Resolved
The Strategy and Resources Committee noted the report.
AI summaryBristol City Council's Strategy and Resources Committee noted the Q1 2026/27 Corporate Risk Report, which lists 14 strategic risks with highway maintenance and HRA stock compliance at the highest score of 28, as at 5 June 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
The Strategy and Resources Committee noted the report.
Non-key Decision Committee Report
PURPOSE: Non-key decision update report
COMMITTEE – Strategy and Resources Committee
DATE: 13 July 2026
TITLE: Q1 2026/27 Corporate Risk Report Officer presenting the report: Aldo Zanetti Title: Risk Manager Committee Chair: Cllr Tony Dyer Executive Director lead: Andy Rothery: Executive Director for Resources
Purpose of Report: The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q1 2026/27. Please see appendix A for the full Corporate Risk Register and the movement of risks over three consecutive periods.
Evidence Base / Context
1. The Council’s Risk and Assurance Policy requires the Corporate Leadership Board (CLB) and relevant Policy Committee(s) to perform quarterly reviews of our Corporate Risks. Where possible, quarterly reporting periods are aligned with financial year calendar, however it is not always possible to achieve this alignment. The risk review for Q1 2026/27 reports on risk activity since 10th March 2026, being the date of the last CLB risk review.
2. The Corporate Risk Report (CRR) is a key document in the council’s approach to the management of risk; it captures strategic risks set out in the Corporate Strategy 2025-2030. It also provides a context on how Directorates perform their high-level risk assessments and is used to inform business planning, budget setting, transformation, and service delivery.
3. The CRR provides assurance to management and Members that Bristol City Council’s significant risks have been identified, and arrangements are in place to mitigate risks to agreed tolerance levels. It should be noted that ‘risk,’ by definition, includes both threats and opportunities, which is reflected in the CRR.
4. Ensuring Service Risk Registers (SRR), Directorate Risk Reports (DRR) and Corporate Risk Reports (CRR) are soundly based helps council to demonstrate it is anticipating and managing key risks and to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
5. The registers and reports are a management tool. They need regular review to ensure that the occurrence of obstacles or events that may put individual’s safety at harm, impact upon service delivery and the council’s reputation are minimised, opportunities are maximised and when risks happen, they are managed effectively to minimise the impact.
6. The CRR summary of risks is attached to this report at Appendix A1 and is the latest position following a review by managers and Directors. The risks in Appendix A1 are presented in the order of severity, 1
OFFICIAL starting with the highest scoring risks followed by lower scoring risks.
Summary of Corporate Risks:
7. Further programme of work with clear instructions to colleagues was undertaken to review and revise each CRR/DRR risk description, internal controls, mitigation plans and governance. The scope of this work included, where possible, the identification of new risks and a fresh look to confirm ongoing risks are current along with the actions to mitigate the risks.
8. Executive Directorate members reviewed their all their risks on during May 2026 to form the current CRR. CLB and policy committees are asked to accept the attached CRR as a working summary report of the critical and significant risks from the Service Risk Registers.
9. The Q1 2026/27 Corporate Risk Report 5th June 2026 contains 14 risks (see Appendix A for further detail):
A summary of risks for this reporting period are set out below:
Critical Threat Risks
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q1 Corporate Risk Report 26/27Report | 599 KB | DownloadRead as text |
Follow Strategy and Resources Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... | Noted | Open |
| 12 Oct 2026 | Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... | Noted | Open |
| 12 Oct 2026 | Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... | Approved | Open |
| 12 Oct 2026 | Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... | Approved | Open |
| 12 Oct 2026 | Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.