Cabinet: Approved the costed bid from the contractor together with the costs of the professional & consultant fees/ additional surveys/client FFE costs for the construction of the new wing; roofing remedial works and other outstanding defects scheme. All costs are to be covered by Children’s Services capital funding; and Authorised the Director of Law and Democratic Services in consultation with the Cabinet Member for Children and Young People to finalise the terms of the Design and Build Contract to be entered into with the contractor.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet Date: 09 July 2025 Millwood Primary Special School – Request for approval to proceed Subject: to appoint contractor – Part A Report of Deputy Leader and Cabinet Member for Children and Young People
Summary 1. This report is presented to Cabinet with a full explanation of the latest position, details of the programme and seeking approval of a costed bid from the contractors for the construction of the new wing; roofing remedial and other outstanding defects scheme. Authorisation is required to enter into a Design and Build Contract with the contractors. Along with an approval request for other client costs stated in Part B of the report.
2. The contractors have completed the Pre-Construction Services Agreement (PCSA) for the detailed design up to RIBA Stage 4. Their costed bid was received on the 23 June 2025. The bid costs are shown in Part B of the report.
3. Cabinet approval is needed at the July meeting to ensure a start on site can be made on 4 August 2025 to meet the tight project deadlines. Initial works will be commenced under an agreed time and cost limited Letter of Intent if it is not possible to agree and execute the required JCT Contract by that date.
Recommendation(s) Cabinet is asked as follows: 1.To approve the costed bid from the contractor together with the costs of the professional & consultant fees/ additional surveys/client FFE costs for the construction of the new wing; roofing remedial works and other outstanding defects scheme. All costs are to be covered by Children’s Services capital funding. 2.To authorise the Director of Law and Democratic Services in consultation with the Cabinet Member for Children and Young People to finalise the terms of the Design and Build Contract to be entered into with the contractor. Reasons for recommendation(s)
Cabinet approval to appoint a contractor is needed at the July 2025 Cabinet meeting to ensure a timely start on site to achieve the tight deadlines for the 4 th wing extension and completion of the roofing remedial/outstanding defects work. Development of additional capacity at Millwood Primary Special School, as set out in the Project Safety Valve agreement between the Council and the Department for Education, is a key element of the specialist place sufficiency strategy. Taken together, the Agreement and strategy set out the business case for the development of new provision and expansion of existing specialist provision to meet increasing demand within Bury and reduce the reliance on placements in Independent Non-Maintained Special Schools (INMSS). The extension scheme at Millwood Primary Special School is a priority within this strategy. Urgent completion of the roofing remedial works/other outstanding defects is required. This has already been delayed due to the previous contractors going into Administration. Alternative options considered and rejected
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.