Community Services Scrutiny Committee refused this item on Thursday 30 June 2011. Below is the council's own wording, with the papers it was decided on.
The policy of allocating developer contributions for the provision and improvement of community facilities had been in place for several years. The allocation of off-site contributions, by area, provides a response to the challenge of providing and enhancing facilities as close as possible to the location of the development. It also speeds up the decision making process and enhances the Council’s approach to the localism agenda, enabling local residents to shape provision in their neighbourhood. Any alternative options considered and rejected: Not applicable Scrutiny Considerations: The Head of Community Development introduced the report. Members this approach as it had help clear a back-log of projects and was welcomed. In response to member questions, the officer explained that off-site referred to developer S106 contributions towards facilities and improvement to be delivered in the area but not on the development site. Lessons had been learnt from the North Area Committee pilot and from the work already completed using this approach in the East Area. This would contribute to future work on devolved decision making. Councillor Todd-Jones proposed the following amendment to the recommendation (additional wording underlined and in italic): The scrutiny committee recognises that scrutinising the policy framework remains part of the pre-scrutiny function but agrees to waive its pre-scrutiny function for making decisions (including project appraisals, where required) about funding improvements to ‘off-site’ community facilities in the East Area that are funded from developer contributions. The amendment was agreed unanimously. The Scrutiny Committee considered and endorsed the amended recommendations unanimously.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1A new approach to allocating funding to enhance the provision of local community facilities was considered by East Area Committee in August 2010 and has been operating consensually between ward councillors and the Executive Councillor for Community Development and Health since this time.
1.2This report asks the Community Services Scrutiny Committee to support this approach by waiving its right to pre-scrutinise decisions about the allocation of funding from developer contributions for enhancing local community facilities within East Area.
Recommendations
The Scrutiny Committee is recommended:
2.1To agree to waive its pre-scrutiny function for making decisions (including project appraisals, where required) about funding improvements to ‘off-site’ community facilities in the East Area that are funded from developer contributions.
Background
3.1Following discussions between the previous Head of Community Development, the Executive Councillor for Community Development and Health and the Chair and Spokes of East Area Committee, a report was presented to East Area Committee on 19 August 2010.
Report Page No: 1 3.2 The purpose of the report was to enable members of the Area Committee to consider options for funding improvements to community facilities in the east of the city. Also, to recommend to the Executive Councillor for Community Development, Health and Community Safety a preferred approach to the scrutiny of potential projects and to the allocation of the funds from planning obligations on developers, also known as Section (s)106 contributions.
3.3The policy of allocating developer contributions for the provision and improvement of community facilities has been in place for several years. The allocation of off-site contributions, by area, provides a response to the challenge of providing and enhancing facilities as close as possible to the location of the development. It also speeds up the decision making process and enhances the Council’s approach to the localism agenda, enabling local residents to shape provision in their neighbourhood.
3.4Off-site contributions are rarely large enough (individually or collectively) to fund new facilities. Consequently, investing in existing facilities or working in partnership with independent providers to create or enhance facilities has invariably proved to be the most effective strategy. Several partners have also used the availability of Council funding to attract other external funding.
3.5The East Area report can be seen on the Council’s website at this link: http://www.cambridge.gov.uk/democracy/mgConvert2PDF.aspx?ID=2 76&T=10 (see item 7)
3.6Whilst ward members and the Executive Councillor agreed to the process whereby the area committee considered and recommended the allocation of funds to the Executive Councillor, this needs to be supported by Community Services Scrutiny Committee by means of waiving its right to pre-scrutinise decisions about the funding of local community facilities through developer contributions.
4. Implications :-
(a) Financial
Generally, investment in improvements to community facilities will be in the form of capital grants to the owners and managers of the facilities. They will be required to enter into a legal agreement with the Council to secure the grant. The agreements will set out the conditions with which the grant recipients will need to comply, including, in most Report Page No: 2 cases, a claw-back clause if for any reason the project is not delivered and/or the money is not used for the purposes for which it was given.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.