AI summaryBury Cabinet approved £701,000 grant and £1,051,500 council match funding to buy eight homes in 2026/27, five for temporary accommodation and three for an Afghan resettlement family. The scheme is expected to save about £0.170m over three years through reduced bed and breakfast use.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFive for temporary accommodation, three for general letting
Money£701,000 grant plus £1,051,500 matchMatch from General Fund Capital Programme
What happens nextAcquire properties by March 2027Year one grant must be spent or returned
Who it affectsHomeless families and Afghan resettlementHouseholds currently in bed and breakfast
What was decided
Cabinet approved the use of £701,000 from the LAHF R4 grant allocation and £1,051,500 from the General Fund Capital Programme as match funding, to enable the acquisition of eight properties in 2026/27. Report P7, 1.6
Members noted that the estimated interest cost of borrowing will be just below £0.068m per annum, or £0.204m over the first three years, based on 30 year PWLB rates of circa 6.44%. Report P7
The properties will be split, with five used as temporary accommodation for homeless families and three as general needs housing for an Afghan resettlement family. Report 1.5, 3.2
Why
The scheme is intended to reduce reliance on unsuitable and high cost temporary accommodation, particularly bed and breakfast placements. Report 3.1
It is expected to deliver estimated reductions of about £0.170m over the first three full years by replacing expensive placements with council owned homes let at affordable rent. Report 3.1
The approach supports the council's statutory housing duties, the Homelessness and Temporary Accommodation Strategy, and the conditions of the LAHF R4 grant. Report 3.2, 5.7
What happens next
All eight property acquisitions must be completed by March 2027, or the year one grant must be returned to MHCLG. Report 1.6, 5.11
Housing Services will be responsible for all repairs and maintenance on the acquired properties, while the Homelessness and Housing Options Service will manage placements, support and move on. Report 3.3
Further equality considerations will be undertaken at the point of purchasing the additional accommodations. Report P34
The money
£701,000 Year one LAHF R4 grant allocation Report 1.6, P7
£1,176,000 Total provisional Section 31 capital grant allocation Report 1.2, P7
£1,051,500 Match funding from General Fund Capital Programme for 2026/27 Report 1.6, P7
£0.068m Estimated annual interest cost of borrowing for match funding Report P7, P40
£0.204m Estimated interest cost over first three years Report P7, 3.1
£0.170m Estimated reduction in temporary accommodation costs over first three years Report 3.1, P31
£3.5m Private temporary accommodation expenditure in 2025/26
£137,600 Total Afghan Resettlement Programme tariff claim for the household of five
Options considered
Rejected: Do nothing. Would not reduce reliance on expensive bed and breakfast placements Report 4.1
Chosen: Acquire eight properties with 60% match funding from General Fund. Invest to save model, similar approach successfully used for LAFH R3 Report 4.2, 1.5, 5.5
Implications
Financial: Additional prudential borrowing of up to £1,051,500 in the General Fund Capital Plan, with interest costs expected to be more than offset by savings in temporary accommodation spending and rental income at affordable rent up to 80% of market rent. Report P40, 5.9
Legal: Section 31 Local Government Act 2003 grant with conditions attached; the Memorandum of Understanding has been signed and returned by the council. Report P33, P39
Equalities: No equalities concerns at this stage; further equality considerations will be taken at the point of purchasing the additional accommodations. Report P34
Risk: Acquisition costs may exceed estimates due to market prices, varying offers and additional legal or property works; the year one grant must be committed by March 2027 or returned. Report P36, 5.11
Staffing: Housing Services will be responsible for all repairs and maintenance; the Homelessness and Housing Options Service will manage placements, support and move on. Report 3.3
Who and where
Homeless families currently placed in bed and breakfast accommodation (55 family households including 87 children as of 30 April 2026) Report 6.3
An Afghan family resettled under the Afghan Resettlement Programme Report 3.2, 1.5
Households on the council's housing waiting list (potential future use of properties once temporary accommodation needs ease) Report 5.11
Council tenants in the 120 existing dispersed temporary accommodation properties, all of which are currently in use Report 5.1
Timeline
October 2024: MHCLG notified council of breach of legislation regarding families accommodated in hotels for more than 6 weeks Report 5.3
December 2025: Cabinet approved LAFH R3 delivery and council notified of LAHF R4 allocation Report 5.5, 5.6
January 2026: LAHF R3 acquisition process commenced Report 5.5
2026 to 2030: Overall LAHF R4 delivery period for 10 homes in total (with a planned pause in 2026/27) Report 1.2, 5.6
March 2026: Temporary Accommodation Strategy developed, setting out a three year delivery plan Report 5.7
30 April 2026: 244 households in temporary accommodation including 434 children Report 6.3
30 June 2026: Cabinet decision approving the scheme
March 2027: Deadline to complete all year one property acquisitions Report 1.6
Plain English for the jargon
LAHF R4: Local Authority Housing Fund Round 4, government funding to increase supply of temporary accommodation
MHCLG: Ministry of Housing, Communities and Local Government
PWLB: Public Works Loan Board, a government body that lends money to local authorities
ARP: Afghan Resettlement Programme
B&B: Bed and breakfast accommodation
MoU: Memorandum of Understanding between the council and MHCLG
HPG: Homelessness Prevention Grant
s31: Section 31 of the Local Government Act 2003, power for the Secretary of State to pay grants to local authorities
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.28
Resolved
Cabinet: Approved the use of £701,000 from the total £1,176,000 combined grant allocation and match funding from the General Fund Capital Programme of £1,051,500 for 2026/27 delivery, to enable the acquisition of eight properties; and Noted that, based on current interest rates of circa 6.44% for 30-year PWLB money, the estimated interest cost of borrowing will be just below £0.068m per annum or £0.204m over the first three years. This will support the reduction of reliance on unsuitable and high cost temporary accommodation over the longer term. (The Council used this approach for the delivery on the previous round of funding under LAFH R3).
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1The Local Authority Housing Fund Round 4 (LAHF R4) provides £950 million of funding to support local authorities in England to increase the supply of better- quality temporary accommodation and drive down the use of Bed and Breakfast for families with children. It will also provide housing for some families on the Afghan Resettlement Programme (ARP). LAHF R4 investment will provide local authorities with a lasting affordable housing assets for the future.
1.2Bury Council was notified in 2025 of its successful allocation under the LAHF R4. Bury has been provisionally identified as eligible to receive capital grant funding under Section 31 of the Local Government Act 2003, with an indicative allocation of £1,176,000. The provisional funding allocation is intended to support the delivery of a mixed programme of temporary accommodation and resettlement properties across the period 2026 to 2030, with a planned pause in delivery during 2026/27. The programme expects the council to deliver a total of 10 units, comprising 5 temporary accommodation units and 5 resettlement properties for general letting.
1.3As part of the Council’s corporate priority to driving inclusive growth, improving children’s lives and to support the objectives of the Homelessness, Temporary Accommodation and Housing Strategy, the Council submitted an EOI as requested to the Ministry of Housing, Communities and Local Government (MHCLG) under the LAHF R4 programme. The submission set out a business case for three delivery approaches: acquisitions through Right to Buy and open market to achieve the 2026/27 targets, as detailed within this Cabinet report; the purchase of discounted Section 106 properties; and the delivery of new housing supply for the period 2028/2030, subject to confirmation.
1.4Since the original MHCLG submission, further work has demonstrated that by maximising grant funding the council could deliver 12 properties in total, comprising seven for temporary accommodation and five for resettlement, generating increased General Fund savings through a further reduction in the use of nightly paid temporary accommodation
1.5This report considers the delivery of LAHF R4 for the 2026/27 period only, for the delivery of eight properties in total. It is proposed that five properties will be used as temporary accommodation for homeless families, with the remaining three provided as general needs accommodation and allocated to an Afghan family as part of the wider Afghan Relocations Programme (ARP). The proposal includes Council match funding of 60% through the General Fund Capital Programme for 2026/27, in line with the requirements of the LAHF R4 grant allocation
1.6The Council has confirmed to the MHCLG its intention to deliver eight properties under LAHF R4 during the 2026/27 period. A total grant allocation of £701,000 has been confirmed to support delivery of the scheme, with all property acquisitions required to be completed by March 2027.The programme will be supported by Council 60% match funding from the General Fund Capital Programme of £1,051,500 in accordance with the conditions of the LAHF R4 grant allocation.
2 Recommendation(s) 2.1 It is recommended that Cabinet; Approve the use of £701,000 from the total £1,176,000 combined grant allocation and match funding from the General Fund Capital Programme of £1,051,500 for 2026/27 delivery, to enable the acquisition of eight properties. Based on current interest rates of circa 6.44% for 30-year PWLB money, the estimated interest cost of borrowing will be just below £0.068m per annum or £0.204m over the first three years. This will support the reduction of reliance on unsuitable and high cost temporary accommodation over the longer term. (The Council used this approach for the delivery on the previous round of funding under LAFH R3)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.