CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 9 July 2025 at 6.00pm

Housing Major Works Programme 2025/26

Approved Executive 1 paper

Cabinet approved this item on Wednesday 9 July 2025. Below is the council's own wording, with the papers it was decided on.

ItemCA.17

Resolved

Cabinet: 1. Approved contract award to Emmanuel Whittaker Ltd for renewal of kitchen & bathrooms to be carried out to Council properties on the Huntley/Massey Estates in Bury for 1 year for the value of £1,153,828.15; 2. Approved the expenditure of £750,000 for additional kitchens and bathrooms to various Council properties across the rest of the Borough; 3. Approved the following contracts for energy efficiency and/or renewable energy works to Council properties on three estates: · Chesham Estate (completes existing scheme) to A. Connolly. Value: £1,443,506.87 · Freetown & Stanley Close to Eco Approach. Value: £1,980,743.50 · Hollinhurst to Live Manage Facilitate. Value £1,646,189.85 4. Approved a contract extension to existing EPC Contract with GGI, to extend work across 3 estates in Prestwich, Tottington & Whitefield, value £1,000,000.00.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Recommendations

1. Approve contract award to Emmanuel Whittaker Ltd for renewal of kitchen & bathrooms to be carried out to Council properties on the Huntley/Massey Estates in Bury for 1 year for the value of £1,153,828.15

2. Approve the expenditure of £750,000 for additional kitchens and bathrooms to various Council properties across the rest of the Borough.

3. Approve the following contracts for energy efficiency and/or renewable energy works to Council properties on three estates:

 Chesham Estate (completes existing scheme) to A. Connolly. Value: £1,443,506.87  Freetown & Stanley Close to Eco Approach. Value: £1,980,743.50  Hollinhurst to Live Manage Facilitate. Value £1,646,189.85

4. Approve a contract extension to existing EPC Contract with GGI, to extend work across 3 estates in Prestwich, Tottington & Whitefield, value £1,000,000.00

1 3.0 Background

Decent Homes

3.1A key regulatory requirement for housing is to ensure all Bury Council homes are maintained, as a minimum, at the Decent Home Standard. A key expectation of the Regulator for Social Housing is that all our homes are ‘of good quality, well maintained and safe homes for tenants’ and comply with the decent homes standard’.

Huntley/Massey Estates

3.2To maintain our homes at this standard we seek approval to enter into a building contract for renewal of kitchen & bathrooms to be carried out to Council properties on the Huntley/Massey Estates in Bury.

3.3After consultation with Bury Council’s Procurement Team the contract was tendered through Procure Plus framework mini competition. This involved a scoring of contractor submissions based 60% on Price, 30% Quality and 10% on Social Value.

3.4We recommend awarding of the contract to Emanuel Whittaker Ltd for a contract value of £1,153,828.15. The contract is for the initial period of one year with the option to extend for a further 12 months should additional work be identified. If an extension is required, this will be brought back to cabinet with the contract value.

3.5All contract procurements have been advised and overseen by Bury Procurement.

Various aged kitchens & bathrooms across Bury

3.6During preparation of tenders we identified an omission in the February 2025 HRA Capital Budget. Provision for ad hoc kitchen and bathroom replacements across the Borough had not been made.

3.7In order to bring forward these works it is recommended approval of an additional Budget provision for kitchens & bathrooms of £750,000.00.

3.8This approval will address an oversight in the February budget. Savings from other budget headings will provide the headroom and there will no overall increase in the HRA capital budget.

Energy Projects

3.9Bury Council Housing Services has gained a positive reputation across Greater Manchester for its work on energy efficiency. In addition to written recognition for our work from the GMCA, a key grant funding body, we won an award and received two highly commended in the NW Regional Energy Efficiency Awards

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Major Works Programme 2025/26Decisions 554 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 26 attended
EO
Councillor Eamonn O'BrienChair, present
ST
Councillor Sean ThorpeCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, apologies
TT
Councillor Tamoor TariqCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, in attendance
PM
Paul McKevittOfficer, expected

All 26 on the meeting page

On this subject at Bury

Search all
  1. Housing Major Works Programme 2025/26This decision
  2. Housing Major Works Programme 2025/26 - Part AApproved
  3. Housing Major Works Programme 2025/26 - Part AApproved
  4. Housing Major Works Programme 2025/26 - Part AApproved
  5. Proposed Major Works Programme for the Councils housing stock 2024/25Approved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies