Following consideration, the Committee unanimously resolved: (1) To note the progress and anticipated spend at the end of the current year 2024-25 as shown in Appendix 1 to the report. (2) To note the additional emergency works raised and carried out in the 2024-25 planned maintenance programme. (3) To approve the 2025-26 planned maintenance programme at an estimated cost of £535,000 as set out in Appendix 2 to the report, to be funded from planned maintenance budgets and the Planned Maintenance Reserve. (4) To nominate and authorise the Head of Property and Regeneration to make changes within the 2025-26 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000 per change, in accordance with Financial Regulations and Contract Standing Orders. (5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the 2025-26 financial year.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The Report provides an update on the current financial year’s approved 2024-25 planned maintenance programme and requests approval for the planned maintenance programme for the next financial year 2025-26.
Recommendation (s) The Committee is asked to:
(1) To note the progress and anticipated spend at the end of the current year 2024-25 as shown in Appendix 1.
(2) To note the additional emergency works raised and carried out in the 2024- 25 planned maintenance programme.
(3) To approve the 2025-26 planned maintenance programme at an estimated cost of £535,000 as set out in Appendix 2, to be funded from planned maintenance budgets and the Planned Maintenance Reserve.
(4) To nominate and authorise the Head of Property and Regeneration to make changes within the 2025-26 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000 per change, in accordance with Financial Regulations and Contract Standing Orders.
(5) To agree to transfer the unspent budgets back to the Planned Maintenance Reserve at the end of the 2025-26 financial year. Strategy and Resources Committee 28 January 2025 1 Reason for Recommendation
1.1Ensuring the Council’s property assets are protected and maintained is essential in meeting its health & safety obligations and providing fit for purpose working environments.
Background
2.1At its meeting on 26 March 2024, this Committee agreed to fund the planned maintenance programme in the sum of £562,000.
2.2This figure is funded from the £230,000 budgeted each year to fund the planned maintenance, with the remainder of £332,000 taken from the Planned Maintenance Reserve.
2.3It should be noted that the budgets were derived in February 2024 and the following spend analysis (against last year’s budget) takes account of forecasted expenditure up to the end of March 2025 i.e. one year later.
3 Update on 2024-25 planned Maintenance Works (indicated in Appendix 1)
3.1Beaconsfield Wall reinstatement (60k)– tender costs received at £35,000 with all drawings and listed building submissions carried out by the in- house team, saving the need for additional consultant cost. Listed Building consent was received in November 2024. The restoration works may be delayed as work cannot be undertaken in lime mortar (a Listed Building requirement) below 5 degrees. Forecast spend £35,000.
3.2Various council buildings - collapsed drains at King Georges field (20k) creating hazards on football pitch required repair. Forecast spend £20,000.
3.3Horton Country Park workshop & Boxing Club asbestos roof replacement (£110k). After discussion with occupiers, a temporary roof will be required while reroofing is underway. This work is programmed for Summer 2025. Forecast spend £nil.
3.4King Georges Field, Poole Road Pavilion – to replace air handling in roof (£20k). Subsequent inspections revealed that the existing plant is salvageable and therefore only minor repairs and new controls at a reduced cost were carried out. Forecast spend £5,000.
3.5Upper Mill Pond - remove silt storage ponds and level grounds (£10k). The fencing was removed, and all excess materials reused by grounds maintenance team including the silt. Over time, this will form topsoil for planting use around the Borough. Forecast spend £4,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.