Following consideration, the Committee unanimously resolved: (1) To note the progress and anticipated spend at the end of the current year 2021-22 as shown in Appendix 1 to the report. (2) To note the two projects and budgets carried over into 2021-22 planned maintenance programme. (3) To approve the 2022/23 planned maintenance programme at an estimated cost of £498,000 as set out in Appendix 2 to the report. (4) Subject to the Council’s financial and contract requirements, to delegate authority to the Head of Property and Regeneration to make changes within the 2022/23 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000. (5) To agree to transfer the unspent budgets back to the planned maintenance reserve at the end of the financial year.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The report provides an update on the approved 2021-22 planned maintenance programme and requests approval for the planned maintenance programme for the next financial year 2022-23
Recommendation (s) The Committee is asked to:
(1) To note the progress and anticipated spend at the end of the current year 2021-22 as shown in Appendix 1.
(2) To note the two projects and budgets carried over into 2021-22 planned maintenance programme.
(3) To approve the 2022/23 planned maintenance programme at an estimated cost of £498,000 as set out in Appendix 2.
(4) Subject to the Council’s financial and contract requirements, to delegate authority to the Head of Property and Regeneration to make changes within the 2022/23 planned maintenance programme to cover unforeseen matters (such as tender price variances) of up to, but not exceeding £20,000.
(5) To agree to transfer the unspent budgets back to the planned maintenance reserve at the end of the financial year.
1 Reason for Recommendation Strategy and Resources Committee 29 March 2022 1.1 The proposed planned maintenance programme is essential to meet the Council’s health & safety obligations and undertake essential maintenance to provide fit for purpose working environments and protect property assets.
Background
2.1At the meeting on the 28th January 2021, Strategy and Resources Committee agreed to fund the planned maintenance programme for 2021/22 totalling £315,000.
2.2This figure is formed from the £210,000 allocated each year to fund planned maintenance, with the remainder of £105,000 taken from the Property Maintenance Reserve.
3 2021/22 Update
3.1Funds totalling £65,000 were also carried over in the Property Maintenance Reserve from the previous financial year for the following two projects which were not completed in 2020-21. They comprise:
3.1.1 The Ashley Centre car park staircase redecorations, roof repairs and floor paint. Due to the contractor carrying out the redecoration works at the end of 2020, the temperatures were not favourable which led to poor paint adhesion to the floors and walls. The contractor had to return to clean off and repaint in May/June 2021 and therefore, the project timescale had to be extended. The cost of works was £45,000.
3.1.2 The Ewell Court House library window replacement had to be deferred as contractors expressed little interest in undertaking the works. The windows were removed in the summer and sent off for remanufacture. The project has experienced a serious delay due to Covid forcing the joinery factory to shutdown numerous times. The works were complete by December 2021 at a cost of £18,000.
3.2The Bourne Hall works to replace light fittings to the Main Hall, corridors and banqueting suites will be carried forward to next year 2022-23. This is due to workload capacity and the need to seek expert mechanical and electrical advice. The budgeted cost for these works is £30,000.
3.3The remainder of the planned maintenance programme has been delivered with savings being made from effective project management, tendering and specification writing which can be returned to the Council’s reserves.
3.4The detail of the projects and costs is shown in appendix 1. Strategy and Resources Committee 29 March 2022 3.5 At the time of writing this report, a net underspend of £94,000 is projected on 2021-22’s programme, as shown in Appendix 1. It is proposed to return the £94,000 back to the planned maintenance reservesfor future years use which would bring the uncommitted reserve balance at 31 March 2022 to £537,000.
4 Funding from Surrey County Council (SCC)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.