3/11/1927/FP – Erection of 16 dwellings and creation of access at land south of 10 Acorn Street, Hunsdon for Croudace Homes Ltd
DecidedCommittee2 papers
Development Management Committee decided this item on Wednesday 29 February 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED – that, subject to the applicant entering into an amended legal obligation pursuant to Section 106 of the Town and Country Planning Act 1990 in respect of the following amended matters: 1. The provision of six affordable dwellings comprising of 4no. 2 bed units and 2no. 3 bed units of which 33% should be rented (2 dwellings) and 66% shared ownership (4 dwellings); 2. A financial contribution of £38,210 towards secondary education, £2,484 towards childcare, £722 towards youth and £2,776 towards libraries; 3. A financial contribution of £28,000 towards the provision for traffic calming and safety enhancement measures and to promote sustainable transport measures; 4. A financial contribution of £5,100 towards Parks and Public Gardens, £13,250 towards Outdoor Sports Facilities and £2,295 towards Children and Young People; 5. 15% of the dwellings shall be constructed to ‘Lifetime Homes’ standard; 6. The provision of fire hydrants. in respect of application 3/11/1927/FP, planning permission be granted subject to the conditions detailed in the report now submitted.
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
That, subject to the applicant entering into a S106 agreement requiring the following matters:
• The provision of six affordable dwellings comprising of 4no. 2 bed units and 2no. 3 bed units; • A financial contribution of £38,210 towards secondary education, £2,484 towards childcare, £722 towards youth and £2,776 towards libraries; • A financial contribution of £28,000 towards the provision for traffic calming and safety enhancement measures and to promote sustainable transport measures; • A financial contribution of £5,100 towards Parks and Public Gardens, £13,250 towards Outdoor Sports Facilities and £2,295 towards Children and Young People; • 15% of the dwellings shall be constructed to ‘Lifetime Homes’ standard • The provision of fire hydrants.
That planning permission be GRANTED subject to the following conditions:
1. Three Year Time Limit (1T121)
2. Levels (2E051)
3. Samples of materials (2E123)
4. Obscured glazing (2E183)(insert:- flank elevation of plot 13)
5. Refuse disposal facilities (2E243)
6. No development shall take place until a Construction Method Statement has been submitted to, and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for: 3/11/1927/FP
• Methods for accessing the site; • The parking of vehicles of site operatives and visitors; • Loading and unloading of plant and materials; • Storage of plant and materials used in constructing the development; • The erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate; • Wheel washing facilities; • Measures to control the emission of dust and dirt during construction; • A scheme for recycling/disposing of waste resulting from demolition and construction works. Reason: To ensure that the construction works and associated activity are acceptable in terms of amenity of the area and highway safety.
7. Construction hours of working - plant and machinery (6N053)
8. No development shall take place until a scheme for the implementation of energy efficiency measures within the development to secure at least 10% of the energy supply of the development from decentralised and renewable or low-carbon sources, shall be submitted to and approved in writing by the Local Planning Authority, and thereafter implemented in accordance with the approved scheme, unless otherwise agreed in writing by the Local Planning Authority.
Reason: To ensure the development assists in reducing climate change emissions in accordance with policy ENG1 of the East of England Plan May 2008 and policy SD1 of the East Herts Local Plan Second Review April 2007.
9. No development shall take place until the following components to deal with the risks associated with contamination of the site have been submitted to and approved in writing by the Local Planning Authority: 3/11/1927/FP
• A preliminary risk assessment which has identified: all previous uses; potential contaminants associated with those uses; a conceptual model of the site indicating sources, pathways and receptors; potentially unacceptable risks arising from contamination at the site.
• A site investigation scheme, based on (1) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off site.
• The site investigation results and the detailed risk assessment (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Management Committee at East Hertfordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.