Community Services Scrutiny Committee refused this item on Thursday 30 June 2011. Below is the council's own wording, with the papers it was decided on.
In conclusion the report recommended that a City Farm was not feasible at Cherry Hinton Hall for the following reasons:- I. Incompatibility with the continuation of the Folk Festival annually at the Hall; II. Although the City Farm concept was supported well during the Masterplan consultation in 2010 there was equally strong support to develop the masterplan which had already been presented. This has created a divergence of opinion, weakening the likelihood of gaining wider community support needed for success; and III. The risk and implications to the Council should the City Farm venture not be successful. Any alternative options considered and rejected: Not applicable. Scrutiny Considerations: Members expressed support for the Master plan. The timeframe was explained and a further version of report would return to this committee when costings were completed. Alternative funding sources were being explored. The Scrutiny Committee considered and endorsed the recommendations in the report unanimously. The Executive Councillor for Arts, Sport and Public Places approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
A site feasibility report for Cambridge City Council
By Phil Back Associates Ltd April 2011
Phil Back Associates Ltd Boston House 212-214 High Street Boston Spa WETHERBY LS23 6AD City Farm Site Feasibility Study
1 Introduction
The proposal to develop a City Farm for Cambridge first came to formal consideration by the City Council in the course of considering the Masterplan for Cherry Hinton Hall, which was taken to Community Services Scrutiny Committee in October 2010. The Council had been made aware of this proposal, and of the apparent desirability of locating the farm at Cherry Hinton Hall, whilst it was preparing a city-wide consultation on the Masterplan earlier in the year, and opportunity was taken to add an additional question to the Masterplan consultation to sound out public opinion on a City Farm at this location.
Residents (and other interested parties) gave the overall Masterplan, and its constituent elements, strong support in the public consultation in 2010. The Masterplan also attracted the committed support of the Friends of Cherry Hinton Hall, a group of local people established to ensure that the park’s ethos and qualities are protected and enhanced. As to the City Farm idea, the response showed that the proposal had significant support, but also that there was substantial opposition to a Cherry Hinton Hall location.
The consultation was reported back to members at the October 2010 meeting, where an officer’s report noted1 that
“the City Farm concept...has substantial support and cannot be ignored because it did not form part of the initial scoping discussions nor feature in the Masterplan. There is, though, limited detail on how this may impact on the site, and on other Masterplan content, and therefore a feasibility study should be undertaken, to determine whether a City Farm is feasible within a reasonable footprint in Cherry Hinton Hall, or indeed whether a different location might be preferable.”
Members also heard representations from the proposers of the City Farm, in support of the proposal, and from the Friends of Cherry Hinton Hall, who oppose the idea. After considering the officers’ report, and the results of the consultation, Members...
“...Supported the principle of a City Farm and instructed officers to work with the City Farm project to prepare a feasibility study to identify the most appropriate location for a City Farm within the city;
“Agreed to liaise with the Folk Festival project team to integrate the Masterplan with operational requirements of the Folk Festival.” 2
The Masterplan and its origins are reviewed in detail elsewhere3, but the map below shows the geography of the plan, and denotes in outline the area which a City Farm would occupy
1 Report to Community Services Scrutiny Committee minutes, meeting on 14th October 2010, para 1.6 2 Community Services Scrutiny Committee minutes, meeting on 14th October 2010
Phil Back Associates Ltd 2 City Farm Site Feasibility Study
– in essence the former propagation site, which was closed by the City Council in 2007, with the structures that existed at that time removed or demolished, and which has remained unused ever since. In the Masterplan this area is designated as a performance area with a mix of grass, planted beds, and informal tree planting, and a new structure that would provide toilet and cafe facilities.
The location in question is behind the existing hall building (which is now used by an independent school) and adjacent to a structure known as the Atcost building, which is leased out Cambridge Regional College (as is a cottage next to the hall) and used as a training and educational facility focussed on the needs of vulnerable and alienated young people. A small area adjacent to the site is used at present as a storage area by the City Council; a small Council depot formerly occupied this part of the site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.