AI summaryBury Cabinet approves disposal of Pyramid Park and Q-Park to Watson Construction Ltd for a residential scheme, with contractual sign-off delegated to senior officers.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSites to be sold to Watson Construction Ltd as development partner
Money£1.73 million BLRF2 grant at riskGrant clawback risk if milestones not met
What happens nextContract award notice and standstillEight working day standstill then contracts
Who it affectsNot stated
What was decided
Cabinet approved disposal of the Pyramid Park and Q-Park sites to Watson Construction Ltd (Company number 08621624) as the development partner. Report P12
Cabinet delegated award of all related contractual documents, including a development agreement, leases, licences and ancillary contracts, to the Executive Director of Place, the Executive Director of Finance, the Council Leader and the Cabinet Member for Regeneration and Growth. Report P13
Cabinet delegated the disposal itself, including commercial terms, best value consideration and the eventual capital receipt, to the same senior officers and members. Report P14
Why
The disposal is needed to meet Brownfield Land Release Fund grant milestones: the site must be sold to a developer by 31st March 2027 and the new homes completed by 31st March 2029. Report P6, P15
Watson was selected through a Competitive Flexible Procedure under the Procurement Act 2023, scored on 65% quality and 35% price, and was ranked first of two final bidders. Report P11, P12, P49
Failure to dispose of the sites would risk full clawback of the £1.73 million BLRF2 grant, loss of an anticipated capital receipt, ongoing anti-social behaviour on the vacant sites, and missed housing targets. Report P16, P17, P18
What happens next
Following Cabinet approval, the council will publish a Contract Award Notice under section 50 of the Procurement Act 2023 and observe an eight working day standstill period. Report P83, P84
Watson will progress a planning application for the residential scheme, targeting approval in 2027 and a start on site later that year, subject to planning timescales. Report P58
Remediation and enabling works at Pyramid Park by Conlon Construction Limited are due to complete in autumn 2026, readying the site for handover. Report P5, P57
The money
£1.73 million BLRF2 grant secured for Pyramid Park remediation, at risk of full clawback if milestones missed Report P4, P16
£85m Cost of the wider Bury Interchange redevelopment adjacent to the sites Report P30
Options considered
Chosen: Dispose of the sites to Watson Construction Ltd as preferred bidder. Selected through a competitive tender under the Procurement Act 2023; meets BLRF2 grant deadlines and aligns with masterplan Report P12, P49
Rejected: Do nothing. Sites would remain vacant, anti-social behaviour and decay would continue, BLRF2 milestones would be missed risking clawback, and regeneration ambitions would be set back Report P16, P17, P18
Rejected: Sell the sites on the open market. Risk of a purchaser land-banking and not delivering housing; a new open market process would take too long and risk missing BLRF2 milestones, with extra staff and consultant costs Report P18, P19
Implications
Financial: A RICS red book valuation has been used to benchmark offers; eventual capital receipt and Best Value consideration are delegated to senior officers. Report P53, P89
Financial: No revenue implications are expected; the existing remediation work is fully funded by the approved grants. Report P90
Legal: The procurement complied with the Procurement Act 2023, but a section 123 Local Government Act 1972 best value duty and Equality Act 2010 duties still apply. Report P53, P87
Legal: Q-Park is subject to existing leasehold interests, including a long lease to Q-Park Ltd and occupational leases with NHS Property Services Limited and Six Town Housing Limited; a title review is required. Report P9, P10, P88
Equalities: An initial screening found no equality impacts expected at this stage, with further review as the scheme progresses. Report P69
Climate: The scheme must deliver a 10% Biodiversity Net Gain uplift; proposals include air source heat pumps, photovoltaic panels and a parking-light approach. Report P72, P73
Risk: Risks include reputational damage, BLRF2 clawback, planning delays, site conditions, build cost inflation and supplier risk; a parent company guarantee is to be sought from Watson Construction (Holdings) Ltd. Report P74, P75, P76, P77, P78
Other: Watson has committed a social value package including work with Bury College and the GMCA Economic Inactivity Trailblazer programme. Report P63, P64, P65
Who and where
Residents of Bury, including families, older people, people needing extra care or specialist accommodation, and care leavers Report P12, P35, P37
Bury College students and staff, due to nearby construction and the new Metrolink footbridge Report P36, P62
Existing tenants and leaseholders at Q-Park, including Q-Park Ltd, NHS Property Services Limited and Six Town Housing Limited Report P9, P10
Transport for Greater Manchester and Metrolink users, due to linked interchange works Report P30, P31, P60
Timeline
March 2023: Cabinet authorised disposal of Pyramid Park and pursuance of BLRF2 funding Report P20
October 2023: Council notified of successful £1.73 million BLRF2 grant award Report P21
April 2026: Competitive Flexible Procedure launched via Find a Tender service Report P11
8th July 2026: Cabinet approved appointment of Conlon for remediation works Report P5
Autumn 2026: Pyramid Park remediation works due to complete Report P5, P57
9 September 2026: Cabinet approves disposal to Watson Construction Ltd Report P2
31st March 2027: BLRF2 milestone: Pyramid Park must be disposed of to a developer Report P6, P15
2027: Watson targeting planning approval and start on site later in the year Report P58
31st March 2029: BLRF2 milestone: new homes at Pyramid Park must be completed Report P6, P15
Plain English for the jargon
BLRF2: Brownfield Land Release Fund, a government programme providing capital funding to release council-owned brownfield sites for housing
CFP: Competitive Flexible Procedure, a procurement process introduced by the Procurement Act 2023
BNG: Biodiversity Net Gain, a mandatory 10% improvement in biodiversity required for new development
GFA: Grant Funding Agreement, the binding contract setting out the funder's terms and the recipient's obligations
PRoW: Public Rights of Way, public highways such as footpaths and bridleways protected in law
POS: Public Open Space, with a formal notice required when a council proposes to dispose of such land
PfE: Places for Everyone, the joint statutory development plan for nine Greater Manchester authorities
UDP: Bury Unitary Development Plan, the current planning policy document for the borough, being replaced by the Bury Local Plan
OPE: One Public Estate, the partnership delivering the BLRF2 programme
GMEU: Greater Manchester Ecology Unit, which provides specialist biodiversity advice to the ten district councils
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.56
Resolved
Decision(s): Cabinet: - Approved the plans for disposal of the sites at Pyramid Park and Q-Park, to Watson Construction Ltd (Company number 08621624) as the Development Partner. - Delegated the award of all contractual documents for example a Development Agreement (if applicable),lease agreements, licence and other ancillary contracts) that relate to the appointment of Watson Construction Ltd (Company number 08621624), to the Executive Director of Place and Executive Director of Finance, and the council Leader and Cabinet Member for Regeneration and Growth. ... view the full minutes text for item CA.56
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet Date: 09 September 2026 Subject: Disposal of Pyramid Park and Q-Park – Part A Cabinet Member for Regeneration and Growth Report of Cabinet Member for Housing Services
Summary 1. This paper outlines proposals to dispose of council-owned, disused brownfield sites at Pyramid Park and Q-Park, and to bring forward high-quality, sustainable residential development. Situated on the edge of Bury town centre, Pyramid Park and Q-Park have long been identified as key strategic regeneration opportunity sites and are highlighted in the Bury Town Centre Masterplan (2022) as suited for residential development at scale.
2. To further our ambitious plans to deliver hundreds of new homes across the borough over the coming years, in late-2023, the council was successful in securing £1.73 million in grant funding for the Pyramid Park site from the Government’s Brownfield Land Release Fund (BLRF2) programme.
3. The BLRF2 grant funding has enabled a package of land remediation and de- risking works to be delivered at the Pyramid Park site, thereby improving viability and readying it for future redevelopment. These land remediation works are currently underway and are being undertaken by the scheme contractor, Conlon Construction Limited (“Conlon”), with completion anticipated in autumn 2026. The appointment of Conlon was subject to a previous, separate report, approved by Cabinet at its meeting on 8th July 2026.
4. In line with the agreed BLRF2 grant funding milestones, upon achieving practical completion of the remediation works, Pyramid Park must be disposed of to a developer by 31st March 2027, who will be able to bring forward and realise the residential scheme at the site. The prospective developer would then be required to complete the new homes by 31st March 2029, at the latest.
5. Both Pyramid Park and Q-Park hold potential as highly sustainable, brownfield town centre sites, well suited to deliver a new, mixed typology, inter-generational housing development. This future residential scheme would be able to realise a significant element of the borough’s identified housing shortfall, helping a range of cohorts to live independently in a sustainable location, meeting a range of housing needs, and complementing the wider town centre regeneration that is taking place.
6. In its current form, Pyramid Park stands as a long-term, council-owned, vacant 7.4-acre brownfield opportunity site which has lain derelict and overgrown for over 15 years and regularly attracts anti-social behaviour, which is exacerbated due to poor visibility and a lack of natural surveillance. The site sits at a sunken level compared to its surroundings and there is limited access for pedestrians into Pyramid Park from the surrounding town centre.
7. Similarly, Q-Park is a council-owned, 1-acre brownfield site, which is highly visible, situated immediately opposite Bury Town Hall on Knowsley Street in the town centre. The three-storey Q-Park structure was designed to accommodate the future construction and loading of an additional six-storey structure atop the completed slab level, which has been confirmed by structural engineers. The undercroft car park space is in use via a long-lease agreement between the council and Q-Park Limited, whilst the airspace above has remained undeveloped and vacant since construction to slab level was completed in 2009 and its appearance is currently detrimental to the wider street scene.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.