Cabinet: 1. Approved the first stages of the Bradley Fold redevelopment as set out in the report; 2. Approved £1,417,000 being added to the capital programme, funded from prudential borrowing. A full breakdown is shown in part B. - includes approval for the expenditure in relation to compensation costs associated with the service of S.25 notices on all units that do not have insurance cover - includes approval for the expenditure of £400,000 associated with the upgrading and relocating the electricity substation and transformer. 3. Noted that where appropriate and subject to relevant risk mitigation, tenants may be placed onto short term contracted out leases to allow continuation of business and income generation whilst Phase 1 is completed; 4. Approved the tender of demolition contractor/s for demolition of units as they become vacant; and 5. Approved the tender of a design team and project manager to progress ‘Phase 1’ to RIBA Stage 3 and update master plan for the whole estate. Note that subsequent will brought to Cabinet at the appropriate time.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1This report sets out proposals for the redevelopment of Bradley Fold Trading Estate. Many parts of the estate are in a dilapidated condition and insurance has been withdrawn on certain parts. Whilst this poses a risk to the Council, it also presents a regeneration opportunity. Investment in the estate will maximise the sites’ potential as a modern industrial hub which generates income for the Council as well as attracting high quality businesses and jobs into the area. 1.2 Proposed action to mitigate the current risk of holding dilapidated buildings where insurance has been withdrawn is outlined within the report as follows:
Implement remedial works identified by risk assessments where possible Where the existing leases provide an obligation for the Council to insure and repair/ rebuild the buildings, where possible, the Council should seek terminate leases with a view to demolish the building or grant occupier/s full repairing and insuring lease/s.
1.3The report outlines proposals to procure a design team and project manager to progress ‘Phase 1’ of the proposed development to RIBA Stage 3 and update the master plan for the whole estate. The report outlines budget costs in relation to undertaking this work as sets out recommendations for approval.
2. Recommendation(s) That Cabinet: 2.1 Approve the first stages of the Bradley Fold redevelopment as set out in the report. 2.2 Approve £1,417,000 being added to the capital programme, funded from prudential borrowing. A full breakdown is shown in part B. - includes approval for the expenditure in relation to compensation costs associated with the service of S.25 notices on all units that do not have insurance cover - includes approval for the expenditure of £400,000 associated with the upgrading and relocating the electricity substation and transformer. 2.3 Note that where appropriate and subject to relevant risk mitigation, tenants may be placed onto short term contracted out leases to allow continuation of business and income generation whilst Phase 1 is completed. 2.4 Approve the tender of demolition contractor/s for demolition of units as they become vacant. 2.5 Approve the tender of a design team and project manager to progress ‘Phase 1’ to RIBA Stage 3 and update master plan for the whole estate. Note that subsequent will brought to Cabinet at the appropriate time.
3. Reasons for recommendation(s) 3.1 Redevelopment of the estate will maximise the sites’ potential by providing high quality industrial units which will drive inward investment, employment opportunities and maximise revenue potential for the Council. 3.2 Termination of existing agreements will reduce & mitigate risk of holding buildings that are in a poor state of repair and do not have 3rd party insurance cover. If tenants are granted short term leases at the discretion of the Head of Land and Property, they will be on the basis that the tenant accepts the building is not insured or may not be rebuilt / repaired if cost of works exceeds the value of the premises or repair work is not viable. Where units are self- contained, and tenants can obtain their own insurance, longer term ‘Full Repairing and Insuring’ leases can be granted on the basis that they undertake agreed improvement works.
4. Alternative options considered and rejected
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.