2010/11 Revenue and Capital Outturn, Carry Forwards and Significant Variances
RefusedScrutiny1 paper
Community Services Scrutiny Committee refused this item on Thursday 30 June 2011. Below is the council's own wording, with the papers it was decided on.
As detailed in the officer’s report. Any alternative options considered and rejected: Not Applicable Scrutiny Considerations: The Principal Accountant introduced the report. The committee made the following comments: I. Members questioned the carry forward requests, which were unusually large even when Brandon Court figures were removed. II. Improved budget management was suggested as a way forward. The Director of Community Services confirmed that all directors were examining the detail of slippages. A late arriving grant for CLG had skewed the figures for the end of year. The Scrutiny Committee considered and endorsed the recommendations in the report by a vote of 5 to 0. The Executive councillor for housing approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted): None
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report presents a summary of the 2010/11 outturn position (actual income and expenditure) for services within the Housing portfolio, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2011/12 are identified.
1.2It should be noted that this report reflects the reporting structure in place prior to the recent changes in Executive reporting responsibilities.
Recommendations
The Executive Councillor is recommended:
a) To agree which of the carry forward requests, totalling £120,990 as detailed in Appendix C, are to be recommended to Council for approval.
b) To seek approval from Council to carry forward capital resources to fund rephased net capital spending of £7,000 from 2010/11 into 2011/12, as detailed in Appendix D.
c) To seek approval from Council to rephase capital expenditure of £32,000 in respect of investment in disabled facilities grants into 2011/12. d) To seek approval from Council to rephase capital expenditure of £423,000 from 2010/11 into 2011/12, in respect of investment in the creation of the Assessment Centre, and to increase the overall budget sum by a further £125,000 to meet identified additional costs of the project, resulting in £2,797,000 being available to be spent in 2011/12 and 2012/13 to complete the project. The additional £125,000 investment has been fully funded by an increase in the CLG contribution towards the project.
e) To seek approval from Council to carry forward capital resources to fund rephased capital spending of £6,159,000 between 2010/11 and 2011/12, in relation to investment in the Housing Revenue Account, as part of the Housing Capital Investment Plan, as detailed in Appendix E and the associated notes, with the resulting need to increase the use of revenue funding of capital expenditure by £951,000 in 2011/12.
f) To seek approval from Council to rephase anticipated capital income of £308,000, from 2010/11 to 2011/12, in the form of the final tranche of Homes and Communities Agency Grant (£25,000) and an element of prudential borrowing (£283,000), both required to complete the 7 units of new build affordable housing.
Background
Revenue Outturn
3.1The outturn position for the Housing portfolio, compared to final revenue budget, is presented in detail in Appendix A.
3.2Appendix B to this report provides explanations of the main variances.
3.3Appendix C sets out the final list of items, for this service portfolio, for which approval is sought to carry forward unspent budget from 2010/11 to the next financial year, 2011/12.
3.4The overall revenue budget outturn position for the Housing portfolio is set out in the table below: Housing £ 2010/11 Revenue Summary Final Budget 2,771,220 Outturn 2,514,885
Variation – Underspend for the (256,335) year Carry Forward Requests: 120,990
Net Variance (135,345)
The variance represents 4.88% of the overall portfolio budget for 2010/11
Capital Outturn
3.5Appendix D shows the outturn position for schemes and programmes within the Housing portfolio, with explanations of variances.
3.6An overall underspend of £7,000 has arisen, due to slippage in investment through the landlord accreditation scheme. Permission has been sought form the grant provider to utilise the remaining resource in 2011/12.
3.7Appendix E shows the capital schemes covered by the Housing Capital Investment Plan (Housing Revenue Account and Housing General Fund schemes funded from HRA resources).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.