Cabinet: 1. Noted the progress made to date in relation to the roof remediation scheme; and 2. Approved the submission of a business case to the North West Construction Hub (NWCH) requesting that a direct award be made to ISG for the Millwood expansion project.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1Millwood School is a primary special school accommodating pupils aged 2-11 with very complex medical needs; severe learning difficulties and delays; autism; challenging behaviour; epilepsy; communication difficulties; sensory and multi-sensory impairments.
1.2In 2010 a replacement building was designed to provide the school with facilities based on a design comprising a central hub, three teaching wings and a hydrotherapy pool. The building was constructed in 2011/12 under a design and build contract by ISG Ltd. The Council commissioned the construction contract and funded it utilising a number of capital grants.
1.3Due to increased demand for specialist provision, additional capacity was created in 2019 through a modest extension under a different contractor. There are currently 161 pupils on roll at the school. Continuing demand pressures requires further additional specialist capacity to be constructed at the school.
1.4There have been ongoing issues with the building linked to the original design and construction, in particular with the roof. Following extensive investigation by specialist structural engineers, and ongoing discussions with ISG Ltd, a full programme of remediation has been developed.
1.5In 2022 ISG commenced a substantial roof replacement scheme at the school, initially focused on the hydrotherapy pool, with phased works to the entrance, hub and three wings. The phasing needs to have regard to the operational needs of the school and is therefore planned to be completed over an extended period. This is due to be completed early 2025.
1.6This report provides an update on the remediation programme and sets out a proposal to expand capacity at Millwood in order to meet increasing demands for local specialist provision.
1.7ISG Ltd have extensive knowledge of the design and construction of the existing building and will be carrying out the works on the building over a protracted period of time. It is therefore proposed to commission ISG to construct the extension to the building to provide the necessary additional capacity, to be implemented in parallel to the remediation works.
1.8In accordance with their defects obligations under the terms of the original 2011 contract, ISG Ltd are currently meeting the cost of the remedial work to the existing building. The Council will fund the costs of constructing the extension and funding has been identified within the Children’s Services capital programme for this purpose.
1.9In order to enable ISG to be appointed to carry out the extension project requires a specific procurement approach on which the Council’s Legal Services and Procurement Team have advised.
1.10Cabinet is requested to approve the submission of a business case to the North West Construction Hub (NWCH) requesting that a direct award be made to ISG for the Millwood expansion project.
1.11Cabinet is also requested to note the progress in relation to the roof remediation scheme.
Recommendation(s)
That Cabinet:
Note the progress made to date in relation to the roof remediation scheme. Approve the submission of a business case to the North West Construction Hub (NWCH) requesting that a direct award be made to ISG for the Millwood expansion project
Reasons for recommendation(s)
There are extenuating circumstances applicable in this situation that support proceeding with this method. These are outlined in section 4.4/4.5 below.
Alternative options considered and rejected
It would not be possible to have two main contractors on site simultaneously from a health and safety perspective, site management, and the efficient running of the school during construction works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.