AI summaryBristol City Council approved procurement of a corporate payment solution contract worth up to £15m over three years to distribute financial assistance to low-income households via vouchers or cash.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpend and procurement of payment solution contract authorised
MoneyUp to £15mOctober 2026 to September 2029, about £5m a year
What happens nextProcure and award contractExecutive Director of Resources to lead, new contract in place before October 2026
Who it affectsLow-income householdsIncludes Free School Meals families, homeless, asylum seekers

What was decided

The committee approved the spend and procurement of a contract to deliver a corporate payment solution to low-income households across a variety of council services. Report P12

The committee authorised the Executive Director of Resources, in consultation with the Chair of the Strategy and Resources Committee, to procure and award a contract or contracts for emergency payment vouchers. Report P14

Why

The existing voucher contract expires in October 2026 and needs to be replaced before then. Report P8

Central government wants future grants from the Crisis and Resilience Fund paid through a cash first approach, so the new solution must allow both vouchers and cash withdrawals if Members agree. Report P4

The contract would support several existing services that award emergency grants, including the Crisis Payment scheme, the Homelessness Assistance fund, Free School Meals holiday vouchers, and support for people with no recourse to public funds or seeking asylum. Report P3

What happens next

The Executive Director of Resources will run the procurement and award a contract or contracts, with social value built into the evaluation. Report P14, P19

Procurement must be carried out in line with the Procurement Act 2023 and the council's own procurement rules, with legal services advising. Report P32

The money

  • up £15m Estimated total contract value, October 2026 to September 2029, emergency payment vouchers Report P14, P27, P29
  • up to £5m per year, for three years Top end annual estimate across all covered services Report P1, P7, P29
  • c£4m to Free School Meals children, per year Estimated annual outlay within the £5m figure Report P7
  • £1m for other services Estimated annual outlay within the £5m figure Report P7

Options considered

  • Rejected: Make all payments by BACS or cash. Not suitable for all households that would receive a grant, and would add administrative time and cost Report P9

Implications

  • Financial: Finance advice states there is no expected budget pressure; support expenditure and administrative costs will sit within existing approved budget envelopes and available funding streams, mainly the Crisis and Resilience Fund. Report P29, P30
  • Legal: The procurement must comply with the Procurement Act 2023 and the council's procurement rules; legal services will advise on the process and resulting contracts. Report P32
  • Equalities: An Equality Impact Assessment has been prepared as Appendix B and is part of the background documents. Report P41, P25
  • Climate: An Environmental Impact Assessment has been prepared as Appendix C. Report P42
  • Risk: A Decision Risk Assessment has been prepared as Appendix D. Report P43
  • Staffing: HR advice is that there are no HR implications from the report. Report P36
  • Other: Any contract awarded will include an appropriate social value evaluation in the final scoring. Report P19

Who and where

  • Low-income households receiving emergency grants from the council Report P1, P3
  • Children eligible for Free School Meals who receive holiday vouchers via the Crisis and Resilience Fund Report P3, P7
  • Households receiving support through the Homelessness Assistance fund Report P3
  • People with no recourse to public funds or seeking asylum who receive assistance Report P3

Timeline

  • 27 April 2026: Legal Team Manager comment provided Report P33
  • 28 April 2026: IT Lead Enterprise Architect comment provided Report P35
  • 08 May 2026: Finance Business Partner comment provided Report P31
  • 11 May 2026: HR Manager comment provided Report P37
  • October 2026: New contract period to begin; existing contract expires Report P8, P14
  • September 2029: End date of the approved contract period Report P14

Plain English for the jargon

  • Crisis and Resilience Fund (CRF): Central government funding that local authorities are expected to distribute using a cash first approach.
  • BACS: Bankers' Automated Clearing Services, the system used for electronic bank-to-bank payments in the UK.
  • No Recourse to Public Funds (NRPF): A condition on some people's immigration status that restricts their access to most public welfare benefits.
  • EqIA: Equality Impact Assessment, an analysis of how a proposal may affect people with protected characteristics.
  • EIA: Environmental Impact Assessment, an analysis of how a proposal may affect the environment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the Committee for Strategy and Resources: 1. Approved the spend and procurement of a contract to deliver a corporate payment solution to low [1] income households, to fulfil the council’s need, via a variety of services. Contractual: 2. Authorised the Executive Director of Resources in consultation with Chair of Strategy & Resources Committee to take all steps required to procure and award a contract or contracts to provide emergency payment vouchers at an estimated value of up £15m from October 2026 to September 2029.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Purpose of report

1. To seek approval to procure and award a corporate payment solution, of either vouchers and/or cash, to a value of up to £5m per year, for three years, to assist the distribution of financial assistance to low-income households.

Evidence Base

1. The council provides various services that award grants to low-income households in emergency need. These could (potentially) include services such as; the Crisis Payment scheme (previously known as Local Crisis and Prevention Fund), Homelessness Assistance fund, Free School Meals vouchers (in school holidays via the government’s Crisis Payment Fund - CRF), and to those with No Recourse to Public Funds assistance/seeking asylum.

2. Payments are currently awarded by way of supermarket vouchers, which can be used in all major supermarkets by choice of the citizen throughout the city, but central government want local authorities to award future grants from the CRF via a ‘cash first’ approach. Therefore, any future contract will need to potentially award grants either by voucher or a payment mechanism that allows citizens to extract cash, if this approach is agreed by Members.

3. Council budgets in respect of these services are known in respect of CRF, but for other services are subject to change, especially given the increased financial pressures. The need for a payment solution however continues for existing services and potentially others, into the future, even if the values change.

Template approved October 25

OFFICIAL 4. The request of a contract for up to £5m per year for three years, is mainly estimated based on CRF funding for the next three years and an associated outlay of c£4m to Free School Meals children, per year, and £1m for other services, to maintain current demand. The £5m quoted is a top end estimate, with no commitment to spend this amount.

5. The existing contract expires in October 2026, so a new solution will need to be in place before then.

Alternative options considered

1. All payments to be made by BACs or cash. This has been rejected, as is not suitable for all households who would receive a grant and the associated administrative time and cost.

Officer Recommendations:

That the Committee for Strategy and Resources:

1. Approve the spend and procurement of a contract to deliver a corporate payment solution to low- income households, to fulfil the council’s need, via a variety of services.

Contractual:

2. Authorise the Executive Director of Resources in consultation with Cllr Dyer to take all steps required to procure and award a contract or contracts to provide emergency payment vouchers at an estimated value of up £15m from October 2026 to September 2029.

Corporate Strategy alignment:

1. Aids priority 2: Supporting children’s, families’ and adults’ health and wellbeing.

City Benefits:

1. The successful award of these contracts will allow the supplier, on behalf of Bristol City Council, to assist low-income families with food and fuel poverty. Any payment will also contain wrap around support and have positive impacts on reducing inequality and improving health and sustainability.

2. Any contract awarded will be also include an appropriate social value evaluation to any final scoring.

Consultation Details:

Consultation has taken place with the Procurement Team and internal and external partners who currently benefit from this provision.

There has also been a variety of soft market testing, and experience taken from similar previous procurement exercises.

Template approved October 25

OFFICIAL Background Documents:

1. 10.1 Report - Procurement of payment vouchers.pdf

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate payment solution to low-income households Equality Impact Assessment: TemplateAppendix B 103 KB Download
PDF
Corporate payment voucher scheme Environmental Impact AssessmentAppendix C 146 KB Download
PDF
Decision Risk Assessment: corporate paymentAppendix D 252 KB Download
PDF
Corporate Payment Solution to Low-Income HouseholdsReport 124 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 24 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, apologies
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present as substitute
NH
Nick HibberdOfficer, in attendance
PA
Pete AndersonOfficer, in attendance

All 24 on the meeting page

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies