Noted the decisions already taken by the council and committee that have secured delivery of homes at Hengrove Park in accordance with the consented outline masterplan and the wider Hengrove Regeneration masterplan and support the continued development of the combined Phase 1 land to deliver 350+ new homes. 2. Noted the commissioning of an updated Built Sport and Active Recreation Facility Strategy which will drive new delivery and funding routes for new sports provision for the City and will help inform the delivery of new sports and leisure provision as part of Hengrove Park. The Committee regrets that a behind-closed-doors decision to dispose of the Phase 1 land (which constitutes the consented Phase 1b land and the Phase 8 land, the latter being the Athletics track site), only hours before Full Council was set to debate the issue. Irrespective of members’ views on the merits of the decision, the Committee believes the Council should aim for a higher degree of transparency and accountability in democratic decision-making processes.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Purpose of report

1. To respond to the Full Council Golden Motion Resolution on 10 March 2026 (Appendix A1) around the delivery of new market and affordable homes on the site of the decommissioned Whitchurch Athletics Track and provision of alternate athletics facilities in South Bristol

2. To provide a background to the wider Hengrove Regeneration Masterplan, decommissioning of the Whitchurch Athletics Track and proposals for housing delivery and sports provision at Hengrove Park, including arrangements for land disposal and financial viability of the development, and providing insight into wider sports provision for South Bristol

Evidence Base:

Background to delivery of Hengrove Park 1. The development of Hengrove Park comes at the end of a decade of investment and project delivery through the Hengrove Regeneration Masterplan (the Masterplan). This formed part of a long term, place-based approach to improving health, wellbeing, housing delivery and community infrastructure in South Bristol, alongside major public and private investment in transport, health, education, employment and leisure infrastructure. Quite uniquely for a major regeneration project this infrastructure has preceded the housing delivery.

2. The wider Masterplan and outline application for Hengrove Park were advised by the Hengrove and Whitchurch Park Neighbourhood Plan. A chronology of the delivery of the masterplan can be found at Appendix A2. which includes details of the public funding supporting delivery. Key to note Template approved October 25

OFFICIAL is public investment from the West Of England Combined Authority Development Infrastructure Fund (DIF) to the council of £19.8m (Appendix A3) and a £9.2 loan secured by Goram Homes from the Homes England Brownfield, Infrastructure and Land Fund (BILF) to help cash flow early infrastructure delivery. Key Infrastructure and BCC Funding into delivery of Hengrove Park Project / Workstream External Funding Of which BCC Risk of repayment to external funder source - spend to Investment funders External date / £ms £ms drawn down Outline Planning and enabling (2015- - - - 1.7 No 17) Outline Planning and enabling (2019) - - - 2 No Rebuild and expansion of Perry Court - - - 10 (CIL) No Primary School Relocation/ Provide New Facilities St OPE6 LRF 2.7 2.7 1 Yes at risk of repayment if non Bernadettes Rugby Club (also inc delivery of homes £600k WP3 DIF) Relocation/ Provide New Facilities - - - 0.5 No Scout Hut WECA DIF WP1: Junction WECA DIF 7.1 7.1 - Yes at risk of repayment if non Improvements delivery of homes. WECA DIF WP2: Bookends public WECA DIF 2.6 2.6 - No realm and highways WECA DIF WP3: Enabling works WECA DIF 10.1 1.6 - £5.1m ‘non-repayable grant’ at Hengrove Park ph1 risk of repayment if non delivery of homes. Other £5m is ‘repayable grant’. Homes England Infrastructure loan HE BILF 9.2 0.7 - Yes – entirely repayable (Spend for the energy centre, park works & commitments to date prescribed in detailed planning and include Action sports Action sports demo & compound demolition/compound and the (currently being partially repurposed energy centre order is going to for van dweller meanwhile use) the Hengrove Park LLP for approval.) Total capital with repayment 29.1 12.1 requirements / clawback Nb: Figures in bold indicate funding at risk of clawback in the event of non-delivery, or loans to be repaid from the sales of the new homes. Figures as at 15/06/26.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Golden Motion Sport 10 March as PassedAppendix A1 79 KB Download
PDF
Hengrove Master Plan and Hengrove Park timeline V1Appendix A2 6 MB Download
PDF
WECA DIFAppendix A3 2.5 MB Download
PDF
Hengrove Park: Original Development Phasing PlanAppendix A4 597 KB Download
PDF
Hengrove Park Draft Phasing Plan 2026Appendix A5 7.3 MB Download
PDF
Hengrove Park and Response to Golden Motion 10 March 2026Report 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 24 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, apologies
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present as substitute
NH
Nick HibberdOfficer, in attendance
PA
Pete AndersonOfficer, in attendance

All 24 on the meeting page

On this subject at Bristol

Search all
  1. Hengrove Park and Response to Golden Motion 10 March 2026This decision
  2. Overview of Hengrove Park Delivery Approach, and Approval to Draw Down WECA DIF Funding Award for Enabling InfrastructureNoted
  3. Hengrove Park Leisure Centre: Parkwood Community Leisure conversion to Lex Leisure Community Interest Company (CIC)Decided
  4. 21/00531/P - Hengrove Leisure Park, Hengrove WayApproved
  5. Funding for Hengrove Park Enabling Works (Highways Junctions and Primary School)Approved
  6. Hengrove Leisure Centre: Parkwood Community Leisure Conversion to Lex Leisure Community Interest Company (CIC)Decided

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies