Cabinet, Wednesday 8 July 2026 at 6.00pm

Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding Request

Approved Executive 1 paper

AI summaryBury Cabinet approved £153,009 extra capital funding to complete the Prestwich Travel Hub and formally accepted a £14m government transport grant to replace an earlier council funding allocation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproved £153,009 extra and accepted £14m grant
Money£153,009.00Additional capital funding for Phase 1A
What happens nextSummer 2026Practical completion of Travel Hub expected
Who it affectsPrestwich residents and usersFuture Travel Hub users and visitors

What was decided

Cabinet approved £153,009.00 of additional capital funding to complete Phase 1A (Travel Hub) and to be met from the Council's Capital Programme and Medium Term Financial Strategy, using part of the funding previously in place for Phase 1A before the CRSTS grant was offered. Report 2.1, 2.2

Cabinet formally accepted the £14m CRSTS grant from Transport for Greater Manchester via the Greater Manchester Combined Authority, subject to legal approval of the terms, and noted that £14m of council capital allocated to the Travel Hub is no longer needed. Report 2.3, 2.4

Authority to take all steps to implement the decision, including finalising arrangements and providing JV LLP member consents, was delegated to the Director of Place in consultation with the Monitoring Officer and the Section 151 Officer. Report 2.5

Why

To complete Phase 1A (Travel Hub) within the agreed programme timeline and allow the facility to open without undue delay. Report 3.1, 1.2

To meet planning pre commencement conditions, Building Control (Fire Strategy) requirements and to install parking control equipment, costs that cannot be met from the existing project contingency and that were identified after the £14m cost envelope was approved in July 2024. Report 3.2, 1.4, 1.5, 1.6

Formal acceptance of the £14m CRSTS funding by Bury Council is required to enable the grant funding to be claimed, removing the council's previous £14m capital funding risk for the build. Report 3.3, 8.3

What happens next

The Full Business Case is to be considered at the Bee Network Committee on 25th June 2026 and at the GM Delivery Group on 14th July 2026, after which the £14m grant can be drawn down. Report 9.3, 9.5

Additional works (crossing upgrade, PARCS installation and emergency egress) are to be completed in the coming weeks and in advance of the Travel Hub being handed over, with practical completion expected Summer 2026. Report 10.2, 1.2

The Council's Capital Programme will only be drawn on for the £153,009 if the final account confirms there is no remaining contingency, and borrowing will be repaid over 20 years at £14,536 per year. Report 7.6, 8.4

The money

  • £153,009.00 Additional capital funding requirement for Phase 1A Report 2.1, 1.3, 7.1
  • £14m CRSTS grant funding to be accepted from TfGM via GMCA Report 2.3
  • £29,337 Pedestrian crossing upgrade from pelican to puffin crossing Report P33, P34
  • £70,000 Additional cost for PARCS parking control equipment Report P33, 7.4
  • £53,672 Emergency egress works to meet Fire Strategy and Building Control Report P33, 7.5, P37
  • £14,536 per year over 20 years Revenue cost of borrowing the £153,009 from the Capital Programme Report 8.4
  • £1,330,000 per year Annual revenue cost that would have applied if the council had funded the full £14m build Report 8.4
  • £145,000 Confirmed total cost of the parking control equipment, up from an original estimate of £75,000 Report 7.4

Options considered

  • Rejected: Do not carry out the works associated with the planning pre commencement condition, including Building Control requirements. Would prevent the Council from opening the Travel Hub Report 4.1, P18
  • Rejected: Do not carry out the works associated with the parking control equipment. Would prevent the Council from opening the Travel Hub Report P18

Implications

  • Financial: The Council's Capital Programme and Medium Term Financial Strategy will fund £153,009, with revenue implications of £14,536 per year over 20 years, far less than the £1,330,000 per year that would have applied to the £14m build. Report 8.1, 8.4, P82
  • Legal: A grant funding agreement with TfGM or GMCA must be reviewed by legal prior to execution and the Council must agree TfGM's Subsidy Control analysis, with a repayment obligation if found non compliant. Report 16.1, 16.3
  • Legal: The development agreement with Morgan Sindall, the Muse subcontract and the Vinci construction contract may need variations, permissible under Public Contract Regulations 2015 regulation 72(f) and the Council's Contract Procedure Rules, with the Pagabo website updated. Report 16.4, 16.8
  • Risk: If the project contingency cannot cover the additional works, the £153,009 will need to be drawn from the Capital Programme; CRSTS approval and spending by end March 2027 are also flagged as risks. Report P70, P71, P72
  • Equalities: A full Equality Impact Assessment was completed for the planning permission and there are no outstanding equalities concerns at this stage. Report 13.2, P65
  • Staffing: Authority to implement, including finalising arrangements and giving JV LLP member consents, is delegated to the Director of Place in consultation with the Monitoring Officer and Section 151 Officer. Report 2.5

Who and where

  • Future users of the Prestwich Travel Hub and visitors to Prestwich Village centre, including pedestrians using the upgraded puffin crossing Report 1.1, 5.2
  • Bury Council and Muse Places Ltd as members of the Prestwich Regeneration LLP Joint Venture Report 1.1, 5.4, P87
  • Prestwich residents and local businesses who will benefit from later phases (new community hub, library, market hall, public realm and 248 new homes) Report P26, P57, 11.1

Timeline

  • 16th July 2024: Cabinet approved the £14m cost envelope for Phase 1A Travel Hub
  • 4th December 2024: Cabinet appointed Vinci Construction Limited as main contractor
  • 11th March 2026: Delegated authority given to finalise the third party operator contract Report 6.2
  • 25th June 2026: Bee Network Committee meeting to consider approval of the Full Business Case Report 9.3, 9.5
  • 8th July 2026: Cabinet decision approving the £153,009 additional funding and accepting the £14m grant
  • 14th July 2026: GM Delivery Group meeting to consider the Full Business Case Report 9.3, 9.5
  • Summer 2026: Practical completion of the Travel Hub expected Report 1.2
  • End March 2027: Deadline for spending the £14m CRSTS grant funding from Round 1 Report 9.4

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a Department for Transport funding programme for economic growth, regional inequality and transport decarbonisation.
  • TfGM: Transport for Greater Manchester, the local government body responsible for delivering Greater Manchester's Transport Strategy.
  • GMCA: Greater Manchester Combined Authority, made up of the ten Greater Manchester councils and the mayor.
  • PARCS: Parking Access and Revenue Control System, an automated system that manages vehicle entry, parking duration and payments.
  • JV: Joint Venture, in this case the Prestwich Regeneration LLP comprising Bury Council and Muse Places Ltd.
  • FBC: Full Business Case, the comprehensive financial and operational proposals required to evidence value for money for CRSTS.
  • LPA: Local Planning Authority, which manages rules, permissions and development frameworks under national legislation.
  • Planning gain: A secured contribution as part of granting planning permission to help mitigate the impacts of development and support local infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.44

Resolved

Cabinet: 1. Approved the additional capital funding requirement of £153,009.00 to ensure the full and successful delivery of Phase 1A (Travel Hub); 2. Approved the use of the Council’s Capital Programme and Medium-Term Financial Strategy to fund the above additional costs using part of the approved funding for Phase 1A that was in place prior to the CRSTS grant being offered; 3. Subject to legal approval of the terms under which it is provided, formally accepted the £14m CRSTS grant funding from Transport for Greater Manchester (TfGM) via the Greater Manchester Combined Authority (GMCA); 4. Acknowledged that, subject to the funding requirement outlined in the recommendation at Section 2.1, the allocation of £14m from the Council's Capital Programme to the Prestwich Travel Hub is no longer required, following the acquisition of £14m from the CRSTS programme to cover this expenditure; and 5. Delegated to the Director of Place, in consultation with the Monitoring Officer and Section 151 Officer, authority to take all steps necessary to implement this decision, including finalisation of any arrangements, and provision of any Council JV LLP member consents.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1The Prestwich Village Regeneration Project will deliver a comprehensive re- development of the Prestwich Village site including the Longfield Centre. The Council has formed a Joint Venture (the JV) with Muse Places to deliver this activity. The project will deliver a new village centre and contribute to the Council’s strategic aims (Bury 2030) and ‘Let’s Do It’ Strategy.

1.2Extensive progress continues to be made on the development and delivery of the project. The first phase (Phase 1A Travel Hub) remains on site with construction of the new facility still on schedule to be delivered Summer 2026.

1.3Further to the approval of several previous Prestwich Cabinet reports, this report seeks the approval for £153,009.00 additional capital funding for extra works to fully deliver the first phase of the Prestwich Village Regeneration project.

1.4Additional funding is required to deliver works that have been identified as a late requirement through the statutory planning consultation and subsequent discharge of the planning pre-commencement conditions for Phase 1A (Travel Hub) – planning gain. It also includes meeting the requirements of the Building Control Assessment (linked to the Fire Strategy) and costs of the installation of necessary parking control equipment to enable full operation of the facility. This risk was identified in the Cabinet report July 2024.

1.5The parking control equipment costs have unfortunately risen since approval for the £14m cost envelope nearly two years ago and until the final account figure is confirmed at practical completion, these costs, the planning gain and Building Control requirements fall outside of the project’s available contingency. However, these costs (in part or full) will be met by the contingency if it is not fully committed.

1.6Details of the above and an explanation for each requirement can be found in Section 7 of this report. Some works have yet to be delivered as part of the construction programme but are imminent to keep delivery of Phase 1A (Travel Hub) on track and to ensure that the Travel Hub will be in operation without undue delay. 1.7 The £14m cost of the Travel Hub will be met via external grant funding secured by officers from the City Region Sustainable Transport Settlement (CRSTS). The additional costs required to complete the project will be met via Bury Council’s Capital Programme and Medium-Term Financial Strategy.

Recommendation(s)

It is recommended that Cabinet:

2.1Approve the additional capital funding requirement of £153,009.00 to ensure the full and successful delivery of Phase 1A (Travel Hub).

2.2Approve the use of the Council’s Capital Programme and Medium-Term Financial Strategy to fund the above additional costs using part of the approved funding for Phase 1A that was in place prior to the CRSTS grant being offered.

2.3Subject to legal approval of the terms under which it is provided, formally accept the £14m CRSTS grant funding from Transport for Greater Manchester (TfGM) via the Greater Manchester Combined Authority (GMCA).

2.4Acknowledge that, subject to the funding requirement outlined in the recommendation at Section 2.1, the allocation of £14m from the Council's Capital Programme to the Prestwich Travel Hub is no longer required, following the acquisition of £14m from the CRSTS programme to cover this expenditure.

2.5Delegate to the Director of Place, in consultation with the Monitoring Officer and Section 151 Officer, authority to take all steps necessary to implement this decision, including finalisation of any arrangements, and provision of any Council JV LLP member consents.

Reasons for recommendation(s)

3.1To successfully complete the delivery of Phase 1A (Travel Hub) within the agreed programme timeline.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub): Additional Funding RequestDecisions 510 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 25 attended
EO
Councillor Eamonn O'BrienChair, apologies
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, apologies
CB
Councillor Carol BirchmoreCommittee Member, in attendance
JR
Councillor Jack RydeheardCommittee Member, in attendance

All 25 on the meeting page

On this subject at Bury

Search all
  1. Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding RequestThis decision
  2. Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved
  3. Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part AApproved
  4. Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)Approved
  5. Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part AApproved
  6. Prestwich Village Regeneration Project: Phase 1B and 2 Development StrategyApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open