Derbyshire County Council
Cabinet, Thursday 21 September 2023 at 2.00pm

A6 Matlock to Whatstandwell Highway Retaining Wall Maintenance Works

Approved Executive 1 paper

Cabinet approved this item on Thursday 21 September 2023. Below is the council's own wording, with the papers it was decided on.

Item139/23

Resolved

RESOLVED to: 1) Approve, in accordance with Protocol 1 of the Financial Regulations and standing order contracts and the Public Regulations (PCR) 2015, to procure suitable contractors(s) to deliver the A6 Matlock to Whatstandwell Highway Retaining Wall Maintenance Works; and 2) Approve for the Executive Director for Place to award contracts, in line with the Council’s Financial Regulations and the Scheme of Delegation.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

21 September 2023

Report of the Executive Director - Place

A6 Matlock to Whatstandwell Highway Retaining Wall Maintenance Works (Cabinet Member for Highways, Assets and Transport)

1. Divisions Affected

1.1Alport and Derwent, Matlock and Wirksworth.

2. Key Decision

2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To seek Cabinet approval, in accordance with Protocol 1 of the Financial Regulations and standing order contracts and the Public Regulations (PCR) 2015, to procure suitable contractor(s) to deliver the A6 Matlock to Whatstandwell Highway Retaining Wall Maintenance Works.

3.2To seek Cabinet approval for the Executive Director – Place to award contracts, in line with the Council’s Financial Regulations and the Scheme of Delegation. 4. Information and Analysis

4.1The structures' ongoing maintenance has revealed that, as traffic volumes and vehicle weights have increased, several parts of the retaining wall require considerable repairs. The partial fall of a retaining wall near Matlock Bath showed the importance of targeted repairs to ensure vehicle access. The present Department for Transport (DfT) funding formula excludes retaining walls, posing a severe risk to the Council's capacity to provide sufficient maintenance on existing retaining walls and necessitating a reliance on reactive maintenance and pressure bids.

4.2Following a successful bid, the DfT awarded the Council £4.867 million from its Highways Maintenance Challenge Fund to undertake the maintenance of retaining walls along the A6 between Matlock and Whatstandwell. Approvals gained, under Protocol 2(a) and (b) of the Council’s Financial Regulations, led to the award of a contract through the Midlands Highway Alliance medium scheme framework (MSF3).

4.3Designers and the Principal Contractor were engaged at an early stage in the project to undertake extensive ground investigations to determine the condition of these walls. Priority designs for the repair work were developed and a target price submitted. A target price is the best estimate of costs, which may increase during the project, especially given the current unstable market with ongoing price increases for labour and materials. To maximise the available project budget, the Council’s Project board has agreed to prioritise specific sites for repair, based on the findings from the extensive site investigations already undertaken. The Project board intends to review and apply for further funding to undertake additional work along the A6 retaining wall corridor.

4.4The knowledge gained from the ground investigations and the wall repair designs remains invaluable. The Council now has a true understanding of the wall conditions, which will assist asset management, enable the development of a reactive plan to undertake the necessary repairs, and aid future bid applications.

4.5The Council’s Project Team has developed a priority risk scoring system, looking at each individual section of wall to consider the risks and the potential for a collapse if the Council does not undertake the wall repairs, and then ranking them in order of priority for repair. The results will be used to develop repair work packages for procurement to target spending where it is most needed. The types of repairs will include: • Ground Anchors, including netting. • Wall thickening techniques such as buttresses. • Reinforcement of earthworks in front of wall. • Pressure grouting to fill inaccessible voids. • Stonemasonry repairs, including full and partial wall rebuilds. • Associated drainage works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A6 Matlock to Whatstandwell Highway Retaining Wall Maintenance WorksReport 103 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
BL
Councillor Barry LewisChairman, present
SS
Councillor Simon SpencerVice-Chairman, apologies
CC
Councillor Charlotte CupitCommittee Member, present
AD
Councillor Alex DaleCommittee Member, present
CH
Councillor Carol HartCommittee Member, present
NH
Councillor Natalie HoyCommittee Member, present
TK
Councillor Tony KingCommittee Member, present
JP
Councillor Julie PattenCommittee Member, apologies
CR
Councillor Carolyn RenwickCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance
CC
Carol CammissOfficer, in attendance

All 18 on the meeting page

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies