Cabinet: 1. In order to progress the development of the scheme to adapt Spurr House, Cabinet is asked to approve a decision to enter into a Pre-Construction Services Agreement with a contractor selected following a tender process, and which will incur a commitment to the payment of pre-construction costs of up to £184,000. Those costs are to be met from the Children’s Services capital programme; 2. In order to progress the scheme to extend Millwood Special School, Cabinet is asked to approve a decision to enter into a Pre-Construction Services Agreement with ISG, and which will incur a commitment to the payment of preconstruction costs of up to £195,000. Those costs to be met from the Children’s Services capital programme; and 3. Cabinet is requested to approve a contract award in respect of Woodbank Primary School, to the lowest tenderer.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1. Cabinet has received a number of reports in respect of capital projects to support a number of developments.
2. A number of these projects are now at different stages of design and delivery but a common theme that is evident with these projects, and others being delivered across the Council, is the challenges linked to market capacity and inflationary pressures. Please see appendices.
3. Demands on the construction industry nationally means that there is limited competition in the marketplace, extended lead times for the supply of materials, with resultant impact on project delivery timescales, and significantly higher tender costs.
4. Technical consultants leading on the design and procurement of projects have attempted to factor time delays and inflationary pressures into schemes, but the market continues to be challenging.
5. This report provides an update on the status of three projects that have previously been reported to Council, given the significant changes that have occurred since first being reported.
Spurr House
6. At its meeting of the 7th September 2022 (CA.51) Cabinet approved the transfer of Spurr House from Adult Care to Children and Young People to facilitate the relocation of the Pupil Referral Unit (Spring Lane School) from its current Spring Lane building. This was to enable vacant possession of the Spring Lane site to be provided to the Department for Education for the construction of the new secondary school. The requirements and consequences of late delivery are detailed in paragraph 8. At the same meeting, Cabinet approved the indicative capital costs (CA.62) for the required improvements and adaptations to the Spurr House building. These costs are shown in Part B.
7. An important consideration in developing the project for the adaptation of Spurr House, is the cost-effectiveness and value of money of the proposed solution, taking into account the benefits of both releasing the Spring Lane site for the new high school, and in providing high quality replacement accommodation for the PRU. 8. There are clear dependencies between a number of projects, with significant risks to delivery, and with financial implications. The Council has committed to provide vacant possession of the Spring Lane site to DfE in order to enable construction of the new high school to commence. There are financial penalties payable by the Council in the event that it does not achieve the vacant possession date, which are £2.4m and reflect the cost of demolishing existing structures and providing the all-weather pitch. Further, the vacant possession date is critical in enabling the provision of the modular accommodation on the Spring Lane site, necessary for the new high school to open in September 2024.
9. These dependencies, and the need to ensure continuity of provision for the PRU present significant risks. The actions set out in this report, to review the cost and programme for the adaptations to Spurr House, and to identify an interim solution in the event of late delivery of those adaptations, are intended to mitigate those risks.
10. The relocation of the Pupil Referral Unit (PRU) to Spurr House is seen as part of a longer-term strategy whereby the Pupil Referral Unit will ultimately be co- located with the new SEMH Free Special School, the indicative timeline for which is completion in the 2025/26 academic year, at which point Spurr House will continue to be used to deliver specialist education provision. The design of the improvements and adaptations reflect this changing use over time.
11. The project for improvements and adaptations to Spurr House has now been developed in greater detail (RIBA Stage 3), and tenders invited. Only one tender was submitted which was at a significantly higher cost than anticipated.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.