Resolved
It was agreed: 1. Councillor Quinn and Officers be thanked for their attendance and update 2. All Councillors receive a copy of the presentation provided by Jon O’Connor Group Leader, Asset Manager.
Overview and Scrutiny Committee agreed this item on Thursday 23 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed: 1. Councillor Quinn and Officers be thanked for their attendance and update 2. All Councillors receive a copy of the presentation provided by Jon O’Connor Group Leader, Asset Manager.
1. The purpose of this report is twofold –
Set out proposed priorities for Highway Investment Strategy tranche 3 (HIS3) and the Highway Maintenance element of the City Regional Sustainable Transport Settlements (CRSTS) funds. A proposed final scheme list for both these funds will be presented in appendices 1 & 2, detailing Strategic and Local road priorities respectively. Set out the priorities of the Integrated Transport Block funding.
2. The highway network is one of the most valuable assets that the Council operates, and is a fundamental connector of people, businesses, and the services that the Council provides. A well-maintained highway network supports our Council priorities as set out in Let’s Do It.
3. As a highway network ages, deterioration increases to the stage where potholes form and require expensive reactive repairs. We have valued the current annual deterioration of our network at approximately £5 million per year.
4. The funding we receive from the Department for Transport (DfT) generally only allows us to prioritise approximately £1.2 million per year for resurfacing schemes. This is not sufficient and will lead to a deteriorating network.
5. Through HIS tranches 1 & 2 an additional £20 million investment in our highway asset has been made available since 2017/18. This additional funding has allowed us to halt deterioration on our classified highways.
6. In previous HIS tranches we have targeted funding to the classified strategic network, however, the condition of our unclassified local roads has unfortunately continued to deteriorate. Therefore, the proposal for the next 4 years is to target the unclassified network with approximately 80% of available funds with the remaining 20% for the classified network.
7. The profile of the HIS3 spending is shown in Figure 1 below. HIS3 Spending Profile (£m)
0.50.9
3.4
5.2
Planned - Strategic Planned - Local Streetscene Road Safety
Figure 1
8. Highway Maintenance CRSTS funds have also been allocated to Bury through GMCA from the DfT. They are an amalgamation of funds received in previous years under the guises of pothole and challenge funding, together with highway maintenance and incentive funding.
9. Highway Maintenance CRSTS is a five year settlement of £12.745 million from 2022/23 to 2026/27. The first year of that funding was included in previously approved proposals as it overlapped with HIS2 and therefore this report will focus on the remaining four years of the CRSTS settlement.
10.HIS3 is the Council’s own borrowed funding and the £10 million funding has been split between highways maintenance, £9.5million and Road Safety £500,000. The highways maintenance allocated will be split over the three year period 2023/24 to 2025/26.
11.The table below summarises the overall amounts concerned with the two funding streams.
Year HIS3 (‘000s) DfT CRSTS (‘000s) Total (‘000s) 2022/23 £ 2,549 £ 2,549 2023/24 £ 3,166 £ 2,549 £ 5,715 2024/25 £ 3,167 £ 2,549 £ 5,716 2025/26 £ 3,167 £ 2,549 £ 5,716 2026/27 £ 2,549 £ 2,549 Total £9,500 £ 12,745 £ 22,245
12. In line with previous years from 2023/24, 50% of CRSTS and 45% of HIS3 will be allocated to planned highway resurfacing and bridge and structures maintenance. The remaining proportion will be allocated to reactive maintenance, such as pothole repairs, patching, street lighting faults and preventative maintenance, such as surface dressing.
13. The table below summarises the proposed spending profile for planned highway resurfacing and bridge/structures maintenance allocations of the above proportions over the forthcoming period from the 2023/24 financial year.
Year Resurfacing Structures Total (‘000s) (‘000s) (‘000s)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Capital Programme: Highway Maintenance Funding 2023/24 to 2026/27 and Integrated Transport Block 22/23Decisions | 374 KB | DownloadRead as text |
PDF |
Highways Capital Programme Appendix 1Decisions | 56 KB | Download |
PDF |
Highways Capital Programme Appendix 2Decisions | 104 KB | Download |
PDF |
Highways Capital Programme Appendix 3Decisions | 61 KB | Download |
PDF |
Highways Capital Programme Appendix 4Decisions | 121 KB | Download |
Follow Overview and Scrutiny Committee at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2026 | Simister and bowlee development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Simister Bowlee Development Framework Supplement... | Agreed | Open |
| 10 Feb 2026 | Elton reservoir development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Elton Reservoir Development Framework Supplement... | Agreed | Open |
| 3 Sep 2024 | MINUTESIt was agreed that the minutes from 24 th July 2024 be approved as a correct record and signed by the Chair. Matters ... | Agreed | Open |
| 3 Sep 2024 | Health and safety reportIt was agreed: - The report be noted | Agreed | Open |
| 24 Jul 2024 | Corporate Parenting ChampionIt was agreed: 1. Councillor Green be appointed as the Corporate Parenting Champion. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.