Cabinet: 1. Accepted the indicative budget and works programme, and 2. Approved the Whitefield Centre works to proceed to formal tender, using a pre-procured ESPO Framework, and subject to additional cabinet approval of the final contract sum prior to award and entering into contract with the preferred supplier/ contractor. Reasons for decision(s) Approval of the works is required in order for the Whitefield Centre project to progress to tender phase. Key considerations within the document have informed both the scope and the methodology for carrying out the works as proposed. Alternative options considered and rejected: 1. Delay instructing the contract: This would delay overall Whitefield Centre completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would prevent the school from receiving the additional intake of pupils and they would have to be housed in alternative provision outside the Borough of Bury. This would also push the works into the winter months, potentially extending the duration on site and associated costs of construction. 2. Seek an alternative solution for the contract: The Council have considered alternative options to deliver the additional accommodation within the timescales provided. This included use of other Council owned property, and the use of modular accommodation on the existing site, partial refiguration only. No other Council owned property could meet the needs of the school within the available timescale. Partial reconfiguration would not provide the classroom accommodation the school requires and there was insufficient space within the school to site modular accommodation or extend. A split site was also discounted as the school would not have the staffing and safeguarding arrangement available to accommodate this. None of the alternative options explored where able to deliver the additional accommodation with the available timescales.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Equality Impact Analysis This equality impact analysis establishes the likely effects both positive and negative and potential unintended consequences that decisions, policies, projects and practices can have on people at risk of discrimination, harassment and victimisation. The analysis considers documentary evidence, data and information from stakeholder engagement/consultation to manage risk and to understand the actual or potential effect of activity, including both positive and adverse impacts, on those affected by the activity being considered. To support completion of this analysis tool, please refer to the equality impact analysis guidance. Section 1 – Analysis Details (Page 5 of the guidance document) Name of Policy/Project/Decision PRU (Phase 2-Whitefield Centre)-request for approval to invite tenders for work in relation to the Pupil Referral Unit. Lead Officer (SRO or Assistant Director/Director) Jeanette Richards Department/Team Children’s Services Proposed Implementation Date 5.6.2024-Cabinet Date Author of the EqIA Samantha Horrocks Date of the EqIA 20.5.2024
1 Bury Council – Equality Impact Analysis 1.1 What is the main purpose of the proposed policy/project/decision and intended outcomes? Can embed or link to existing report/document in this section
The Pupil Referral Unit (PRU) is a special school catering for 137 secondary age (11-16) pupils with a range of additional educational needs. The PRU operates out of four buildings.
The proposal is to request approval to invite tenders for work in relation to the Pupil Referral Unit, specifically in relation to the PRU’s Whitefield Centre.
This relates to Phase 2 of works following the relocation of the main PRU building from Spring Lane to the New Kershaw Centre in February 2024 (Phase 1). Approval is required to proceed to tender to obtain a competitive construction price.
Alongside this, one of the PRU’s other buildings, Milltown House has had to be taken out of use because of its condition. The loss of the Spring Lane School site, and limitations to the scope of accommodation available at the NKC has resulted in a shortfall of accommodation available to the PRU, particularly in respect of the delivery of vocational subjects.
The local authority has worked with the leadership team of Spring Lane school, and the Oak Leaning Partnership, which is the proposed sponsor of Spring Lane School, to determine the immediate requirements for accommodation, but also to develop a longer-term estate strategy recognising the changing demands on provision, and the existing fragmented nature of the PRU estate, operating out of four buildings.
Phase 2 is now urgently required, to further expand/ enhance the current provision at the New Kershaw Centre and the Whitefield Centre following the relocation from Spring Lane School. Initially, the focus was on the possible internal reconfiguration of the PRU’s existing building in Whitefield. However, time constraints, requiring the accommodation to be available from the autumn term, resulted other options also being considered. The provision of temporary modular accommodation for the whole school positioned at Whittaker Street, Radcliffe was found to be the only option that could deliver the accommodation that the school require within the timescales available.
2 Bury Council – Equality Impact Analysis Section 2 – Impact Assessment (Pages 6 to 10 of the guidance document)
2.1Who could the proposed policy/project/decision likely have an impact on? Employees: Yes Community/Residents: Yes Third parties such as suppliers, providers and voluntary organisations: No – the additional accommodation is primarily for use by school pupils, and so the impact will be on pupils on roll at the school, and the staff employed in the school.
If the answer to all three questions is ‘no’ there is no need to continue with this analysis.
2.2Evidence to support the analysis. Include documentary evidence, data and stakeholder information/consultation Documentary Evidence:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.