to 1) Note the progress being made on the preparation of the Chesterfield-Staveley Regeneration Route; 2) Approve in principle the carrying out of further consultation and delegate authority to the Executive Director for Place, in consultation with the Cabinet Portfolio Holder for Infrastructure and Environment to agree the format and timing of this; 3) Note the need for the allocation of up to £1.8million from the Regeneration Kick Start Fund to cover essential work before Cabinet next receives a report on the project, expected to be in September 2023; and 4) Approve in principle the acceptance of grant funding towards project preparation and delegate authority to the Director of Finance and ICT to review terms and conditions and to accept grant funding of up to £7.3 million. to 1) Note the progress being made on the preparation of the Chesterfield-Staveley Regeneration Route; 2) Approve in principle the carrying out of further consultation and delegate authority to the Executive Director for Place, in consultation with the Cabinet Portfolio Holder for Infrastructure and Environment to agree the format and timing of this; 3) Note the need for the allocation of up to £1.8million from the Regeneration Kick Start Fund to cover essential work before Cabinet next receives a report on the project, expected to be in September 2023; and 4) Approve in principle the acceptance of grant funding towards project preparation and delegate authority to the Director of Finance and ICT to review terms and conditions and to accept grant funding of up to £7.3 million.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Regeneration Pipeline Programme – Chesterfield-Staveley Regeneration Route (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1Staveley North and Whittington and Brimington.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and/or it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To update Cabinet on progress and next steps for preparation of the Chesterfield-Staveley Regeneration Route (CSRR); to seek approval to the carrying out of consultation, to note the provision of further financial resources to enable work to continue; to seek approval in principle to the acceptance of grant funding. 4. Information and Analysis
4.1The CSRR constitutes the single, largest project within the Council’s Regeneration Pipeline (part of the Growth Zone North Programme), creating a highway link of 6km that will parallel the A619 between Tapton and Staveley and open up to the east of Chesterfield along the ‘Staveley Corridor’ and support the delivery of up to 1,800 homes and 3,400 jobs.
4.2The scheme has a provisional grant allocation through the Government’s Large Local Majors (LLM) element of the Roads Investment Strategy (RIS) programme which is managed by the Department for Transport (DfT). Currently, the scheme is at a preparatory stage – Outline Business Case (OBC) - and is targeted for construction between 2025 and 2027. Derbyshire County Council (DCC) is the scheme sponsor on behalf of DfT, working closely with Chesterfield Borough Council (CBC) as a committed delivery partner.
4.3Ahead of construction, the scheme requires planning consent - for which preparatory work is underway - and land assembly, for which Cabinet approvals will be sought in due course. All affected landowners are already engaged in the preparation process through matters such as access to land for surveys, but no negotiations have yet commenced over land acquisition.
4.4The project has strong governance in place which reflects the partnership nature of delivery. In addition to focused working groups involving officers from DCC and CBC framed around key themes/issues, the governance arrangements are:
• The Project Control Board - meets weekly, is chaired by DCC and attended by all key professional officers from both the County and Borough/District councils, supported by external project management and contractor input both directly and through various working groups. This informs the provision of updates to the Regeneration Programme Assurance Board. • The elected member Programme Board – is strategic and advisory. It meets bi-monthly and comprises senior officers and DCC portfolio holders. • The Joint Growth Board – meets every two months and is attended by the Leaders, portfolio holders and senior officers of both the County and Chesterfield Borough councils to address the key relationship and delivery issues across an agreed programme of projects, including the CSRR. 4.5 It is considered that the current governance arrangements provide senior officers and portfolio holders with sufficient oversight of the various workstreams to ensure that the project remains on track for successful delivery or to quickly identify and address issues during the lifespan of the project.
Current Position and Next Steps 4.6 Cabinet last considered the project at its meeting of 8 December 2022 and agreed to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.