Bury Metropolitan Borough Council
Cabinet, Tuesday 30 June 2026 at 6.00pm

Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement Measures

Agreed Executive 1 paper

AI summaryBury Cabinet extends the A.Connolly housing contract on Bent Hill estate for 12 months at £2,100,075.60, and awards a one-year decarbonisation contract to NextEnergy Capital worth £2,173,551, covering 265 properties across several wards.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedHRA capital and carbon reduction works
Money£2,100,075.60 and £2,173,551Estimated values for the two contracts
What happens next31 July 2026 and 8 September 2026Proposed start dates for the two contracts
Who it affects265 properties across five wardsDecent Homes and carbon works

What was decided

Cabinet agreed to extend the existing contract with A.Connolly Limited for the Bent Hill estate in Prestwich (Sedgley Ward), covering 140 properties in Programme A, by 12 months from 8 September 2026 at an estimated value of £2,100,075.60.

Cabinet awarded a contract to NextEnergy Capital Limited for Programme B decarbonisation works across several estates, with a one-year initial term from 31 July 2026 and an option to extend a further 12 months, at an estimated initial value of £2,173,551.

Why

The decisions form part of the HRA Capital Investment Programme 2026/27 and Carbon Reduction Sustainability Improvement Measures, addressing Decent Home standard Thermal Comfort failures and energy efficiency across council housing stock.

What happens next

The NextEnergy Capital contract is to commence on 31 July 2026, with the A.Connolly extension commencing on 8 September 2026, both carrying an option or term that runs into 2027.

The money

  • £2,100,075.60 Estimated value of the 12-month extension to the A.Connolly Limited contract for Bent Hill estate, 140 properties
  • £2,173,551 Estimated value of the initial one-year term of the NextEnergy Capital Limited contract for Programme B works

Options considered

  • Chosen: Extend existing A.Connolly Limited contract for Bent Hill estate by 12 months. Forms part of Programme A within the HRA Capital Investment Programme 2026/27
  • Chosen: Award new contract to NextEnergy Capital Limited for Programme B estates and 70 thermal comfort fails across the borough. Delivers carbon reduction and sustainability improvement measures with an option to extend

Implications

  • Climate: Programme B works target carbon reduction and Thermal Comfort failures on 70 properties across Redvales, Ramsbottom, Besses, North Manor and Bury East areas.
  • Other: Works cover 265 properties in total: 140 on Bent Hill and 125 across the Programme B estates.

Who and where

  • Tenants of 140 properties on the Bent Hill estate, Prestwich, Sedgley Ward
  • Tenants of 95 properties on Goshen Estate, Redvales Ward
  • Tenants of 24 properties on Sumner Avenue Estate, Radcliffe North and Ainsworth Ward
  • Tenants of 6 properties on Knowles Street Estate, Redbank Ward
  • Tenants of 70 properties with Thermal Comfort fails across Redvales, Ramsbottom, Besses, North Manor and Bury East areas

Timeline

  • 31st July 2026: Proposed commencement of the NextEnergy Capital Limited contract (initial 1-year term)
  • 8th September 2026: Commencement of the 12-month extension to the A.Connolly Limited contract

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
  • Decent Home standard: Government minimum standard for social housing condition, covering thermal comfort among other criteria
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.25

Resolved

Cabinet agreed: An extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) in respect of Bent Hill estate, Prestwich, Sedgley Ward – 140 properties, which forms part of Programme A, for a further term of 12 months commencing on 8th September 2026 and a total estimated contract value of £2,100,075.60; and A contract award to NextEnergy Capital Limited (Company number 05975233), in respect of the estates mentioned below which comprise of Programme B, for an initial term of 1 year (proposed commencement date of 31st July 2026) and the option to extend for a further 12 months. The total estimated contract value for the initial term is £2,173,551: Goshen Estate Redvales Ward - 95 properties Knowles St Estate Redbank Ward - 6 properties Sumner Avenue Estate- Radcliffe North and Ainsworth Ward- 24 properties Decent Home standard - Thermal Comfort fails for 70 properties throughout the borough. These are located within the Redvales, Ramsbottom, Besses, North Manor, and Bury East areas.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 30 June 2026 Contract awards in respect of the HRA Capital Investment Subject: Programme 2026/27 and Carbon Reduction - Sustainability Improvement Measures Report of Cabinet Member for Housing Services

Summary By way of background, On 10th February 2026 Cabinet approved the Housing Revenue Account (“HRA”) Capital Works Programme for 2026/27 and a budget of £5.6m for Carbon reduction schemes - Sustainability Improvement Measures. The purpose of the current report is to seek formal approval of the following contract awards for Carbon reduction schemes below: 1. An extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) (“A.Connolly) for a further term of 12 months commencing on 8th September 2026 and total estimated contract value of £2,100,075.60. During the period of extension, the work carried out by A.Connolly will be in respect of Bent Hill estate Prestwich Sedgely Ward - 140 properties, which forms part of Programme A.

2. A contract award to NextEnergy Capital Limited (Company number 05975233), in respect of the estates mentioned below which comprise of Programme B, for an initial term of 1 year (proposed commencement date of 31st July 2026) and total estimated contract value of £2,173,551: 2.1 Goshen Estate Redvales Ward - 95 properties 2.2 Knowles St Estate Redbank Ward - 6 properties 2.3 Sumner Avenue Estate- Radcliffe North and Ainsworth Ward- 24 properties 2.4 Decent Home standard - Thermal Comfort fails for 70 properties throughout the borough. These are located within the Redvales, Ramsbottom, Besses, North Manor, Bury East areas, 1. Recommendation(s) 1.1 Cabinet is asked to approve the following: 1.1 An extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) in respect of Bent Hill estate, Prestwich, Sedgley Ward – 140 properties, which forms part of Programme A, for a further term of 12 months commencing on 8th September 2026 and a total estimated contract value of £2,100,075.60. 1.2 A contract award to NextEnergy Capital Limited (Company number 05975233), in respect of the estates mentioned below which comprise of Programme B, for an initial term of 1 year (proposed commencement date of 31 st July 2026) and the option to extend for a further 12 months. The total estimated contract value for the initial term is £2,173,551: 1.3 Goshen Estate Redvales Ward - 95 properties 1.4 Knowles St Estate Redbank Ward - 6 properties 1.5 Sumner Avenue Estate- Radcliffe North and Ainsworth Ward- 24 properties 1.6 Decent Home standard - Thermal Comfort fails for 70 properties throughout the borough. These are located within the Redvales, Ramsbottom, Besses, North Manor, Bury East areas, 2. Reasons for recommendation(s) 2.1 The primary reason for requesting approvals for the programmes from both A.Connolly's and NextEnergy is to ensure continuation of the Bury Council Housing retrofit programme, which is aimed at helping to achieve Energy Performance Certificate (“EPC”) C by 2030 along with aims to reduce energy consumption and carbon emissions. Retrofit surveys are underway in preparation for Social Housing/Warm Homes Fund (Wave 3) grant application which is essential to support HRA capital investment. 3. Alternative options considered and rejected

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction: Sustainability Improvement MeasuresDecisions 673 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 20 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, in attendance
CB
Councillor Carol BirchmoreCommittee Member, in attendance
JR
Councillor Jack RydeheardCommittee Member, in attendance

All 20 on the meeting page

On this subject at Bury

Search all
  1. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresThis decision
  2. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresApproved
  3. Care at Home - Request to Delegate the Authority to Contract AwardsRefused

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies