To approve the revised capital programme as attached at Appendix A, which includes approved amendments to the programme, detailed at point 11 and 12 of this report, since the last Capital Monitoring report was approved by Cabinet in February 2022. Two items are to be approved within this report: · £46k increase to Health Hub – Whittle Surgery to reflect the final costs of this scheme. · £104k Chorley Adaptation Grant to reflect an increase in the grant funding allocation to the Council. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st March 2022. 1. To approve the revised capital programme as attached at Appendix A, which includes approved amendments to the programme, detailed at point 11 and 12 of this report, since the last Capital Monitoring report was approved by Cabinet in February 2022. Two items are to be approved within this report: · £46k increase to Health Hub – Whittle Surgery to reflect the final costs of this scheme. · £104k Chorley Adaptation Grant to reflect an increase in the grant funding allocation to the Council. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st March 2022. Reasons for recommendations: To ensure the Council’s Capital Programme is monitored effectively. Other options considered and rejected: None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report the outturn financial position of the Council in respect of the capital programme at 31st March 2022, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 31st March 2022.
Recommendations to Executive Cabinet
2. To approve the revised capital programme as attached at Appendix A, which includes approved amendments to the programme, detailed at point 11 and 12 of this report, since the last Capital Monitoring report was approved by Cabinet in February 2022. Two items are to be approved within this report: £46k increase to Health Hub – Whittle Surgery to reflect the final costs of this scheme. £104k Chorley Adaptation Grant to reflect an increase in the grant funding allocation to the Council
3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report);
4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st March 2022.
Reasons for recommendations
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None. Corporate priorities
7. The report relates to the following corporate priorities:
Involving residents in improving their A strong local economy local area and equality of access for all
Clean, safe and healthy communities An ambitious council that does more to meet the needs of residents and the local area
Background to the report
8. The capital budget for 2021/22 was set at £38.1m at Council in February 2021. This was increased following approval of the 2020/21 outturn to £46.2m. The monitoring report as at 31st July 2021 increased the total budget to £46.6m. This was reduced to £42.6m in the quarter two monitoring report and reduced further to £28.6m at quarter three.
Section A: Capital Programme
Key issues
9. The total cost of the Council’s capital investment programme for 2021/22 has decreased since the quarter 3 monitoring report approved by Cabinet, from £28.6m to £23.9m as at 31st March 2022. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
10. The breakdown of the net decrease in the programme of £4.7m is detailed in Appendix B.
11. Budget variations approved since the last monitoring report have resulted in a total increase of £3.181m to the capital programme, comprising an increase of £0.046m in 2021/22 and an increase of £3.135m in future years. The table below details the changes. Table 1: Approved budget changes since the last monitoring report
Increase / Increase / (Reduction) (Reduction) 2022/23 Date Scheme 2021/22 and future Approved by approved years £’000 £’000 An ambitious council that does more to meet the needs of residents and the local area Subject to Executive Health Hub – Whittle Surgery 46 - approval of Cabinet this report
Town Hall Decarbonisation - 1,590 Council 19-Apr-22
A strong local economy
Bengal Street - 1,100 Council 22-Feb-22
Clean, safe and healthy homes and communities Subject to Chorley Adaptation Grant Executive - 104 approval of (increased allocation) Cabinet this report Astley Cottage - 341 Council 17-May-22
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.