Community Services Scrutiny Committee refused this item on Thursday 30 June 2011. Below is the council's own wording, with the papers it was decided on.
To make effective and efficient use of Council buildings and to accelerate the building works timetable to benefit from the current dispensation from HMRC which will allow £500,000 to be returned to Reserves. Any alternative options considered and rejected: Not applicable. Scrutiny Considerations: The Head of Specialist Services tabled slightly amended recommendations. In response to member questions he confirmed that a favorable planning decision from South Cambs District Council was expected shortly. The timeframes suggested were tight but achievable. The Scrutiny Committee considered and endorsed the recommendations in the report unanimously. The Executive Councillor for Community Development and Health approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
The Mercury Abatement project at the City Crematorium (SC379) creates a new crematory to house mercury abatement equipment and three new cremators. This will leave the old crematory without an operational function and with no direct site access should works
Page 1 of 7 be undertaken in the future. This scheme is to undertake the refurbishment of the former crematory whilst the site is still accessible for projects of this scale to maximise the use of the space created and provide modern facilities for the bereaved, mourners, staff, officiants and funeral directors. It is also planned to provide a glazed roof above the Cloisters, again whilst the site is accessible, allowing covered access to floral and other tributes.
Target Start date November 2011 Target completion date February 2012
1.2The Cost Total Capital Cost £206,000
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £0
Repairs & Renewals £206,000 21158
Section 106 £0
Other £0
Revenue Cost current budget Year 1 provision current budget Ongoing provision
1.3The Procurement It is anticipated that the most efficient method of procurement is to use the building contractors extant as part of the Mercury
Page 2 of 7 Abatement project. A waiver will be sought to enable the works to be procured and delivered within the financial year.
2 Capital Project Appraisal & Procurement Report
2.1What is the project?
The Mercury Abatement project will create a new crematory: Further investment is needed to remove the redundant equipment and make efficient use of the space created as outlined in Section 6.2 of the Service Business Plan dated December 2010. The works outlined below are considered necessary to meet the requirements of a modern service and also to meet the welfare needs of the bereaved, staff, officiants and funeral directors.
• Removal of existing cremators and closing existing flues • Creation of new work areas (including refrigeration) • Creation of offices and business reception • Improvements to vestry facilities • Installation of staff toilets and showers • Removal of suspended ceiling to allow access to natural light • New undertakers’ restroom • Improved transfer chamber (from chapels) • Creation of space for operational expansion • Glazed roof to cloisters adjacent to both chapels
The Bereavement Services team consider that the works should be undertaken at the same time as the Mercury Abatement project to mitigate the Council’s exposure to VAT partial exemption risk and to gain operational and cost efficiencies of using builders whilst on site.
2.2What are the aims & objectives of the project? • to make effective and efficient use of Council buildings • to accelerate the building works timetable to benefit from the current dispensation from HMRC which will allow £500,000 to be returned to Reserves
Page 3 of 7 2.3 Summarise the major issues for stakeholders & other departments?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.