RESOLVED to: 1) Note the implications of flood risk for the process to be followed in submitting a planning application for the Ashbourne Relief Road and in obtaining a successful outcome; 2) Approve the approach recommended in this report that two options, coloured blue and pink on Figure 2, be the subject of further assessment ahead of a further report to Cabinet to identify one of these as ‘preferred’; and 3) Approve the carrying out of informal targeted engagement with landowners and occupiers over the blue and pink options.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Ashbourne Relief Road – Route Alignment and Public Consultation (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1Dovedale and Ashbourne.
2. Key Decision
2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To advise Cabinet of the outcome of pre-application and sequential testing of the proposed Ashbourne Relief Road; to outline a proposed approach to submission of the planning application; and to seek approval in principle to assess alterations to scheme alignment and authorisation of targeted public engagement around these alterations.
4. Information and Analysis
Overview of Previous Decisions and Commissioned Studies 4.1 At its meeting of 29 June 2017, Cabinet agreed for detailed investigations, surveys and preparatory work to be undertaken to explore strategic solutions to the traffic issues being experienced within the unique historic core of Ashbourne (Minute No.195/17 refers). This particularly related to north-south movements along the A515 which connects the Peak District National Park to the national strategic road network (via the A50 trunk road) and passes through Ashbourne town centre. This work culminated in public consultation, carried out in late 2020, and reported to Cabinet at its meeting of 11 February 2021 (Minute No. 28/21 refers). The options under consideration were:
• Option 1 – Small-scale schemes • Option 2 – Junction improvements • Option 3 – Western bypass options o ‘A’ – following an alignment coloured red on Figure 1 below o ‘B’ – Following an alignment coloured pink on Figure 1 • Option 4 – Eastern bypass option
4.2Cabinet agreed that ‘Western Bypass Option A’ be confirmed as the ‘preferred route’ and that Western Bypass Option B and the Eastern Bypass be dismissed from further assessment.
Figure 1
4.3In the February 2021 report, a detailed description of Western Bypass Option A was given, specifying its exact length (2,817 metres) and the precise locations of its junctions with the A52 and A515, together with details of the alignment between these points. Cabinet’s authorisation is therefore required to pursue any design which varies from these, and this is sought through this report on the basis of further analysis below: Scheme Preparation and Implications 4.4 Progress towards producing the Environmental Statement for the preferred option has been underway for some time, with a substantial amount of work carried out on ecological surveys and analysis alongside preliminary design of the scheme. This reached the point in March 2023 of the commencement of pre-application liaison with the County Council’s Regulatory Services (as the Council will be the determining planning authority, as well as the applicant). By far the most significant consideration arising from this is with regard to flood risk and the implications this could have both on the delivery programme and on the outcome.
4.5Where a proposed development impacts upon Defined Flood Zones 2 or 3, as is the case for the preferred route, the applicant must supply the outcome of a ‘sequential test’. This forms part of the planning application so is considered by the planning authority at the point of submission rather than being resolved in advance. Guidance relating to this sets out that the applicant must assess potential alternative ‘sites’ and identify any which could be suitable for the proposed development. For alternative sites, the assessment should cover any issues that would prevent development on the site and whether these issues could be overcome. In this regard, the relief road should be regarded as the ‘site’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.