Strategy and Resources Committee, Tuesday 27 January 2026 at 7.30pm

Planned Maintenance Programme 2026-27

Noted Committee 3 papers

AI summaryEpsom and Ewell's Strategy and Resources Committee approved a £757,000 planned maintenance programme for 2026-27 covering Bourne Hall, Epsom Playhouse, CCTV and other council properties, funded mainly from the Planned Maintenance Reserve.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted2026-27 planned maintenance programme
Money£757,000 estimated costPlus up to £20,000 per change authorised
What happens nextProgramme to be delivered in 2026-27Unspent budgets to return to Reserve
Who it affectsCouncil property assets and tenantsIncludes libraries, leisure, depots, CCTV, allotments

What was decided

The Committee approved the 2026-27 planned maintenance programme at an estimated cost of £757,000, funded from the £230,000 annual budget and £527,000 from the Planned Maintenance Reserve. Report P7, 8.7

The Head of Property and Regeneration was authorised to vary the programme by up to £20,000 per change for unforeseen matters such as tender price variances. Report P8, 8.9

The Committee noted progress on 2025-26 works and additional emergency works carried out, with about £516,000 of the £535,000 budget forecast to be spent and £19,000 returned to the Reserve. Report P5, P6, 6.1, 6.2

Why

The programme is needed to protect council property assets, meet health and safety duties and provide fit for purpose working environments. Report 1.1

Works are either essential maintenance or required to meet statutory and commercial tenant lease obligations. Report P88, P89

Several projects are expected to reduce energy use and carbon emissions, supporting the council's climate priorities. Report 12.3, 12.4

What happens next

Officers will deliver the 2026-27 programme of works set out in Appendix 2, including ceiling, decoration, fencing, CCTV, electrical and regulatory works. Report 7.1, 7.2, 7.3, 7.5, 7.6, 7.7, P79, 8.1, 8.2, 8.3

Unspent budgets at the end of 2026-27 will be transferred back to the Planned Maintenance Reserve. Report P9

Quarterly forecasts will be produced to monitor the council's VAT partial exemption position through the year. Report 10.2

The money

  • £757,000 Estimated cost of 2026-27 planned maintenance programme Report P7, 8.7
  • £230,000 Standard annual planned maintenance budget for 2026-27 Report 8.7, 10.3
  • £527,000 Amount to be drawn from the Planned Maintenance Reserve in 2026-27 Report 8.7, 10.3
  • £20,000 Maximum value of each in-year change authorised for the Head of Property and Regeneration Report P8, 8.9
  • £535,000 2025-26 planned maintenance programme budget agreed on 28 January 2025 Report 2.1
  • £305,000 Maximum 2025-26 draw from Planned Maintenance Reserve (subject to actual spend) Report 2.2
  • £516,000 Forecast 2025-26 actual spend including commitments Report 6.1
  • £19,000 Forecast underspend in 2025-26 to be returned to the Reserve Report 6.2, P108
  • 375,597 Opening balance of Planned Maintenance Reserve at 1 April 2025 Report P106
  • 500,000 Transfer from Interest Equalisation reserve into Planned Maintenance Reserve in 2025-26 Report P110
  • 200,000 Budgeted contribution into Planned Maintenance Reserve in 2025-26 Report P111
  • 757,597 Forecast balance of Planned Maintenance Reserve as at 31 March 2026 Report P112
  • 230,597 Forecast balance of Planned Maintenance Reserve as at 31 March 2027 after 2026-27 programme Report 10.5

Options considered

  • Chosen: Approve the 2026-27 planned maintenance programme at £757,000 funded from the annual budget and the Planned Maintenance Reserve. Works are essential maintenance or needed for statutory and lease obligations, and the reserve has sufficient balance after a £500,000 transfer from the Interest Equalisation reserve. Report P7, 8.7, 8.8, P88, P89, P110
  • Chosen: Authorise the Head of Property and Regeneration to make in-year changes of up to £20,000 per change. Allows the programme to absorb tender price variances and unforeseen matters without returning to committee, subject to Financial Regulations and Contract Standing Orders. Report P8, 8.9
  • Chosen: Transfer any 2026-27 unspent budget back to the Planned Maintenance Reserve at year end. Consistent with the reserve's purpose of smoothing over and underspends between years. Report P9, 6.2

Implications

  • Financial: The 2026-27 programme is £527,000 above the £230,000 annual budget and will be funded from the Planned Maintenance Reserve, which is forecast to fall to about £230,597 by 31 March 2027 after a £500,000 top-up transfer in 2025-26. Report 10.3, 10.4, 10.5, P110, P112
  • Financial: Works will be monitored quarterly to avoid breaching the council's 5% VAT partial exemption limit. Report 10.2
  • Legal: The Legal Officer identified no legal implications arising from the report. Report 11.1
  • Equalities: Various works affect operational buildings; impact will be managed to minimise disruption, with no specific equality impact assessment flagged. Report 9.1
  • Climate: Several projects (LED lighting, energy efficiency meters, air source heat pump preparation at Bourne Hall) are expected to reduce energy use and carbon emissions. Report 12.3, 12.4, 4.3, 7.2
  • Risk: Concrete repairs at Ashley Centre are required to prevent spalling concrete posing a health and safety risk to the public and vehicles. Report 7.14
  • Risk: CCTV upgrades are needed to maintain compliance with GDPR because many existing analogue systems have poor picture quality. Report 7.7
  • Other: The council remains under a statutory Best Value duty to maintain fit for purpose properties until Local Government Reorganisation Vesting Day on 1 April 2027. Report 12.6

Who and where

  • Bourne Hall users and staff, including Library offices, due to asbestos ceiling removal, external decoration and spiral staircase works Report 7.2, 7.3
  • Epsom Playhouse visitors and hirers, with Myres studio redecoration, upper bar toilet upgrade and fire alarm alterations Report 7.11, 7.12, 7.13
  • The tenant of 92 High Street (commercial property), with damp investigation and redecoration timed to the March 2026 lease expiry Report 7.5
  • Allotment users, with fencing inspections and repairs across the council's allotment sites Report 7.6
  • The public using the Ashley Centre, due to concrete repairs to de-bonding and spalling areas Report 7.14
  • Longmead Depot staff and Community and Wellbeing Centre users, with external decorations Report 7.8, 7.9
  • Council staff at the Epsom Clock Tower, with clock mechanism repairs and external jet washing Report 7.10
  • Residents and visitors benefiting from CCTV, hard surface, wall and fence safety repairs across the borough Report 7.7, 7.15

Timeline

  • 28 January 2025: Previous committee approved the 2025-26 planned maintenance programme at £535,000 Report 2.1, P126
  • 1 April 2025: Opening balance of the Planned Maintenance Reserve was 375,597 Report P106
  • During 2025-26: Emergency works completed at Beaconsfield Wall, Bourne Hall Banqueting Suites, Epsom Playhouse dimmer room cooling, Bourne Hall reception blinds and Stonieleigh Parade Garages Report 5.1, 5.2, 5.3, 5.4, 5.5
  • 27 January 2026: Committee approved the 2026-27 programme and authorised officer variations up to £20,000 per change Report P7, P8
  • During 2026-27: Programme of planned maintenance, regulatory and emergency works to be delivered Report 7.1, 7.2, P79
  • End of March 2026: 2025-26 financial year ends, with forecast spend of around £516,000 and £19,000 returned to the Reserve Report 6.1, 6.2, P108
  • 31 March 2026: Forecast balance of Planned Maintenance Reserve stands at 757,597 Report P112
  • 31 March 2027: Forecast balance of Planned Maintenance Reserve falls to 230,597 after the £527,000 draw Report 10.5
  • 1 April 2027: Local Government Reorganisation Vesting Day; council remains under Best Value duty until this date Report 12.6

Plain English for the jargon

  • Planned Maintenance Reserve: An earmarked council reserve used to smooth over and underspends on the annual planned maintenance programme between years.
  • LGR Vesting Day: The date on which Local Government Reorganisation takes effect, here 1 April 2027, after which the council's continuing maintenance duty may change.
  • VAT partial exemption limit: A 5% cap on the proportion of VAT a local authority can recover on exempt activities; the council monitors this so large works do not push it over the limit.
  • GDPR: General Data Protection Regulation, the data protection rules requiring the CCTV upgrade.
  • Building Safety Act: Legislation effective from March 2022 that requires annual fire risk assessments and related works cited in the programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item46

Resolved

Following consideration, the Committee unanimously resolved: (1) To note the progress and anticipated spend at the end of the current year 2025-26 as shown in Appendix 1 to the report. (2) To note the additional emergency works raised and carried out in the 2025-26 planned maintenance programme. (3) To approve the 2026-27 planned maintenance programme at an estimated cost of £757,000 as set out in Appendix 2 to the report, to be funded from planned maintenance budgets and the Planned Maintenance Reserve. (4) To nominate and authorise the Head of Property and Regeneration to make changes within the 2026-27 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000 per change, in accordance with Financial Regulations and Contract Standing Orders. (5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the 2026-27 financial year.
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Strategy and Resources Committee

Summary

This report provides:

 a progress update on the current (previously approved) financial year 2025-26 planned maintenance programme;

 and requests approval for next year’s planned maintenance programme for the financial year 2026-27.

Recommendation (s) The Committee is asked to:

(1) To note the progress and anticipated spend at the end of the current year 2025-26 as shown in Appendix 1.

(2) To note the additional emergency works raised and carried out in the 2025- 26 planned maintenance programme.

(3) To approve the 2026-27 planned maintenance programme at an estimated cost of £757,000 as set out in Appendix 2, to be funded from planned maintenance budgets and the Planned Maintenance Reserve.

(4) To nominate and authorise the Head of Property and Regeneration to make changes within the 2026-27 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000 per change, in accordance with Financial Regulations and Contract Standing Orders. Strategy and Resources Committee 27 January 2026

(5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the 2026-27 financial year.

Reason for recommendation

1.1Ensuring the Council’s property assets are protected and maintained is essential in meeting its health & safety obligations and providing fit for purpose working environments.

Background

2.1At its meeting on 28 January 2025, this Committee agreed to fund the planned maintenance programme in the sum of £535,000.

2.2This figure is formed from the £230,000 given this year to fund the planned maintenance, with the remainder of up to £305,000 (dependent on actual spend) taken from the Planned Maintenance Reserve.

2.3It should be noted that the budgets were derived in December 2024 and the following spend analysis (against last year’s budget) takes account of forecasted expenditure up to the end of March 2026 i.e. over one year later.

3 Update on 2025-26 planned Maintenance Works (Appendix 1)

3.1Horton Country Park Workshop & Boxing Club asbestos roof replacement - deferred from last year as limited resources prevented it being undertaken last summer. This year, the budget was increased to allow for a temporary roof to protect equipment in the Boxing Club and Lower Mole Workshop while the work proceeded. Additional works were required to remove power cables fixed to the underside of the roof and additional support provided to the ridge area to strengthen the roof structure.

Budget £140,000 Spend £147,000 Work completed

3.2Epsom Playhouse replacement air conditioning to auditorium – following discussions with a specialist consultant, a new design was proposed which incorporates cooling to the air handling units and new quiet air conditioning system. The revised proposal cost far exceeds the original £40k approved budget and a Capital Bid has been submitted for next financial year 2026-27. £9k has been spent on the revised design with future spend paused pending outcome of Capital Bid.

Budget £40,000. Spend £9,000 Awaiting Capital Bid

3.3Epsom Playhouse Internal redecoration to foyer and additional lights - carried out in August 2025 (theatre shut down period) and completed with additional lighting and new feature pendant light in foyer. Strategy and Resources Committee 27 January 2026 Budget £30,000 Spend £29,000 Work completed

3.4Alexandra Recreation Ground main pavilion internal redecoration - decorations were carried out to changing rooms, toilets and external windows and to the front elevation.

Budget £15,000 Spend £6,000 Work completed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planned Maintenance Programme 2026-27 Appendix 1Appendix 234 KB Download
PDF
Planned Maintenance Programme 2026-27 Appendix 2Appendix 215 KB Download
PDF
Planned Maintenance Programme 2026-27Report 363 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
ND
Councillor Neil Dallen MBEChair, present
HD
Councillor Hannah DaltonVice-Chair, present
CA
Councillor Chris AmesCommittee Member, present as substitute
JB
Councillor John BeckettCommittee Member, present
KC
Councillor Kate ChinnCommittee Member, apologies, sent representative
JL
Councillor James LawrenceCommittee Member, present
JM
Councillor Jan MasonCommittee Member, apologies
LM
Councillor Lucie McIntyreCommittee Member, present
HR
Councillor Humphrey ReynoldsCommittee Member, present
AC
Councillor Alex ColeyCouncillor in Attendance, in attendance
CC
Cagdas CanbolatOfficer, in attendance
PI
Piero IontaOfficer, in attendance

All 18 on the meeting page

On this subject at Epsom and Ewell

Search all
  1. Planned Maintenance Programme 2026-27This decision
  2. Planned Maintenance Programme 2025-26Noted
  3. Planned Maintenance Report 2024-25Noted
  4. Planned Maintenance Programme 2023-24Noted
  5. Planned Maintenance Programme 2022-23Noted
  6. Planned Maintenance Programme 2021-22Agreed

More from Epsom and Ewell Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
10 Nov 2026 Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... Noted Open
10 Nov 2026 Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report Noted Open
10 Nov 2026 Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... Agreed Open
10 Nov 2026 Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... Agreed Open
10 Nov 2026 Urgent DecisionFollowing consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies