Strategy and Resources Policy Committee, Monday 13 July 2026 at 2.00pm

Print and Mail Re-procurement and Approved Budget

Approved Committee 3 papers

AI summaryBristol City Council's Strategy and Resources Committee has approved raising the approved spend on the Xerox Print and Mail contract to £17.8m and a 12-month extension to 31 March 2028, ahead of a full re-procurement for a new five-year deal.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedXerox contract spend limit raised to £17.8m, extended to 31 March 2028
Money£17.8m approved spend; £6.3m additionalUp to 31 March 2028; not a request for new budget
What happens nextFull re-procurement exerciseNew five-year contract to begin 01 April 2028
Who it affectsNot stated

What was decided

The committee authorised increasing approved spend on the Print and Mail contract with Xerox to £17.8m for the period up to 31 March 2028. Report P9

Delegated authority was given to the Executive Director, Growth and Regeneration to put in place a 12-month extension to the current Xerox contract to 31 March 2028 under improved terms. Report P9

The committee noted that the service will run a full re-procurement exercise to support a new five-year contract starting 01 April 2028. Report P9

Why

The current five-year Xerox contract ends on 31 March 2027, and a 12-month extension is needed to give time to re-procure, particularly as additional work such as Clean Air Zone printing was not in the original costing. Report P3, P5, P24

Royal Mail costs have risen 137% since 2020, a further £339k was spent on additional printers, and a £3.9m Clean Air Zone printing requirement was not forecast in the original business case. Report P3

Finance and legal advice confirm the £6.3m increase is within budget and that variations under the Public Contracts Regulations 2015 support the change, with a Regulation 72(3) notice to be published. Report P22, P23, P27, P28, P29

What happens next

The service will run a full open-market re-procurement exercise for Print and Mail, aiming to bring savings forward in June 2027 as part of the savings recovery plan. Report P4, P9, P24, P25

The Executive Director, Growth and Regeneration will use delegated authority to vary the current contract with Xerox on improved terms to cover the period to 31 March 2028. Report P9

The service is expected to return to the committee with the results of the tender process and to drive digitisation across council departments during the extension. Report P4, P9, P25

The money

  • £17.8m New total approved spend on the Xerox Print and Mail contract to 31 March 2028 Report P3, P22
  • £6.3m Additional approval being sought above the current £11.5m limit on Proactis Report P19, P22
  • c.£10.4m Spend on the Xerox contract from 1 April 2022 to 1 April 2026 Report P3, P22
  • £3.7m Forecast spend for 2026/27, taking the total to a forecast £14.1m by 31 March 2027 Report P3, P22, P24
  • £7.4m Forecast spend over 2026/27 and 2027/28 combined Report P22
  • £3.9m Estimated Clean Air Zone printing cost on the contract to 31 March 2028 Report P3
  • £339k Additional spend committed to increase the number of printers to meet service requirements Report P3
  • £1.7m Net budget within the centralised Print and Mail cost centre covering 2026/27 and 2027/28 Report P22
  • £2.0m Forecast recharge contributions from other budgets, such as CAZ and the HRA Report P22

Options considered

  • Chosen: Extend the current Xerox contract by 12 months to 31 March 2028 with higher approved spend. Allows time to re-procure and avoids a gap in provision or breach of contract risk Report P3, P9
  • Rejected: Terminate the current Xerox contract once the £11.5m Proactis limit is reached. Risks legal challenge for breach of contract, financial penalties, a gap in provision, and reputational damage Report P6

Implications

  • Financial: The £6.3m increase is not a request for additional budget; annual £3.7m cost is covered by £1.7m net budget and £2.0m of recharge contributions, with spend to be monitored. Report P22, P23
  • Legal: The original contract was procured under the Public Contracts Regulations 2015; the increase relies on Regulation 72, which limits variations to 50% of the original £11m contract value, and a Regulation 72(3) notice must be published. Report P27, P28, P29
  • Equalities: An Equality Impact Assessment is listed as an appendix to the report. Report P38
  • Climate: The re-procurement and digitisation aims to reduce print volumes, cut use of natural resources, lower vehicle movements for mail delivery, and reduce congestion and carbon emissions. Report P4, P11, P13, P15
  • Risk: Finance notes the service has no approval to overspend and expenditure should be monitored and corrected if needed, given variable contract costs based on activity. Report P23
  • Staffing: HR advice records no HR implications from the report. Report P33, P34
  • Other: IT is supportive of the report, noting that any change in contract and resulting technology change will take time to implement. Report P31, P32

Who and where

  • Bristol City Council departments using Print and Mail services, including the Clean Air Zone and Housing Revenue Account Report P3, P22
  • The current supplier, Xerox, whose contract is being extended and varied Report P3, P9
  • Future bidders for the new five-year Print and Mail contract beginning 01 April 2028 Report P9
  • Council service users, who may see more digital communication channels during the extension Report P4, P9

Timeline

  • 1 April 2022 to 1 April 2026: Backwards-looking contractual spend of c.£10.4m on the Xerox contract Report P3, P22
  • 2026/27: Forecast contract spend of £3.7m Report P3, P22
  • 31 March 2027: Current five-year Xerox contract expires Report P3, P5
  • June 2027: Service intends to put forward savings as part of the savings recovery plan Report P4
  • 31 March 2028: End of the 12-month extension period for the current Xerox contract Report P3, P9
  • 01 April 2028: New five-year Print and Mail contract expected to begin Report P9

Plain English for the jargon

  • CAZ: Clean Air Zone, the council's income-generating scheme whose printing was not in the original contract costing
  • Proactis: The council's procurement register, which currently shows an £11.5m contract spend limit
  • Regulation 72: A rule under the Public Contracts Regulations 2015 that sets out when and how existing contracts can be modified, including a 50% limit on the value of variations
  • HRA: Housing Revenue Account, a budget area forecast to contribute £2.0m of recharges
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That the committee for Strategy and Resources: 1. Authorised the increase in approved spend against the Print and Mail contract to £17.8m for the period up to 31 March 2028. 2. Provided delegated authority to the Executive Director, Growth and Regeneration to affect a 12-month extension to the current Xerox contract to cover the period up to 31 March 2028 under improved terms. 3. Noted that the service will undertake a full re-procurement exercise to support a new five-year contract beginning on 01 April 2028.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Purpose of report

1. We want to provide committee with information about the future procurement of Print and Mail functions and seek approval to reprocure Print and Mail services following the end of the current contractual arrangements 2. We are seeking authorisation to increase the approved spend on the current Print and Mail contract with Xerox and extend the current contract to cover the period up to 31 March 2028

Evidence Base:

1. The service wishes to seek a 12-month extension to the existing Xerox contract covering the period up to 31 March 2028 to allow enough time to undertake a full re-procurement exercise. This would take the total approved spend request against the contract to £17.8m. 2. The current spend to date 01 April 2026 on the Print and Mail Xerox contract is c.£10.4m 3. The current 5-year contract with Xerox expires on 31 March 2027 with the current forecast spend to be £3.7m for 2026/27 taking the total spend to 31st March 2027 to a forecast of £14.1m. 4. Clean Air Zone (CAZ) printing activity was not factored into the original costing for the contract. It is estimated CAZ would total £3.9m of contract spend to 31 March 2028. 5. The CAZ is income generating. This contract spend is necessary in order to recover CAZ income. 6. It should also be noted that since 2020 there has been a 137% increase in Royal Mail costs which were not forecast in the original business case. 7. In addition, a further £339k of spend was committed in response to increasing the number of printers to meet service requirements. Template approved October 25

OFFICIAL 8. Whilst undertaking the re-procurement exercise it is the intention of the service to drive digitisation across council departments in an effort to reduce spend. The service would be looking to put forward savings in June 2027 as part of the savings recovery plan. 9. The procurement exercise will seek to continue the council’s journey to digitalisation. This will enable different avenues of communication with service users and deliver efficiencies

A key decision is therefore required in order to pay the current supplier [Xerox] for at least the remainder of the contract term [up until 31 March 2027].

Alternative options considered

1. Terminate the current contract with Xerox once the contract spend limit (£11.5m) on Proactis has been reached. This would risk incurring legal challenge for breach of contract and potentially financial penalties. It is highly likely there would be a gap in provision of Print and Mail in the time taken to re-procure a new contract and risks a high degree of reputational damage for Bristol City Council.

Officer Recommendations:

That the committee for Strategy and Resources:

1. Authorises the increase in approved spend against the Print and Mail contract to £17.8m for the period up to 31 March 2028. 2. Provides delegated authority to the Executive Director, Growth and Regeneration to affect a 12- month extension to the current Xerox contract to cover the period up to 31 March 2028 under improved terms. 3. Notes that the service will undertake a full re-procurement exercise to support a new five-year contract beginning on 01 April 2028.

Corporate Strategy alignment:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Print and Mail EqIA 2024Appendix B 214 KB Download
PDF
Print and Mail EIA July 2026Appendix C 145 KB Download
PDF
Print and Mail Re-procurement and Approved BudgetReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 24 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, apologies
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
DW
Councillor David WilcoxCommittee Member, present as substitute
NH
Nick HibberdOfficer, in attendance
PA
Pete AndersonOfficer, in attendance

All 24 on the meeting page

On this subject at Bristol

Search all
  1. Print and Mail Re-procurement and Approved BudgetThis decision
  2. Print and Mail Strategic ReviewApproved
  3. Print and Mail Contracts ReviewApproved
  4. Procurement of Print and Mail ServicesApproved
  5. Facilities Management Futures - Print and Mail ServicesApproved

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open