Cabinet: Approved in principle the fully costed bid from the contractor together with the costs of the professional/consultant/client FFE costs fees for the construction of the new wing. All costs are to be covered by Children’s Services capital funding. Subject to such validation being obtained, noted that authorisation will be sought under the urgent Decision route under the Constitution to be followed for final approval. Authorised the Director of Law and Democratic Services in consultation with the Cabinet Member for Children and Young People to finalise the terms of the Design and Build Contract to be entered into after such Urgent Decision has been obtained. Reasons for decision(s): Development of additional capacity at Millwood Primary Special School, as set out in the Project Safety Valve agreement between the Council and the Department for Education, is a key element of the specialist place sufficiency strategy. Taken together, the Agreement and strategy set out the business case for the development of new provision and expansion of existing specialist provision to meet increasing demand within Bury and reduce the reliance on placements in Independent Non-Maintained Special Schools (INMSS). The project at Millwood Primary Special School is a priority within this strategy. Alternative options considered and rejected: Whilst it is possible to re-procure the scheme, this would result in significant delay to delivery of the project with no certainty that costs will be reduced. The option to reprocure will remain, to be pursued in the event that the costed bid is rejected. In that event all the work carried out to date will be utilised to form an integral part of the tender documents to be issued.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet Date: 05 June 2024 Millwood Primary Special School – Programme Update & request Subject: for approval to appoint contractor – Part A Report of Deputy Leader and Cabinet Member for Children and Young People
1.0Summary 1.1 This updated report is presented to Cabinet with a full explanation of the latest position, details of the programme and seeking approval of a fully costed bid from the contractors for the construction of the new wing and authorisation to enter into a Design and Build Contract with them. Along with an approval request for the other client costs stated in Part B of the report.
1.2The contractors have completed the Pre-Construction Services Agreement (PCSA) for the detailed design up to RIBA Stage 4. Their costed bid was received on the 7 May 2024. This is shown in Part B of the report. Recommendation(s)
Cabinet is asked as follows: 1.To approve the fully costed bid from the contractor together with the costs of the professional/consultant/client FFE costs fees for the construction of the new wing. All costs are to be covered by Children’s Services capital funding. 2.To authorise the Director of Law and Democratic Services in consultation with the Cabinet Member for Children and Young People to finalise the terms of the Design and Build Contract to be entered into with the contractor. This report is issued without finalised bid figures from ISG as these will not be available until 31st May 2024. They will then be reviewed internally and validated by independent consultant surveyors Poole Dick. Provided that the final bid figure can be recommended, an amended report will then be issued. Cabinet approval is needed at the June meeting to ensure a start on site can be made on 1st July 2024 to meet the tight project deadlines. Initial works will be commenced under an agreed time and cost limited Letter of Intent if it is not possible to agree and execute the required JCT Contract by that date Reasons for recommendation(s) Development of additional capacity at Millwood Primary Special School, as set out in the Project Safety Valve agreement between the Council and the Department for Education, is a key element of the specialist place sufficiency strategy. Taken together, the Agreement and strategy set out the business case for the development of new provision and expansion of existing specialist provision to meet increasing demand within Bury and reduce the reliance on placements in Independent Non-Maintained Special Schools (INMSS). The project at Millwood Primary Special School is a priority within this strategy. Alternative options considered and rejected
Whilst it is possible to re-procure the scheme, this would result in significant delay to delivery of the project with no certainty that costs will be reduced. The option to re- procure will remain, to be pursued in the event that the costed bid is rejected. In that event all the work carried out to date will be utilised to form an integral part of the tender documents to be issued. Risk Management The Council has put robust client-side contract management arrangements in place to mitigate risk and ensure effective delivery of the project. _________________________________________________________ 2.0 Background
2.1Cabinet have received a suite of reports regarding progress/approvals in relation to this scheme. Below are the dates of the cabinet reports (See below links to the reports): -
14 December 2022 12 July 2023 6 September 2023 2.2 It has only been possible for a report to be submitted at the earliest in June 2024 to Cabinet seeking approval of a fully costed bid from the contractor for the construction of the new wing and authorisation to enter into a Design and Build Contract with them.
2.3Whilst these timescales are disappointing, the contractor remains confident that the building will be completed for occupation by September 2025 as the anticipated construction period is 53 weeks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.