Resolved
To note the progress and key achievements of the Modern Ways of Working Phase 2 Programme. To note the progress and key achievements of the Modern Ways of Working Phase 2 Programme.
Cabinet noted this item on Thursday 21 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the progress and key achievements of the Modern Ways of Working Phase 2 Programme. To note the progress and key achievements of the Modern Ways of Working Phase 2 Programme.
FOR PUBLICATION
DERBYSHIRE COUNTY COUNCIL
CABINET
21 September 2023
Report of the Executive Director - Corporate Services & Transformation
Modern Ways of Working (MWOW) Phase 2 - Progress update
1. Divisions Affected
1.1County Wide
2. Key Decision
2.1This is not a Key Decision
3. Purpose
3.1The purpose of this report is to provide Cabinet with an update on the Modern Ways of Working (MWoW) Phase 2 Programme of work. The report outlines key achievements, and change in scope from the original approved Outline Business Case (OBC) on 5 May 2022.
3.2Cabinet are asked to note progress made under the MWoW Phase 2 Programme, the key achievements and the closure of the programme.
4. Information and Analysis
4.1Background In September 2020, the Council commenced work on its Modern Ways of Working (MWoW) Programme. A key workstream identified during the development of the Council’s Enterprising Council Strategy, the Programme looked to maximise the opportunities available through changes to working practices following the pandemic. 4.2 Phase 1 evolved from undertaking a collaborative approach to co- ordinate a number of different workstreams to respond to a changing working landscape following the pandemic. A Business Continuity Group (BCG) was developed to consider the immediate, and longer term, impact on employees, the support required and key messages.
4.3Phase 1 of the Programme engaged with a Group of over 170 employees to help to start to shape the Council’s approach. A series of workshops were held with this cohort of employees to share their views on what Modern Ways of Working meant for them, both in the immediate short term, and in the future. A more flexible and hybrid approach to working arrangements was a primary finding. To support the flexible and hybrid approach, consideration was given to the introduction of an asset rationalisation approach and utilising a smaller working footprint.
4.4The principal aspiration for MWoW Phase 1, was to reintroduce employees back into County Hall at speed and, aligned with the cessation of Covid-19 measures at that time, take advantage of using office spaces in a different way. The programme of activity for MWoW Phase 1 was approved at Cabinet on 17 June 2021 and included the allocation of a budget of £0.401m to support implementation.
4.5The Phase 1 Programme comprised of five workstreams as follows:
• People • Communications & Engagement • Information Communication Technology (ICT) • Property • Information Governance
4.6The Programme was initially focused on County Hall and was widened out to include John Hadfield House and Chatsworth Hall. This involved carrying out departmental surveys to understand what future spaces were required by teams, de-cluttering offices, securing analogue records for movement and re-locating staff. This work saw the development and installation of more flexible spaces including hot desking, informal break-out areas and additional meetings rooms. Installation of a large number of workstations and pilot meetings rooms equipped with ICT also took place, to facilitate agile working and hybrid meetings.
4.7The MWoW approach today has been built on the significant shift in working practices, including the rapid implementation and use of new technology across the organisation, with the Council seeking to base work, and relationship with the people of Derbyshire, on quality of service and process, rather than the desks being used or the buildings which staff sit in.
4.8Work undertaken across the organisation and with staff involved during Phase 1 revealed that there was the potential to realise huge benefits for the organisation and the services it delivered to the public as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Modern Ways of Working (MWOW) Phase 2: Progress updateReport | 212 KB | DownloadRead as text |
Follow Cabinet at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... | Noted | Open |
| 10 Sep 2026 | To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. | Approved | Open |
| 10 Sep 2026 | Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... | Noted | Open |
| 10 Sep 2026 | Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... | Approved | Open |
| 10 Sep 2026 | Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.