To approve the revised capital programme, attached at Appendix A, which includes an amendment to the programme of £3.989m, as detailed at point 12 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31st March 2024.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring. Corporate priorities
7. The report relates to the following corporate priorities:
Housing where residents live well A green and sustainable Borough
An enterprising economy with vibrant Healthy, safe, and engaged communities local centres in urban and rural areas
Background to the report
8. The Capital Budget for 2023/24 was set at £21.103m by Council in February 2023. This was increased following approval of the 2022/23 outturn to £22.998m, then further amended in the Quarter 1, Quarter 2 and Quarter 3 Capital Monitoring Reports covering the first 9 months of the year to £15.822m as approved at Executive Cabinet in February 2024.
9. Following the changes detailed in this report, the total programme now stands at £13.185m the details of which are shown in Appendix B.
Section A: Capital Programme
Key issues
10. The total cost of the Council’s capital investment programme for 2023/24 has decreased since the 2023/24 Quarter 3 report approved by Cabinet, from £15.822m to £13.185m as at 31st March 2024. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
11. The breakdown of the net decrease in the programme of £2.636m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme
12. Budget variations approved since the last monitoring report have resulted in a total increase of £3.989m to the capital programme. The table below details the changes. Table 1: Approved budget changes since the last monitoring report Increase / Increase / (Reduction) Virement Virement (Reduction) Date 2024/25 and From To Approved by 2023/24 approved future years £’000 £’000 An Enterprising Economy With Vibrant Local Centres In Urban and Local Areas Asset Improvements 600 Council 27/02/24 18/07/23/ Chorley Bus Station 445 Council/Cabinet 22/02/24 18/07/23/ Chapel Street 83 Council/Cabinet 22/02/24 18/07/23/ Euxton Private development - retail units 50 Council/Cabinet 22/02/24 Astley Village Nursery and Retail Units 149 Cabinet 22/02/24 Green And Sustainable Borough Delivering green agenda (65) This report 03/07/24 Fleet Replacement 900 Council 16/04/24 Housing Where Residents Live Well Chorley Adaptation Grant (Formerly 775 Council 27/02/24 DFG) Leisure Centres - capital works and 200 Council 27/02/24 maintenance Gillet playing fields 724 Council 09/05/24 Jubliee Rec (272) This report 03/07/24 Birkacre Reservoir 400 Council 16/04/24 TOTAL (65) 4,054 - -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.