AI summaryBury Cabinet approved a contract with Conlon Construction Limited worth up to £1,554,000 for remediation works at the 7.4-acre Pyramid Park brownfield site, unlocking it for future residential development of up to 150 homes.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedAppoint Conlon Construction Limited as main contractor
Money£1,554,000.00 including contingencyTotal contract value, term of 90 days
What happens nextWorks start July 2026, complete autumn 2026Site must be sold to developer by 31 March 2027
Who it affectsFuture residents and town centreWill enable up to 150 new homes on a derelict site
What was decided
Cabinet authorised the council to enter a Schedule of amendments to a JCT Design and Build Contract (2016) with Conlon Construction Limited, up to £1,554,000.00 including contingency, for a 90-day term. Report P8
Cabinet accepted Conlon Construction Limited as the contractor to deliver the Remediation Main Works, subject to finalising outstanding contract amendments and clarifications. Report P9
Cabinet delegated acceptance of the final contract sum (up to £1,554,000.00 including contingency) to the Director of Law and Democratic Services, in consultation with the Executive Director of Place, the Executive Director of Finance, the council Leader, and the Cabinet Member for Strategic Growth. Report P10
Why
Remediating the long-disused, 7.4-acre council-owned brownfield site will unlock it for high-quality, sustainable residential development and help meet housing need in the borough. Report P1, P7, P15, P16
Works must be completed so the site can be disposed of to a developer by 31 March 2027, in line with the Grant Funding Agreement with One Public Estate, or the £1.73 million BLRF2 grant could be clawed back. Report P2, P6, P11
An independent cost consultant has market tested and verified Conlon's submitted works packages, confirming value for money within the BLRF2 funding envelope. Report P7, P44, P45
What happens next
Enabling and site preparatory works are scheduled to start in July 2026, with main remediation progressing west to east, concluding with demobilisation in early autumn 2026. Report P3, P47
A non-definitive Public Right of Way through the site will be temporarily closed until the works are complete. Report P41
A separate four-stage procurement is underway to find a development partner for the future residential scheme, with a further Cabinet report to follow. Report P37
The money
£1,554,000.00 Maximum total contract value including contingency for the Remediation Main Works contract with Conlon Construction Limited Report P8, P10, P46
£1.73 million BLRF2 grant funding awarded in late-2023 to support planning, design, land remediation and enabling works at Pyramid Park Report P2, P22
Options considered
Rejected: Re-run the procurement process for a new main works contractor. Would delay start-on-site by several months, jeopardise the 31 March 2027 development agreement deadline, risk BLRF2 grant clawback, expose the council to build cost inflation, and incur extra fees Report P10, P11, P12, P13
Rejected: Do nothing and/or return the BLRF2 grant to One Public Estate. Pyramid Park would remain derelict, attracting anti-social behaviour; the borough would lose much-needed town centre housing, council tax revenue, and wider regeneration benefits Report P14, P15, P16, P17, P18, P19
Implications
Financial: The remediation works are fully funded by the BLRF2 grant, with no revenue implications for the council. Report P77
Legal: The North West Construction Hub framework and mini-competition expressly permitted a two-stage process allowing direct award of the main works following satisfactory completion of pre-construction services. Report P74, P75, P76
Equalities: An initial equality impact screening found no equality concerns at this stage; impacts will be kept under review. Report P58
Climate: A 10% Biodiversity Net Gain uplift has been agreed, with the Townside Grade B Site of Biological Importance habitats retained and enhanced on-site and off-site. Report P40, P61, P80
Risk: Reputation, permissions, delivery, supplier and financial risks are identified, with mitigation including experienced project management, contingency sums, planning consent already granted, and robust contractual arrangements. Report P63, P64, P65, P66, P67, P68, P69, P70, P71, P72
Other: Conlon will deliver social value outcomes including use of local supply chain, work experience for Bury College students, apprenticeships, and ex-service personnel placements via Project RECCE. Report P52, P53
Who and where
Future residents of up to 150 new homes at Pyramid Park, including families, older people, extra care and care leavers Report P33, P34, P36, P55
Bury town centre visitors and businesses benefiting from regeneration of a long-derelict site Report P27, P56
Bury College students gaining work experience opportunities through the scheme Report P52, P53
Local supply chain, including Bury-based subcontractor Cheetham Hill Construction undertaking main land remediation works Report P52
Users of a non-definitive Public Right of Way through the site, which will be temporarily closed Report P41
Timeline
Late-March 2023: Council submitted full BLRF2 funding bid for Pyramid Park Report P21
15 March 2023: Cabinet authorised disposal of Pyramid Park for residential use Report P21
October 2023: Council notified of successful £1.73 million BLRF2 grant funding award Report P22
2024: Conlon appointed via mini-competition under the NWCH Low Value Construction Framework Report P4
2 July 2024: Full planning application submitted for land remediation and associated works (ref 70903) Report P42
19 December 2024: Planning consent granted for the remediation works (ref 70903) Report P3, P42
July 2026: Remediation main works scheduled to commence Report P3, P47
Autumn 2026: Remediation works currently anticipated to complete Report P3, P47
8 July 2026: Cabinet decision to award main works contract Report P47
31 March 2027: Site must be disposed of to a private developer to comply with the Grant Funding Agreement Report P6, P11
Plain English for the jargon
BLRF2: Brownfield Land Release Fund, a government programme providing capital funding to release council-owned brownfield land for housing
BNG: Biodiversity Net Gain, a requirement for new development to deliver a measurable positive impact on biodiversity of at least 10%
JCT: Joint Contracts Tribunal, a UK provider of standard building contracts including the JCT Design and Build Contract (2016)
NWCH: North West Construction Hub, a public sector construction procurement framework serving the North West of England
PCSA: Pre-Construction Services Agreement, a contract appointing a contractor for pre-construction services ahead of the main building contract
GFA: Grant Funding Agreement, the legally binding contract setting out the terms of the BLRF2 grant between the council and One Public Estate
OPE: One Public Estate, the partnership delivering the BLRF2 programme on behalf of MHCLG
PRoW: Public Rights of Way, public highways protected in law including footpaths, bridleways and byways
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.45
Resolved
Cabinet: 1. Authorised the council to appoint and enter into a Schedule of amendments to JCT Design and Build Contract (2016) with Conlon Construction Limited (company number 00708997) as the main contractor to deliver the Pyramid Park Remediation Main Works to unlock the site for residential development, up to a total contract value of £1,554,000.00 including contingency, and term of 90 days; 2. Accepted the recommendation that Conlon Construction Limited undertake the Pyramid Park Remediation Main Works as per the estimated contract value set out in this report, subject to the agreement of any outstanding contract amendments and clarifications; and 3. Delegated acceptance of the final contract sum up to a total contract value of £1,554,000.00, including contingency, to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Executive Director of Finance, and the council Leader and Cabinet Member for Strategic Growth.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1. The Pyramid Park Remediation Main Works will help unlock and bring a key council-owned, 7.4-acre disused brownfield site forward for high-quality, sustainable residential development in the near future. Situated on the edge of Bury town centre, Pyramid Park has long been identified as a key strategic regeneration opportunity site and is highlighted in the Bury Town Centre Masterplan (2022) as suited for high quality residential development at scale.
2. In order to accelerate the council’s ambitious plans to deliver hundreds of much-needed new homes across the borough over the coming years, the council was successful in securing £1.73 million in grant funding, in late-2023, from the Government’s Brownfield Land Release Fund (BLRF2) programme, which is overseen by One Public Estate (OPE) and supported by the Ministry of Housing, Communities and Local Government (MHCLG). The BLRF2 grant provides for the remediation and de-risking of the Pyramid Park site, which will prepare it for residential redevelopment in the future and improves viability of the site for a developer.
3. The proposed works packages included within the JCT Design and Build Contract (2016) encompasses the delivery of a full land remediation strategy and associated preparatory enabling works at the Pyramid Park site, to be undertaken by the scheme contractor Conlon Construction Limited (Company number 00708997 ) (“Conlon”). Subject to Cabinet approval, these proposed main works, which received planning consent in 2024 (ref: 70903), are scheduled to commence in July 2026 and last through to completion, which is currently anticipated in autumn 2026.
4. The proposed Remediation Main Works Contract follows on from the current Pre-Construction Service Agreement (PCSA) period between the council and Conlon. Conlon were appointed in 2024 following a mini competition under the North West Construction Hub (NWCH) Low Value Construction Framework Lot 1, which facilitated early contractor involvement in the Pyramid Park remediation scheme.
5. This collaborative PCSA period has ensured the continued viability of the proposed main works and that the remediation scheme remains within the approved BLRF2 grant funding envelope and to the agreed delivery milestones, as per the Grant Funding Agreement (GFA) with OPE.
6. It should be noted that following remediation works the site must be disposed of to a private developer by 31st March 2027, who will lead the delivery of the residential development. Undertaking the remediation works in a timely fashion is therefore vital in ensuring the council complies with the existing Grant Funding Agreement.
7. The agreed enabling and land remediation works packages submitted by Conlon within the proposed main works JCT Design and Build Contract, have been independently market tested and verified by the council’s appointed cost consultants, to ensure that value for money has been achieved for the proposed main works scheme. Recommendation(s) It is recommended that Cabinet: 8. Authorise the council to appoint and enter into a Schedule of amendments to JCT Design and Build Contract (2016) with Conlon Construction Limited (company number 00708997) as the main contractor to deliver the Pyramid Park Remediation Main Works to unlock the site for residential development, up to a total contract value of £1,554,000.00 including contingency, and term of 90 days.
9. Accept the recommendation that Conlon Construction Limited undertake the Pyramid Park Remediation Main Works as per the estimated contract value set out in this report, subject to the agreement of any outstanding contract amendments and clarifications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.